SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013 Note: For Maintain Potential Projects usage

COS 03/31/2013 Note: For Maintain Potential Projects usage only.


SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-J-200-01
Pressure Instrumentation 30-Apr-13 INSTRUMENTATION
MP
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.00 DOCUMENT REVIEW

See See
1.01 Intrinsically Safe Circuits SATIP-J-903-01 Intrinsically Safe Circuits
Remarks Remarks

2.00 MATERIAL RECEIVING

Storage, Handling and Preservation


2.01
Visual Inspection
SAIC-T-5001 SAIC-T-5001 I S Weekly Inspection by Contractor QC

Also see SATIP-J-003-01 Piping and Tubing; and


SATIP-J-902-06 Instr. Racks, Boxes and Cabinets
Accessories include pulsation dampeners (snubbers),
Pressure Gauges
siphons, diaphragm seals, etc.
2.02 Material Receiving SAIC-J-6201 SAIC-J-6201 H S/W SA PID shall be notified on initial delivery of each listed
Visual Inspection
instrument or accessory (by type or manufacturer).
"S"- Aramco supply material
"W"- Contractor supply material

Also see SATIP-J-003-01 Piping and Tubing; and


SATIP-J-902-06 Instr. Racks, Boxes and Cabinets
Pressure Switches
Accessories include pulsation dampeners (snubbers),
2.03 Material Receiving SAIC-J-6202 SAIC-J-6202 H W siphons, diaphragm seals, etc.
Visual Inspection
SA PID shall be notified on initial delivery of each listed
instrument or accessory (by type or manufacturer).

Also see SATIP-J-003-01 Piping and Tubing; and


SATIP-J-902-06 Instr. Racks, Boxes and Cabinets
Accessories include pulsation dampeners (snubbers),
Pressure Transmitters
siphons, diaphragm seals, etc.
2.04 Material Receiving SAIC-J-6203 SAIC-J-6203 H S/W SA PID shall be notified on initial delivery of each listed
Visual Inspection
instrument or accessory (by type or manufacturer).
"S"- Aramco supply material
"W"- Contractor supply material

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013 Note: For Maintain Potential Projects usage only.
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-J-200-01
Pressure Instrumentation 30-Apr-13 INSTRUMENTATION
MP
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Also see SATIP-J-003-01 Piping and Tubing; and


SATIP-J-902-06 Instr. Racks, Boxes and Cabinets
Accessories include pulsation dampeners (snubbers),
Differential Pressure Transmitter
siphons, diaphragm seals, etc.
2.05 Material Receiving SAIC-J-6204 SAIC-J-6204 H S/W SA PID shall be notified on initial delivery of each listed
Visual Inspection
instrument or accessory (by type or manufacturer).
"S"- Aramco supply material
"W"- Contractor supply material

Also see SATIP-J-003-01 Piping and Tubing; and


SATIP-J-902-06 Instr. Racks, Boxes and Cabinets
Recorder / Indicator
Accessories include pulsation dampeners (snubbers),
2.06 Material Receiving SAIC-J-6016 SAIC-J-6016 H W siphons, diaphragm seals, etc.
Visual Inspection
SA PID shall be notified on initial delivery of each listed
instrument or accessory (by type or manufacturer).

Also see SATIP-J-003-01 Piping and Tubing; and


SATIP-J-902-06 Instr. Racks, Boxes, and Cabinets
Instrumentation Accessories
Accessories include pulsation dampeners (snubbers),
2.07 Material Receiving SAIC-J-6017 SAIC-J-6017 H W siphons, diaphragm seals, etc.
Visual Inspection
SA PID shall be notified on initial delivery of each listed
instrument or accessory (by type or manufacturer).

3.00 DOCUMENT REVIEW AND BENCH TESTING

As needed, in accordance with manufacturer's


Pressure Gauges
instructions. SA PID shall be notified on start of
3.01 Document Review SATR-J-6201 SATR-J-6201 H S bench calibration for each shipment / batch (by
Bench Testing
type or manufacturer).

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013 Note: For Maintain Potential Projects usage only.
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-J-200-01
Pressure Instrumentation 30-Apr-13 INSTRUMENTATION
MP
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Pressure Switches As needed, in accordance with manufacturer's


3.02 Document Review SATR-J-6202 SATR-J-6202 H W instructions. SA PID shall be notified on start of
Bench Testing calibration for each shipment / batch.

Pressure Transmitters As needed, in accordance with manufacturer's


3.03 Document Review SATR-J-6203 SATR-J-6203 H S instructions. SA PID shall be notified on start of
Bench Testing calibration for each shipment / batch.

Differential Pressure Transmitter As needed, in accordance with manufacturer's


3.04 Document Review SATR-J-6204 SATR-J-6204 H S instructions. SA PID shall be notified on start of
Bench Testing calibration for each shipment / batch.

Recorder / Indicator As needed, in accordance with manufacturer's


3.05 Document Review SATR-J-6002 SATR-J-6002 H W instructions. SA PID shall be notified on start of
Bench Testing calibration for each shipment / batch.

4.00 INSTALLATION

SATIP-J-902-06 Instr. Racks, Boxes and Cabinets


Support / Enclosure Installation See See
4.01 SA PID shall be notified on start of installation for each
Visual Inspection Remarks Remarks
plant area and process system.

Pressure Gauges
SA PID shall be notified on start of installation for each
4.02 Instrumentation Installation SATR-J-6201 SATR-J-6201 H W plant area and process system.
Visual Inspection

Pressure Switches
SA PID shall be notified on start of installation for each
4.03 Instrumentation Installation SATR-J-6202 SATR-J-6202 H W plant area and process system.
Visual Inspection

Pressure Transmitters
SA PID shall be notified on start of installation for each
4.04 Instrumentation Installation SATR-J-6203 SATR-J-6203 H W plant area and process system.
Visual Inspection

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013 Note: For Maintain Potential Projects usage only.
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-J-200-01
Pressure Instrumentation 30-Apr-13 INSTRUMENTATION
MP
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Differential Pressure Transmitters


SA PID shall be notified on start of installation for each
4.05 Instrumentation Installation SATR-J-6204 SATR-J-6204 H W plant area and process system.
Visual Inspection

Recorder / Indicator
SA PID shall be notified on start of installation for each
4.06 Instrumentation Installation SATR-J-6002 SATR-J-6002 H W plant area and process system.
Visual Inspection

General Instrumentation Accessories


SA PID shall be notified on start of installation for each
4.07 Instrumentation Installation SAIC-J-6205 SAIC-J-6205 H W plant area or process system.
Visual Inspection

See SATIP-J-003-001 Piping and Tubing


Piping and Tubing Installation See See
4.08 SA PID shall be notified on start of installation for each
Visual Inspection Remarks Remarks
plant area and process system.

Intrinsically Safe Barrier


See SATIP-J-903-01 Intrinsically Safe Circuits
& Cable Installation See See
4.09
Visual Inspection Remarks Remarks H H SA PID shall be notified on start of installation for each
intrinsically safe circuit.
(where applicable)

5.00 PRE-COMMISSIONING

Pressure Gauges As needed, in accordance with manufacturer's


5.01 Instrumentation Installation SATR-J-6201 SATR-J-6201 H W instructions. SA PID shall be notified on start of
Field Calibration installation for each plant area and process system.

Pressure Switches As needed, in accordance with manufacturer's


5.02 Instrumentation Installation SATR-J-6202 SATR-J-6202 H W instructions. SA PID shall be notified on start of
Field Calibration installation for each plant area and process system.

Pressure Transmitters As needed, in accordance with manufacturer's


5.03 Instrumentation Installation SATR-J-6203 SATR-J-6203 H W instructions. SA PID shall be notified on start of
Field Calibration installation for each plant area and process system.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013 Note: For Maintain Potential Projects usage only.
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-J-200-01
Pressure Instrumentation 30-Apr-13 INSTRUMENTATION
MP
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Differential Pressure Transmitters As needed, in accordance with manufacturer's


5.04 Instrumentation Installation SATR-J-6204 SATR-J-6204 H W instructions. SA PID shall be notified on start of
Field Calibration installation for each plant area and process system.

Recorder / Indicator As needed, in accordance with manufacturer's


5.05 Instrumentation Installation SATR-J-6002 SATR-J-6002 H W instructions. SA PID shall be notified on start of
Field Calibration installation for each plant area and process system.

See SATIP-P-104-04 .Boxes and Wireways


Hazardous Location
See See Hold point for fiber damming and cement pouring.
5.06 Enclosure Sealing
Remarks Remarks H H SA PID shall be notified on start of installation for each
Visual Inspection
plant area and process system.

Intrinsically Safe Circuit


As needed, in accordance with manufacturer's
Final Inspection See See
5.07
(before energization, Remarks Remarks H H instructions. SA PID shall be notified on start of
installation for each plant area and process system.
where applicable)

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1
adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use