Professional Documents
Culture Documents
Field Training Report
Field Training Report
WINTER TRAINING ON
(RAILWAY CONSTRUCTION)
SUBMITTED BY
Amongst the different modes of transport, Railways have their greatest utilization
in the transport of large volumes of heavy and bulk commodities and passengers over long
distances with safety, comfort and convenience.
The line in Bombay was ready by November 1852 and on November 18, 1852, a
few engineers and directors of the GIP Company had a trial run between Bombay and Thane.
However officially, the first train in India (and in Asia) was flagged off on April 16, 1853, a
Saturday, at 3:35 pm between Boree Bunder (Mumbai) and Thane, a distance of 34 kms. The
importance of the day can be gauged from the fact the Bombay government declared the day
as a public holiday.
The train, hauled by three engines -- Sindh, Sahib and Sultan -- carried as many
as 400 passengers in its 14 coaches on its debut run. The Great Indian Peninsula Railway had
ordered a set of eight locomotives from Vulcan Foundry, England, for the purpose. A suit of
Durbar Tents erected at Thane welcomed the first train and a cover for four hundred persons
was built with tables laid with menu literally groaning under every delicacy of the season.
India had, however, spotted one of its earliest locomotives as early as December
22, 1851. The first steam engine, Thomason, hauled some wagons containing mud and earth
during the construction of the Solani aqueduct near Roorkee. The second one, Lord Falkland,
named after a Bombay governor, was seen a year later near Byculla, Bombay, doing shunting
duties. The third one was used for the trial run of the passenger train in November 1852. And
it was only after all this that the much-publicised “official” first train saw the light of the day
on April 16, 1853. Wasn’t it a long, long journey before the “official” first train saw the light
of day. And since then there has been no looking back.
The railways in India are the largest rail web in Asia and the world’s second
largest under one management. With a huge workforce of about 1.65 million, it runs some
11,000 trains every day, including 7,000 passenger trains. The tale of how railway
communication gained foothold in India, where the locomotive was once considered as a
“fire-spitting demon”, is indeed an interesting one.
1)Trunk Routes
2)Main Lines
3)Branch Lines
Formation Components
Formation comprises of Granular layer (sub-ballast and or Blanket) over prepared
subgrade and embankment fill. General profile of formation shown below:
Track Foundation: Constitutes ballast, sub-ballast, blanket and subgrade, which is placed /
exist below track structure to transmit load to subsoil.
Formation Top: Boundary( interface) between ballast and top of blanket orsubgrade
(where blanket layer is not provided).
Cess: Portion at top of formation level, extends from toe of ballast to edge of
formation.
Ballast: Crushed stones with desired specifications placed directly below the sleepers.
Sub-ballast: Sub-ballast is a layer of coarse-grained material provided between
blanket/subgrade and ballast and confined to width of ballast section only. However,
sub-ballast is not in vogue on Indian Railways. Therefore, its provision has not been
considered in these Guidelines.
Blanket: Blanket is a layer of specified coarse, granular material of designed thickness
provided over full width of formation between subgrade and ballast.
Track structure
Rails : Rails are the members of the track laid in two parallel lines to provide an
unchanging, continuous and level surface for the movement of trains.
Sleepers:-the member laid transversely under the rail for supporting and fixing them
to the gauge distance apart known as sleeper.
Rail Gauges
The different gauges can broadly be divided into the following four categories:
1. Broad Gauge: width 1676 mm to 1524 mm
2. Standard Gauge: width 1435 mm and 1451 mm
3. Metre Gauge: width 1067 mm, 1000 mm and 915 mm
4. Narrow Gauge: width 762 mm and 610 mm
Fig..Types of Gauges
3. Cost of Track:
The cost of railway track is directly proportional to the width of its gauge.
If the fund available is not sufficient to construct a standard gauge, a metre gauge or a narrow
gauge is preferred rather than to have no railways at all.
4. Speed of Movement:
The speed of a train is a function of the diameter of wheel which in turn is limited by the
gauge.
The wheel diameter is usually about 0.75 times the gauge width and thus, the speed of a train
is almost proportional to the gauge.
If higher speeds are to be attained, the broad gauge track is preferred to the metre gauge or
narrow gauge track.
5. Nature of Country:
In mountainous country, it is advisable to have a narrow gauge of the track since it is more
flexible and can be laid to a smaller radius on the curves.
This is the main reason why some important railways, covering thousands of kilometers, are
laid with a gauge as narrow as 610 mm.
On site we observe that all are the broad gauges are used. The broad gauge having the length
of 1676mm.
Fig.Broad Gauge
(i) Sub-grade in bank or cutting is structurally sound so as not to fail in shear strength under
its own load and live loads; and
(ii) Secondly, any settlement due to compaction and consolidation in subgrade and subsoil
should be within the permissible limits.
Subgrade should be designed to be safe against shear failure and large deformations. dequacy
of subsoil against shear strength and settlement should also be examined. The sub soil is not
as per the requirement the we can provide the blanketing material to avoid the settlement of
the railway track.
Blanket Layer
To avoid failure of track formation due to inadequate bearing capacity and to safeguard
against swelling and shrinking, adequate blanket thickness must be provided in all cases at
the time of construction of new lines, permanent diversions, raising of formation, in cuttings
etc. or while rehabilitating a failing track formation. Depth of blanket layer of specified
material depends primarily on type of subgrade soil and axle load of the traffic.Depth of
blanket to be provided for axle loads upto 22.5t for different types of subgrade soils
(minimum top one meter thickness) has been given as under. In case more than one type of
soil exists in top one meter then soil requiring higher thickness of blanket will govern.here on
this site they provided 1.10m depth of blanket material.
The quality and depth of blanket material, as specified in these Guidelines, would carry out
the above functions satisfactorily under Indian conditions.
The level of blanket material is checked by the auto level before and after the
compaction.The compaction is done the 10tone vibratory roller.the 10 times the roller is
passed with full vibration then the density is checked by the sand replacement method.
1.Rail :-
Definition :-Rails are the members of the track laid in two parallel lines to provide an
unchanging, continuous, and level surface for the movement of trains. To be able to
withstand high amount of stresses these are made of high carbon steel.
Functions of Rails
Rails are similar to steel girders. These are provided to perform the following
functions in a track.
Rails provide a continuous and level surface for the movement of trains.
Rails provide a pathway which is smooth and has very little friction.
Rails serve as a lateral guide for the wheels.
Rails bear the stresses developed due to vertical loads transmitted to them through
axles and wheels of rolling stock as well as due to braking and thermal forces.
Rails carry out the function of transmitting the load to a large area of the formation
through sleepers and the ballast.
The section of the rail should be such that the load of each wheels is transferred to the
sleepers without exceeding the permissible stresses.
The section of the rail should be able to withstand the lateral forces caused due to fast
moving trains.
The bottom of head and top of foot should be given such shapes that fishplates can be
easily fitted.
The centre of gravity of the rail section should preferably coincide the centre of the
height of the rail so that maximum tensile and compressive stresses are nearly equal.
The web of the rail section should be such that it can safely bear the vertical load
without buckling.
The head of the rail should be sufficiently thick for adequate margin of vertical wear.
The foot of rail should provide sufficient bearing area on the underlying sleepers so
that the compressive stresses on the timber sleeper remain within permissible limits.
The section of the rails should be such that the ends of two adjacent rails can be
efficiently jointed with a pair of fish plates.
The surfaces for rail table and gauge face should be sufficiently hard to resist the
wear.
The contact area between the rail and wheel flange should be as large as possible to
reduce the contact stresses.
The specimen of rail should be able to withstand the blow of a falling weight in the
test specified by the specifications
The composition of the steel should conform to the specifications adopted for its
manufacture by Open Hearth of Duplex Process
The overall height of the rail should be adequate to provide sufficient stiffness and
strength as a simply supported beam.
The foot of the rail should be wide enough so that the rail is stable against
overturning.
There should be balanced distribution of metal in head, web and foot.
Types of Rail
Formerly wooden rails are used with thin plates. Later on the Cast–iron, Malleable
iron,Wrought iron, steel rails are used.At present,the rails are Classified mainly into 3 types :-
2.Fastening
Rail fastening system refers to a group of railway fasteners that are used to fasten
steel rail to railway sleeper. Common components of rail fastening system include rail clip,
railroad spike, rail bolt, rail tie plate, rail pad, washer, plastic dowel, rail insulator and rail
shoulder, etc.
The main function of rail fastening system is preventing steel rail from lateral and
horizontal movement. Besides that, rail fastening system also can absorb and transfer the
pressure from locomotive to railway sleeper. In a word, rail fastening system ensures the rail
in gauge and protects rail safety. Rail fastening system has a lot of types that is composed of
different fasteners.
Rail fastening system is a means of fixing rails to sleepers.it is used to keep rails in
proper position.
Important fittings are:
1. Fish Plates
2. Spikes
3. Bolts
4. Chairs and key
5. Bearing Plates
1.FISH PLATES
Fishplate, splice bar or joint bar is a metal bar that is bolted to the ends of two rails to join
them together in a track.it is used maintain the continuity of rails & to allow for expansion
and contraction of rail due to temperature difference. Maintain correct alignment of line both
horizontally & vertically. Fishplate is a small copper or nickel silver plate that slips onto
both rails .
2.FISH BOLTS
Holes are drilled through plates and web of rails and then fish bolts and nuts are
provided in these holes.Alternate holes are made elongated and oval shaped so that bolts in
the rails will not be turned by vibrations.Holes are made of larger diameter generally 5mm-
6mm to allow for expansion & contraction.
Fig.Fish bolts
2)SPIKES
Spikes are used to hold rails to wooden sleepers.A rail spike is a large nail with an
offset head that is used to secure rails and base plates to sleepers. know day the rcc pre
stressed sleepers are used in that for fastening already the provisions are made.
3)BOLTS
High strength bolt is a typical kind of rail bolt that is made of high strength steel.
Like other types of rail bolt, high strength bolt is used to connect the ends of rail together.
The train operation usually produce huge load to the rail track, and railway track has lateral
and horizontal movement. The functions of high strength bolt are prevent the track from
movement and ensure the safety. As for the type, most of railroad bolts is high strength bolt,
such as Diamond neck track bolt, Rail bolt NF F50-008, Fish bolt, Clip bolt HS26 & HS32,
Special bolt, and so on.
Fig.Bolts
5)BEARING PLATES
It is in Rectangular shape plates made up from mild steel or cast iron. It is used below flat
footed rails to distribute the load on a larger area of the sleepers .it is also Placed below rails
carrying heavy vehicles at high speed.
Fig.Bearing plates
Fig.Rail Pad
RAIL ANCHOR
Rail anchors made in one-piece construction from spring steel are designed to
fasten the rail tight on the base of the rail to prevent the rail from longitudinal movements, i.e.
the “ creeping” of the rail, caused by changing temperature, grades, traffic patterns, and
braking action of trains.
Rail anchors are applied to the rail base directly and lodge up against the tie. Rail
anchors provide a large bearing surface against rail base and rail tie, preventing cutting and
wear, and eventually to prolong the working life of the rail ties. Anchors are made for a
specific rail weight and base width, which can be classified into two types: the Drive-on rail
anchors and Spring type rail anchor.
Fig.Clip
3.SLEEPER
It is a component of permanent way laid transversely under the rails and performing
the following functions.
I. To support the rails firmly and evenly
II. To maintain the gauge of the back correctly
III. To distribute the weight common on the rails over a sufficiently large areas of the ballast
IV. To act as an elastic medium between the rail and the ballast and to absorb the vibrations
of the trains.
V. To maintain the track at proper grads
VI. To align the rail properly
2.Steel sleepers
They are in the form of steel trough inverted on which rails are fixed directly by keys or nuts
and bolts and used along sufficient length of tracks.
Concrete sleepers
R.C.C and pre-stressed concrete sleepers are now replacing all other types of
sleepers except to some special circumstances such as crossing bridges etc here timber
sleepers are used. They were first of all used in France round about in 1914 but are common
since 1950. They may be a twin block sleepers joined by an angle iron. It may be a single
block pre-stressed type.
Drawings
As we all know that drawing is the language of the civil engineers.on site we
firstly observe the drawings of various proposed work at different station from the wakav
station to wadshinge station. There is one intermidate station is madha.
On madha station there is a proposed railway station and the new railway yard
construction.rom the adjacent station vakav 399.27 chainage (distanace 7.20kms)there are
seven line in which 3 line are exiting and 5 line are proposed.three lines are having spacing
between two first two line are 5.30m and the 2nd and 3rd line having 10m spacing.on madha
station there 14 crossing point including 2 emergency crossing.the railway platform is high
On wadsinge station there are there lines the existing down line of 791m,,existing
up main line 726m,existing 2nd loop line of 760m.we can see in the drawing there are some
proposed works are shown like proposed down loop line of 770m, exisisting main up line to
be convert into the main down line of 770m,the 2nd loop line to be convert into the up main
line of 770m and construction of the new up loop line of 770m.as per the crs the distance
between the two track is 5.30 m min.
Setting out :- It is a process of transferring the distance from the plan already prepared, to the
ground before starting the construction. The plan as designed and prepared is set out on the
ground in the correct position. Setting out in a sense, is a reverse of the conventional.
surveying plans are prepared by the designer using the data from the site. While, in setting
out the plans and designs prepared by the designer are transffered accurately onto the site.
On the site we have the drawings of the fob and the all dimensions of the bridge.oue
job is to set out the diamensions on the field. First job is we observed the drawing and the
distance of the bridge. Here the have given the c/c distance between the bridge and the main
existing building of the near about 35m.we take the all diamensions in the AutoCAD file and
by using the co ordinates method we set it on the filed.
The depth of the column foundation is 5.85.the m30 grade RMC concrete is
used.the bolts of the plates are fixed with the steel then it is filled with the concrete to
matching the all bolts the plate is used which is shown below:
Fig.Filling Of The Column Base Fig Placing Of The Plate Matching The Bolts
After that the column of the fob is placed on that platform and its bolted.when we are
placing the column by using the crane it is possibility of to get the crackes between the
column base concrete.this cracks are fillied by the high grade concrete known as GP2.it is
mixed with water in prapotional manner and the it fillied in the cracks after that we can place
the column in that base when it is dry.
When we are placing the column on the column base there is one base plate is placed
between it.the plate is placed for the purpose to match the all column leveland avoid the
tilting of the column. The level of each base and the rested column bottom plate level is
checked by the auto level.this procedure is done for all supports and checked by auto level.
Types Of Platform
1.Central Platform
2.Side Platform
3.Other Platform
Side Platforms
Side platforms provide access to trains along one side of the track. The passenger
must
decide between platforms based on their direction of travel prior to descending to platform
level.all station on the side I observerd that all are the side platforms.
The length shall accommodate the train (26 coaches as per the Indian Railways’
future plans for the standard number of coaches/train) and two locomotives at each end.
1. Need for directional decisions to be made prior to descending to the platform, in order
to avoid backtracking and delay.
2. Need for clear signage to be provided so that customers can select the appropriate
platform.
3. Need for passengers to change levels and cross tracks to change train directions.
4. Less space efficiency, resulting in wider stations (minimally sized platforms meeting.
5. requirements under NFPA 130 will be larger than a single minimally sized center
platform).
6. Greater number of VCEs for equivalent capacity.
CONSTRUCTION OF PLATFORM
First the marks the dimensions on the filed by using the total station and drawings
On the site then the excavation is done.after the excavation the ucr masonary in the is laid
upto the depth 300mm