Professional Documents
Culture Documents
Bath Refractory Installation Specification
Bath Refractory Installation Specification
CVD CONVERSION
BATH REFRACTORY
INSTALLATION SPECIFICATION
JANUARY 2019
This document, and all copyright in it, is the property of NSG Group Limited, and
its contents shall not be reproduced in whole or in part without the consent of
NSG Group Limited.
Neither NSG Group Limited nor any other member of the Group shall accept any
liability in respect of any claims, whether by the recipient or any third party,
arising out of or in connection with any use of this document or any of the
technical data or information contained herein or of any advice furnished in
connection herewith.
DOCUMENT HISTORY
CONTENTS
1. INTRODUCTION 4
2. SAFETY 4
3. CONTRACTOR RESPONSIBILITY 4
3.1 General 4
3.2 Scope of Works 5
3.3 Manpower 6
3.4 Program 6
3.5 Contractor co-operation 7
3.6 Site Cleanliness 7
3.7 Equipment 7
3.8 Materials 7
3.9 Damage to Refractory 8
3.10 Handling, Delivery to Site and Storage 8
6. OTHERS 16
NSG Group Copyright Confidential
1. INTRODUCTION
The description of this document gives the program of works related to Tin bath
installation which must be met, or improved on. And it is the contractor’s
responsibility to ensure that they fully understand their scope of works. They can
contact the engineer if they are unsure of any aspects of the scope (see contact
details below Chapter 6). It is also assumed that the contractor fully understands
their scope of works when their offer is received.
2. SAFETY
The contractor must observe the VGI3 site health and safety policy which is
provided in separate sheet.
VGI3 Conversion
Project Site Health and Safety Rules R01.docx
Safety equipment such as helmet, long-sleeve shirt, safety shoes, safety goggles
and reflective jacket is required to wear. Instep protector and dust mask etc. will
be required for refractory handling work.
3. CONTRACTOR RESPONSIBILITY
The contractor has the following responsibilities and requirements, these are set
out below.
3.1 General
4
NSG Group Copyright Confidential
Making good to existing work, work done under other contracts or work
under the contract, which the contractor disturbs or otherwise affects
by the performance of their work. The affected work shall be made
good by the contractor, at his own cost, in every trade, to match the
adjacent work to the satisfaction of the engineer.
Coordinating the execution of the work under the contract with the
work of other contractors working in the immediate location of the work
under the contract in a manner that will allow them access to the areas
in which they are required to perform work, and which will ensure that
there will be no interference with, nor interruption of, the work of other
contractors.
3.3 Manpower
3.4 Program
Following is the existing program but not decided the exact date.
6
NSG Group Copyright Confidential
The contractor should allow in his offer for any necessary overtime to
complete the work to the program. For the installation program see
employer’s requirements section 5.
The contractor must ensure that the construction site is tidy at the end
of each working day. And the contractor must ensure the cleanliness
when NSG required.
3.7 Equipment
NSG (VGI) will supply the equipment below for the necessary brickwork.
Compressor air is not included in the supply, so contractor should prepare
their own if necessary.
Electric supply
AC380V, 50HZ (3phase + Neutral)
NSG supply primary cable to the each distribution board. The contractor
should use own distribution board and not use local site connector.
Water supply
Overhead crane (5 ton), common use
Hoist crane (3 ton) at RHS Bay1, common use
Stud welding equipment
The contractor should make the list and submit to NSG of their equipment.
And also the contractor must have available, on site, any relevant test or
inspection certificates for their equipment, such certificates to be provided
to the engineer if requested. Electric, water supply and other site condition
is referred in the separate sheet.
3.8 Materials
The NSG engineer should approve all materials provided and used by
the contractor necessary to carry out the installation equipment
required.
7
NSG Group Copyright Confidential
Refractory shall be handled and stored by methods and appliances that will
not damage them.
Pallets with refractory shall not be stacked more than three high.
All refractory and cements shall be stored under cover and kept dry.
Refractory and cements shall be stacked clear of floor and any "lying"
water.
8
NSG Group Copyright Confidential
4.2 Terminology
Canal
The connection between the furnace and the Bath.
Bath
A refractory-lined steel casing in which the molten glass floats on a bed
of molten tin.
Section 0
The front taper section of the Bath before the first bath column.
Shoulder
The transition of the bath from the wide end to the narrow end. It is
the tapered section half way down the length of the Bath.
Exit End
The point of the bath at the end of the narrow end where the glass
ribbon is transferred to rollers and enters the LEHR.
Bay
The bath bottom casing is split into a number of sections, these are
called bays. Each bay is 10 feet (3048mm) in length. Bay markings will
be indicated on the side of the bath roof
Bath Roof
The roof of the bath is a suspended steel and refractory construction. It
is independent of the bath bottom casing.
4.3 General
4.3.1 Datums
9
NSG Group Copyright Confidential
Bath bottom blocks and roof bricks will be handled in accordance with the
methods outlined in the VGI3 conversion specifications.
The contractor will be responsible for supplying any necessary tools and
equipment required for the refractory installation, except as specifically
detailed in the remainder of this specification.
The following is a typical list of tools and equipment that the contractor
must supply if required. This list is intended for guidance only, and must
not be taken as a full and final list of all equipment to be provided by the
contractor. The contractor must satisfy himself that he has the required
tools available before commencing work on site.
(a) Temporary lighting with guide and code reel with shock prevention
(b) Rubber mallets (large)
(c) Wooden wedges
(d) Cloth lifting slings (min. 1 ton capacity)
(e) 1 meter & 500mm long precision spirit levels
(f) Tommy bar
(g) Optical leveling equipment and qualified operator
(h) Portable industrial vacuum machine
(i) Air compressor for ramming equipment
(j) Soft bristle brushes (long and short handle)
(k) Fine mesh sieve for cement
(l) Cement mixer (with unused drum and paddle)
(m) Saw for insulation refractory cutting
(n) Wooden centers for support of front and exit lintels
(o) 12mm thick plywood (NOT chipboard) (approx. size is 1000mm x
500mm) – for protection of all the bottom blocks and side blocks
(p) General bricklaying tools. It includes block trolley (overhead monorail)
(q) Temporary timber supports as required
(r) Heavy duty polythene sheet to cover complete bath bottom block area
- area approx. 400m2
(s) Temporary timber protection at hot end area to prevent damage
(t) Temporary plywood sheeting to bath sides when roof sections raised
(u) Ramming guns and spare ramming tools. Torque testing tools and
auxiliary equipment
10
NSG Group Copyright Confidential
The contractor has to carry out all kind of works to import/export own tools.
NSG don’t have any responsibility tax, carnet, recipient, etc.
Other equipment which use the electric, air or water should be supplied the
necessary specifications.
Bath center line, 1st station line and Bay end line will be provided by
steelwork contractor, but other datums (e.g. around restrictor area or
around exit lip) should be prepared by the contractor.
The contractor will provide a suitably qualified welder to carry out the stud
welding for fixing the blocks to the casing and all other labour required for
the installation, fixing, torque testing, ramming, and grouting (cement
between side blocks and steel casing) of the bath blocks. The stud welding
equipment will be supplied by NSG (VGI).
After installation of blocks it should be checked all bottom block level again
to satisfy the target block level, then the contractor is responsible for
cleaning and covering the blocks with protective layers of tape (on the
expansion joints), polythene and plywood as detailed in the equipment list
above to prevent damage or contamination to bath structure.
Installation of the bath roof refractory and roof side wall will be done by
the contractor supervised by a contractor’s supervisor and a NSG engineer.
The roof refractory will be assembled in accordance with the NSG (VGI)
plant constructional specification.
The bath roof refractory support hangers, heater elements, busbar and
aluminium cables will also be installed by the contractor supervised by a
contractor’s supervisor and a NSG engineer. Roof sidewall support brackets
will be installed by the steelwork contractor.
11
NSG Group Copyright Confidential
NSG (VGI) will in charge of all related area at Spout & Lip. The
contractor has no responsibility in this area.
NSG (VGI) will assemble the Spout & Lip and install the new assembly.
For the setting of spare Spout & Lip is also performed by NSG (VGI).
NSG (VGI) will also install the new front tweel, flat arch and sealing
assemblies.
Spread section is the area from the front of the bath to the parallel
section including the end of Bay 1.
The contractor is to install the bottom and side blocks for all spread
section which includes Section 0, and includes the fused cast alpha-beta
alumina restrictor assembly as shown in appendix 1.
NSG will supply of all the replaced bottom and side blocks.
The contractor is to install the bottom and side blocks from Bay 2 to
Bay 6 and Bay 10 as shown in appendix 1.
NSG will supply of all the replaced bottom and side blocks. The
standard bottom blocks are available to replace any wide section until
Bay 10, excluding at the barrier position.
To install the last row, it should be measured the actual length and
required to cut from the standard block to fit this length.
NSG will supply of all the replaced bottom and side blocks.
The contractor is to install the bottom and side blocks from Bay 12 to
Bay 16 and at exit end as shown in appendix 1.
NSG will supply of all the replaced bottom and side blocks.
The stud welding equipment and torque testing equipment will be provided
by NSG (VGI). The contractor must provide a suitably qualified welder to
operate the stud welding equipment.
The gap between the bath casing sidewall and side blocks will be filled
throughout the bath where new blocks are installed. The bottom of the gap
should first be sealed with a layer of ramming cement to prevent seepage
under the blocks and then filled with grouting cement. Note the
requirement for any block surfaces which will be in contact with grouting
cement to be coated with water repellent prior to installation.
13
NSG Group Copyright Confidential
5.2.8 Others
The contractor should provide a rate for installation of bottom blocks per
block, per row and per bay in the wide, shoulder and narrow section (not
including side blocks). This rate may be used to increase or decrease the
final value of blocking work and should also include all fixing requirements
described above.
The contractor must work closely with the steelwork contractor who is
responsible for the roof steelwork such as setting of top cover plates. The
onus is on the contractors to ensure the agreed programme is adhered to.
Before roof installation work, roof casing should be once lowered to the
appropriate height for installation work by the contractor. (about
300mm higher than original height). Main purpose of this casing
lowering is to execute the refractory installation work from bath inside
with safely proper height and minimize to install the refractory from top
of the roof casing.
About 20% of roof refractory are new, and remained are the salvaged
refractory. Care should be taken when install the salvaged refractory
not to drop and make damage.
14
NSG Group Copyright Confidential
New busbars, aluminium cables and cable cleats for new heating zone
(from Bay1 to Bay 3 and from Bay 10 to Bay16) should be installed by
the contractor. These busbars and aluminium cables are newly supplied.
Refer appendix 6.
Heater element installation work should be done with two workers, one
is from top of the roof casing and the other from inside the casing. This
work should be carried out after the roof casing is lowered to original
(drawing) height.
All the heater elements from Bay 10 is the longer type (longer at above
plug brick), so it should be cared not to be broken the elements when
install the element and connect with cable. Refer appendix 5 for the
longer type element area.
The contractor will install the roof side wall from casing section 1 to
casing 3 at LHS and to casing 4 at RHS. These areas are already
removed so removal work is not included in this scope.
The contractor will install the roof side wall from casing section 12 to
casing 18. These areas are already removed so removal work is not
included in this scope.
15
NSG Group Copyright Confidential
5.3.8 Others
6. OTHERS
If additional or detail drawings is necessary to resolve any other queries including
content of this documents, contact person will be as follows.
Kazuyuki Kogamo
e-mail : Kazuyuki.Kogamo@nsg.com
Isao Takahashi
e-mail : Isao.Takahashi@nsg.com
16
NSG Group Copyright Confidential
17
NSG Group Copyright Confidential
18
NSG Group Copyright Confidential
19
NSG Group Copyright Confidential
20
NSG Group Copyright Confidential
21
NSG Group Copyright Confidential
22
NSG Group Copyright Confidential
ITEMS
1. Bottom installation
*Design and Installation of bottom blocking trolley
*Making the datum line
*Transportation of new blocks from warehouse to beside bath
*Unpack new blocks and put each blocks to wooden pallets
*Putting in the new blocks from beside bath to inside the bath
*Cutting carbon felt and set under the block
*Bottom block and side blocks Installation
*Making record of shims
*Measurement and making record of bottom block level
*Cutting bottom blocks to adjust length
*Stud welding
*Torque checking
*Transportation of necessary material from warehouse to beside the bath
*Ramming the mortar and cement
*Installation of carbon fiber, washer and nut
*Protection of bottom blocks including cleaning gaps, taping gaps
*Protection of new blocks area including sideblocks
*Transportation of empty pallets and box to warehouse
*Tidy up waste packing material (vinyl, pp band, polystyrene, etc)
ITEMS
2. Roof casing down
*Roof casing down (total 750mm down)
ITEMS
3. Roof installation
*Transportation of hangers, busbars and aluminium cables from warehouse to bath
*Transportation of roof blocks and heater elements from warehouse to bath
*Putting in and installation of the hanger,busbar,refractory,heater elements
*Cutting roof blocks for H/E and shoulder area
*Installation of the roof side wall
*Installation of aluminum busbars and aluminum braids
*Installation of partition plates (2 positions)
*Connection of the aluminum braids and heater wiring
*Transportation of empty pallets and box to warehouse
*Tidy up waste packing material (vinyl, pp band, polystyrene, etc)
*Cleaning (vacuuming) of inside busbar chamber and top of the roof casing
End of document
23