Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

1

Scheduling Techniques in Projects

Lecture-5 Line of Balance Method

Dr. J. Uma Maheswari


Associate Professor
Department of Civil Engineering
umapaul@civil.iitd.ac.in
2

Lecture-5 Line of Balance Method


 Repetitive projects

 LoB – Critical Path


3

Linear projects
 Linear projects are projects involving repetitive
activities
– Vertically linear (typical floors in a building)
– Horizontally linear (highway, pipeline, etc.)
 Several names available
– Construction Planning Technique (CPT)
– Vertical Production Method (VPM)
– Time- Location Matrix Model
– Time Space Scheduling Method
– Time Versus Distance Diagrams
– Linear Balance Charts
– Velocity Diagrams or
– Linear Scheduling Method (LSM)
4
LoB
 History
 It is widely used in the construction industry for the
execution of repetitive projects such as mass
housing, high-rise buildings, tunnels, highways, etc.
 LOB representation
4

3
Units

2 F

1
0 5 10 15 20 25
Days
5

Case Example 1
No Activity Activity ID Duration IPA
(days)
2 Brickwork –T1 B1 90
3 Joinery Works – T1 J1 75 2FS
4 Flooring Works – T1 F1 90 3FS
5 Painting Works – T1 P1 80 4FS
6 Brickwork –T2 B2 90 2FS
7 Joinery Works – T2 J2 75 3FS, 6FS
8 Flooring Works – T2 F2 90 4FS, 7FS
9 Painting Works – T2 P2 80 8FS, 5FS
6

CPM vs. PDM vs. LoB


B1 J1 F1 P1
90 75 90 80
CPM

B2 J2 F2 P2
90 75 90 80

LOB
90
B J
180 150
75

PDM
7

Assumptions in LoB
 The logical CPM/PDM network of each unit
is maintained
 Crews’ work continuity is retained

Single parallel staggered Typical vs. Non-typical


CREW CONTINUITY
8

LOB – Buffer
4

3 A
B
C
Units

E
F
2 G
H
I

1
0 5 10 15 20 25 30

Days
Example 1 Interior of 4 class rooms
Activity Description Dur Dur IPA
ID (hrs) (day)
A Floor level marking 4 0.5 -
B Fixtures for roof panels and AC ducts 8 1 A
C Internal wiring 16 2 B
D Pipe laying for sprinklers 8 1 B
E Fixing roof panels 24 3 C, D
F Fixing wall panels 24 3 E
G Flooring 24 3 F
H Painting and finishing 16 2 G
I Electrical fixtures 8 1 H

 Duration for each activity – single crew


 Buffer – 0.5 days between each activities
PDM Network for one unit

2.5 C 4.5
2.5 2 4.5
0.5 0.5

0 A 0.5 1 B 2 5 E 8 8.5 F 11.5


0 0.5 0.5 0.5 1 1 2 5 3 8 0.5 8.5 3 11.5
0.5 0.5
2.5 D 3.5
3.5 1 4.5

0.5
12 G 15 15.5 H 17.5 18 I 19
12 3 15 0.5 15.5 2 17.5 0.5 18 1 19
Schedule for four rooms (n =4)
Dur Buffer Time for Scheduled start date
ID IPA (days) Type Dur (n-1) units 1st unit 4th unit
A - 0.5 - 1.5 0 0 + 1.5 = 1.5
B A 1 Start 0.5 3 0 + 0.5 + 0.5 = 1 1 + 3 = 4
C B 2 Start 0.5 6 1 + 1 + 0.5 = 2.5 2.5 + 6 = 8.5
D B 1 Start 0.5 3 1 + 1 + 0.5 = 2.5 2.5 + 3 = 5.5
E C, D 3 Start 0.5 9 2.5 + 2 + 0.5 = 5 5 + 9 = 14
F E 3 Start 0.5 9 5 + 3 + 0.5 = 8.5 8.5 + 9 = 17.5
G F 3 Start 0.5 9 8.5 + 3 + 0.5 = 12 12 + 9 = 21
H G 2 End 0.5 6 24.5 - 6 = 18.5 21 + 3 + 0.5 = 24.5
I H 1 End 0.5 3 27 - 3 = 24 24.5 + 2 + 0.5 = 27
Total duration = 27 +1 = 28 days
Start date
ID dur 1st unit 4th unit
LoB Diagram (only critical) A 0.5 0 1.5
B 1 1 4
C 2 2.5 8.5
D 1 2.5 5.5
E 3 5 14
F 3 8.5 17.5
4
G 3 12 21
H 2 18.5 24.5
I 1 24 27
3 A
B
Units

C
2 E
F
G
1
H
0 5 10 15 20 25 30
I
Days
LoB Diagram (all activities)
4

3
B
C
Units

E
F
2 G
H
I
D
1
0 5 10 15 20 25 30

Days
LoB Diagram (all activities)
15

Unit-based and Non-unit based


 Most repetitive scheduling methods
available so far are assumed of identical
sub-units in the identified units of repetition.
– Unit-based repetitive projects
– Non-unit-based repetitive projects
TYPICAL CROSS SECTIONS

Existing
carriageway

Left side widening


Right side widening Existed
central line

Proposed
central line

Concentric widening New


carriageway
Left side widening with
service road
17

Different capacity lecture rooms


18

Different capacity lecture rooms


19

Different capacity lecture rooms

You might also like