Professional Documents
Culture Documents
Engineering Management 3000/5039: Tutorial 2 - Solutions
Engineering Management 3000/5039: Tutorial 2 - Solutions
Engineering Management 3000/5039: Tutorial 2 - Solutions
TUTORIAL 2 - SOLUTIONS
A1// Total
= Direct Direct
Manufacturing + + Direct
Labour material Manufacturing
Cost for 500 units Overhead
=5 hrs/unit × $22 × 500 + $40 per unit × 500 + 0.4 × (5 × 22 × 500) = $97,000
Giving a total revenue value required by selling the additional 500 units of:
The Unit price for 500 items is $121,250/500 = $242.5 per unit
(b) Since we have a total of 2500 widgets the Unit CM is given by:
Unit Contribution Margin = (Total CM) / (Number of widgets)
(c)
Profits = Revenue - Total Cost
Profits = Revenue – [Fixed Costs + Variable Cost ]
Thus
Net operating profit = $4 x 2500 – ($2,000 + $500) – ($4000 + $1000)
Net operating profit = $2,500
Profit = Revenue – Total Costs (Note no fixed costs are given so fixed cost = $0)
Assignment of costs
Work in progress 1:
Direct material cost (for 100 units) $100,000
(100 x $1000)
Conversion cost (50% units) $30,000
(100 x 600 x 50%)
Total work in progress 1 $130,000
Work in progress 2:
Direct material cost (100 units) $100,000
(100 x $1000)
Conversion cost (50 units 25% completed) $7,500
(50 x 600 x 25%)
Total cost (based on completed units)= $1,517,500/ 800 = $1896.88 per unit
NOTE: When we say that "100 units are in production and conversions are completed by 50%",
means that only 50% of the 100 units have been converted and completed.
Only 800 units are totally complete, on the shelf and ready for sale. The other units are considered
still incomplete as they are still in the production phase and are not yet ready for sale and have not
yet been packaged.
c) For a better profit, choose the product mix which contains more of the product that has
a higher contribution margin.
Selling price - Variable cost per unit A = 20 -10 = $10 per unit
CMA =
per unit A
CMB per $4
= 0.25 hrs per unit B = $16 per hour
machine hour
Product A is more profitable per hour of machine time, thus A should be produced more
than B. Choose product mix of 4A to 3B.
B=0.75A
For every 4 items of A sold 3 items of B sold. i.e. B=0.75A
also
For every 3 items of A sold 5 items of C sold. i.e. A=0.6C
a) At breakeven point:
Total revenue = Total cost = Total Fixed Cost + Total Variable Cost
d) Determine which would be the more profitable product mix from the list
below:
Product mix1 A:B:C = 10:9:9 Profit = 10*10 + 9*8 + 9*3 = $199 profit / mix1
Product mix2 A:B:C = 9:10:9 Profit = 9*10 + 10*8 + 9*3 = $197 profit / mix2
Product mix3 A:B:C = 9:9:10 Profit = 9*10 + 9*8 + 10*3 = $192 profit / mix3
Product mix4 A:B:C = 9:9:9 Profit = 9*10 + 9*8 + 9*3 = $189 profit / mix4
As product A has the highest CM, Mix 1 is the most profitable since it has the greater
quantity of product A in the mix.
= 192 x $600
= $115,200
Even though it costs the company less on a per unit basis to manufacture a batch of 2000 units
compared to 1000 units (i.e. $174/unit1000 compared to $111/unit2000 ) and the per unit
contribution margin is greater for the batch of 2000 (CM2000= $512 /unit ) compared to the
batch of 1000, (CM1000= $482 /unit), the company may be reluctant to make a batch of 2000
units.
Why?, because it may require some form of upgrade or expansion to the existing plant to
accommodate the increased volume of product. If this is the case and it is a one off request it
might not be worth the company doing this as they will not recover the additional cost for the
upgrades required. However if this is possibly one of may orders of this size or greater, then
long term the upgrade costs can be recovered. This is a management decision.
However, in this example the company should proceed with the manufacture of the 2000 unit
batch. We can see the economy of scale in action in this example, since the fixed
potion of the costs remained constant for both orders of 1000 and 2000 units.
Meaning the management didn't have to spend more money upgrading existing plant to
accommodate the order.