Professional Documents
Culture Documents
Description Total Work Planned / Actual Progress Beginning Work Progress
Description Total Work Planned / Actual Progress Beginning Work Progress
Description Total Work Planned / Actual Progress Beginning Work Progress
Construction of Foundation
ASHOORA
104 Planned Work
Form Work for Columns
7
(Where applicable)
Nos Actual Progress
5 Planned Work
1 Test Pits
Nos Actual Progress
85 Planned Work
6 Radiography of Joints 8"dia
Nos Actual Progress
DEVELOPMENT OF 8" PMG PIPELINE BETWEEN PARC
65 Planned Work
Pipe Coating, HSS / Coating on
7
Girth welds and Bends
Nos Actual Progress
1 Planned Work
Examination of Pipe Coating with
8
Holiday Detector
Job Actual Progress
ASHOORA
wet areas , swamps, ditches and
11
flooding areas / Anchor Flanges
(if applicable) Nos Actual Progress
25 Planned Work
12 Installation of Valves 8"dia
Nos Actual Progress
64 Planned Work
13 Bolting Joints 8"dia
Nos Actual Progress
6 Planned Work
Pipeline Works for Installation of
16 PRV Connections including 1" x
3/4" Piping
Nos Actual Progress
6 Planned Work
Pipeline Works for Installation of
17
Drain Points 2"dia
Nos Actual Progress
1 Planned Work
Fabrciation and Installation of Pig
18
Launcher & Pig Receiver
Job Actual Progress
1 Planned Work
1 Installation of CP system
Job Actual Progress
Commissioning of Pipeline
1 Planned Work
1 Commissioning of Pipeline
Job Actual Progress
MG PIPELINE BETWEEN PARCO & PSO SHIKARPUR
Construction of Foundation
0 0
AHEAD 0
104 100%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 13
91 88%
0 0%
AHEAD 0
104 100%
0 0%
AHEAD 104
0 0%
0 0%
AHEAD 104
0 0%
#VALUE! #VALUE!
#VALUE! 0
5 100%
0 0%
AHEAD 600
0 0%
0 0%
AHEAD 600
0 0%
0 0%
AHEAD 0
600 100%
0 0%
AHEAD 55
150 73%
0 0%
AHEAD 32
53 62%
MG PIPELINE BETWEEN PARCO & PSO SHIKARPUR
0 0%
AHEAD 65
0 0%
0 0%
AHEAD 1
0 0%
0 0%
AHEAD 600
0 0%
0 0%
AHEAD 60
540 90%
0 0%
AHEAD 30
0 0%
0 0%
AHEAD 25
0 0%
0 0%
AHEAD 64
0 0%
0 0%
AHEAD 600
0 0%
0 0%
AHEAD 600
0 0%
0 0%
AHEAD 6
0 0%
0 0%
AHEAD 6
0 0%
0 0%
AHEAD 1
0 0%
0 0%
AHEAD 0
450 100%
0 0%
AHEAD 0
450 100%
0 0%
AHEAD 450
0 0%
0 0%
AHEAD 1200
0 0%
0 0%
AHEAD 1
0 0%
Commissioning of Pipeline
0 0%
AHEAD 1
0 0%