Biweekly Quality Report # 12 16 August To 31 August 2019 (Civil)
Biweekly Quality Report # 12 16 August To 31 August 2019 (Civil)
2- Sub base First & second layer laying and compaction with testing, Asphalt first & Second layer completed at 12B
Completed
3- Sub base First & second layer laying and compaction with testing, Asphalt first & Second layer completed at 3B
Completed
4-Excavation work for 12A In progress.
5- Excavation & Snad bedding for Section 2A Completed.
The work was carried out in compliance with the most recent drawings & documents
approved for construction(If No, explain)
2 YES☐ NO☐
Obsolete or Superseded drawings & documents were removed (If No, explain)
3 YES☐ NO☐
Were there any Quality – related work interruptions or hold points ? (If Yes, explain)
5 YES☐ NO☐
How many Inspection Requests were issued? Accepted?(If none issued, explain) ISSUED : ----15---
6 ACCEPTED:----15-----
How many Material Inspection Requests were issued? Accepted? (If none issued, explain) ISSUED : -------0------
7 ACCEPTED:-----0------
Work Procedures are available & are in regular usage.(If No, explain)
9 YES☐ NO☐
The Quality Record System is up-to-date & available at worksite.(If No, explain)
10 YES☐ NO☐
Major equipment was delivered to the worksite according to the planned project schedule.(If
No, explain)
13 YES☐ NO☐
The Contractor complied with all Safety & Loss Prevention Requirements(If No, explain)
14 YES☐ NO☐
NCR : Non-Conformance report , MDR : Material Damage Report , MOSR : Material Shortage / Overage Report