Download as pdf or txt
Download as pdf or txt
You are on page 1of 42

DEMOLITION

SAFETY
DEMOLITION
Objectives
At the end of the session, the participants will be able to:

1. Learn what are the proper plan for demolition


process.
2. Determine what are the hazards that will be exposed
during demolition.
3. Learn what measures to prevent the hazards when
demolition is on going.
Demolition
safety 2
DEMOLITION

Complete or partial dismantling


of a building or structure by pre-
planned and controlled methods
or procedures

Demolition
safety 3
SAFE DEMOLITION
REQUIRES ADEQUATE
PLANNING

Demolition
safety 4
New York
Demolition
safety 5
Why Plan?
 Identify the Hazards
 Meet Legislative Requirements
 Ensure Appropriate Equipment
 Ensure Safe Disposal of Materials
 Determine Appropriate Methods of Demolition
 Determine Cost of Demolition

Demolition
safety 6
Key Areas for Planning
 Type of Construction
 Type of Structure (Ht., Use)
 State of Structure
 Structural Hazards
 Hazardous Substances
 Location of Services
 General Conditions of Adjoining Structures
 Access and Egress
 Suitability of Site for Equipment
Demolition
safety 7
Demolition Technique
 Sequential – gradual reduction of height in reverse
order to its construction

 Induced – key structural members are weakened or


removed, causing the whole part of the structure to
collapse

Demolition
safety 8
Method of Demolition

 Manual – use of hand held tools

 Mechanical – use of heavy equipment,


wires and chain, power shear, etc.

 Explosives – use of explosives

Demolition
safety 9
Workplan
 Technique and Method of Demolition
 Sequence of Work Operation
 Estimate of Time of Completion
 Equipment to be Used
 Proposed Access and Egress
 Public Protection

Demolition
safety 10
Workplan
 Bracing and Shoring
 Disconnection of Services
 Methods of Handing/ Disposal of
Demolished Materials
 PPE Requirements
 Demolition Personnel and Supervisor

Demolition
safety 11
Procedure
Manual Demolition

 All utilities shut off


 All glasses removed
 Shoring or other measures implement
 Protection of workers from fall
 Stairs to be demolished last

Demolition
safety 12
Procedure
Explosives

 By Competent Person

 Precautions from:
 Smokes, matches & open flames
 Radio Frequency for Electrical
Detonators

Demolition
safety 13
Transport of Explosives

 Vehicles shall have tight floors covered


w/ wood
 Explosives and Blasting implements
shall not be transported with other
materials

Demolition
safety 14
Storage
 All explosives must be accounted for
 Follow manufacturer’s instructions
 Detonators should be stored in a separate magazine
 Storage should be fire and bullet-resistant

Demolition
safety 15
Proper Use
 Operation between Sunup & Sundown
 Precaution on the use of f mobile radio transmitting
equipment.
 Suspension of operation during electrical storm

Demolition
safety 16
After Blasting

 Disconnect firing line from blasting


machine
 Allow dust and smoke to subside
 Inspect if all charges have been
exploded

Demolition
safety 17
Equipment

 Cranes
 Bulldozers
 Excavators
 Work Platform
 Wrecking Ball

Demolition
safety 18
Hazards Associated with Demolition

 Falls
 Being Hit/Trapped/Crushed by Objects
 Manual Handling
 Hazardous Substances and Dangerous Goods
 Noise and Vibration
 Electric Shock
 Fires and Explosions
 Equipment

Demolition
safety 19
Falls

 Falling through fragile roofing material


 Falling through openings
 Falling from open edges
 Falling out of elevating work platforms
 Failure of equipment

Demolition
safety 20
Falls

 Falling from roof or other elevated area


 Lift shafts
 Collapse of flooring
 Collapse of ground
 Tripping over debris

Demolition
safety 21
Being Hit/Trapped/Crushed by Objects

 Falling debris (from service ducts and lift


shafts)
 Accidental/uncontrolled collapse of a
structure
 Use of equipment (crane lifting loads)
 Failure of structural members (load
bearing steelwork)

Demolition
safety 22
Manual Handling

 Using equipment
 Operating equipment
 Manual demolition
 Lifting material
 Clearing up
 Loading trucks/bins

Demolition
safety 23
Hazardous Substances

 Lead
 lead based paint, tanks containing lead based
petrol
 Asbestos
 sprayed coatings, insulation materials, fire
resistant walls/partitions, cement sheets,
flooring materials
 PCBs
 stones, bricks and concrete aggregates

Demolition
safety 24
Dangerous Goods

 Flammable liquids/vapors and sludge from


industrial process and confined space

Demolition
safety 25
Noise and Vibration

 Equipment
 Falling debris
 Explosives

Demolition
safety 26
Electric Shocks

 Live wires from structures

Demolition
safety 27
Fires and Explosions

 Flammable materials
 Welding or cutting
 Leaks of explosives gases from accidental
damage of pipes
 Arson especially when the site is
unattended

Demolition
safety 28
Equipment
 Electrocution
 Plant failure
 Dropping material
 Equipment striking persons
 Noise and vibration

Demolition
safety 29
Equipment

 Flying particles
 Dust and other airborne hazards
 Falling objects onto operators
 Structural collapse of floors
 Welding and cutting hazards
 Falls

Demolition
safety 30
Hierarchy of Control

 Elimination
 Substitution
 Isolation
 Engineering Control
 Administrative Control
 Personal Protective Equipment

Demolition
safety 31
Elimination

 Disconnect services to the demolition site


 Ensure there are no sparks or ignition
sources where there is risk of fire or
explosion
 Ensure separation between the public and
demolition activities

Demolition
safety 32
Substitution

 Use power shears, in place of grinding or


oxy-acetylene cutting, where there is a risk
of fire

Demolition
safety 33
Isolation

 Install screens on equipment to protect


from dust and noise
 Install barriers and fences
 Mark off hazardous areas

Demolition
safety 34
Engineering Control
 Install safe working platforms (scaffolds and elevating work
platforms)
 Install edge protection to open edges of landings, stairways and
fixed platforms
 Use shoring and bracing to support loads
 Modify tools or equipment
 Provide guarding to machinery or equipment
 Provide shatterproof/guarded windscreens on equipment

Demolition
safety 35
Engineering Control

 Install anchor points for fall arrest systems


 Spray water to suppress dust
 Use chutes for dropping debris
 Use cranes for lowering loads
 Install vehicle buffers where equipment is
exposed to an open edge
 Provide flash arresters on gauges and hoses
of welding equipment

Demolition
safety 36
Administrative Control

 Limit the amount of time a person is


exposed to a particular hazard
 Implement and document safe working
procedures for all hazardous tasks
 Train and instruct all personnel
 Identify hazardous substances prior to
work

Demolition
safety 37
Administrative Control

 Implement safe procedures for handling


hazardous substances
 Implement procedures
for disconnecting services to the site
 Use lookouts at the site
 Implement confined space entry
procedures
 Ensure all loads to be lifted are accurately
calculated

Demolition
safety 38
Personal Protective Equipment

 Safety Helmets
 Harnesses and Lanyards
 Boots
 Gloves
 Respirators
 Hearing Protectors

Demolition
safety 39
Demolition

 Preparation
 Barricading of property (distance equal
to 1 1/2 times of height of structure)
 Protection of adjoining property
 Disconnect existing gas, electric and
other services
 Removal of glass

Demolition
safety 40
Demolition

 During Demolition Work


 Floor by floor in descending order
 Provision of chute for disposal of
debris
 Special structures
 Chimney
 Trusses and girders
 Pre-stressed members

Demolition
safety 41
“If we Fail to Plan
We Plan to Fail”

Demolition
safety 42

You might also like