Download as pdf or txt
Download as pdf or txt
You are on page 1of 67

Sub-Clause 1.

15: Limitation of Liability


Written by George Rosenberg1

The substance of this provision was already such loss. Normal rules of the underlying law of
in Sub-Clause 17.6 in the 1999 edition and the contract (unless mandatory) are thus excluded.
has now been separated from other Where the Sub-Clause to which the exception
provisions dealing with Risk and applies clearly sets out the loss or damage which
Responsibility. this exclusion from exemption refers to this does
not raise an issue. However, there are issues in
As before it generally exempts parties from liability respect of the cross reference to Sub-Clauses 8.8
to the other for “loss of use of any Works, loss of and 13.3.1(c).
profit, loss of any contract or any indirect or
consequential loss” except in respect of a list of
The new items are:
identified Sub-Clauses. The list has been extended
and several of the changes are very significant. It Sub-Clause 8.8 [Delay Damages]
also limits liability to certain levels in some
circumstances. Finally, it excludes parties from Sub Clause 8.8 already states that “this Sub-Clause
cover by the exemption and limits in certain shall not limit the Contractor’s liability for Delay
circumstances. All three elements have changed. Damages in any case of fraud, gross negligence,
Two additions are particularly noteworthy. The deliberate default or reckless misconduct by the
interaction between this Sub-Clause and Sub- Contractor.” Thus, if the Contractor is guilty of one
Clause 8.8 insofar as it relates to the liability- these types of misbehaviour it will not be able to
limiting effect of Delay Damages is confusing and it take advantage of the cap on Delay Damages. The
is very unclear what the final result should be taken lifting of the limitation in the Sub-Clause partly
to mean. There is also a similar lack of clarity in duplicates the last paragraph of Sub-Clause 1.15.
the way in which the Sub-Clause applies the This paragraph also lifts the limit in such
exemption to Sub-Clause 13.3.1(c) (proposals for circumstances but goes further in allowing the
valuation of variations). general limit of liability under the Contract to be
exceeded.
Exceptions to exemption from liability to As noted above Sub-Clause 1.15 is divided into two
the other party for loss of use of any Works, parts. The first lifts the exclusion of liability for
loss of profit, loss of any contract or any loss of profit etc. The second lifts the limits of
indirect or consequential loss liability under the Contract.
The list of exceptions to the exemptions from The reference to Sub-Clause 8.8 in Sub-Clause 1.15
liability in the 1999 edition extended to only 2 is under the first part and thus is intended to
items (Payment on Termination and Indemnities). remove the exemption from liability for losses of
It is now extended to some additional items. profit when applying Delay Damages. Since Sub-
Clause 8.8 provides that Delay Damages are the
It should be noted that the wording of the Sub- only damages due from the Contractor for failure to
Clause goes further than merely to negate the meet the Completion Date, except in the event of
exemption from of liability for these items. It says Termination Under Sub-Clause 15.2 [Termination
that “neither party shall be liable for loss of profit” for Contractor’s Default] it would therefore seem
etc. … “other than under…” . Thus, if the party can that the exclusion is intended to prevent arguments
show such loss, it confers an express right to claim

1
George Rosenberg is a Consultantat Corbett & Co. International Construction Lawyers Ltd. He can be contacted at george.rosenberg@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
LimitationOfLiability/GR/2018(1)/1/CLAL 1
www.corbett.co.uk
that Delay Damages incorporate loss of profits and It is doubtful that it was FIDIC’s intention to open
to allow for the possibility of loss of profit claims in the door to such arguments. However, the reading
the event that the Contractor is terminated for of the Contract which leads to this conclusion is a
cause. If the latter were the case one would have reasonable one and it is altogether possible that a
thought that Sub-Clause 1.15 would include Sub- tribunal confronted with the issue will reach this
Clause 15.2 (or more correctly Sub-Clause 15.4) in conclusion.
the list. There may, however be an argument that
an Employer is now entitled to claim loss of profit See comment on the last paragraph of 1.15 below
following termination for cause. for the consequences as regards non-consensual
omissions intended to allow the Employer to have
Sub-paragraph (c) of Sub-Clause 13.3.1 the work completed by others.
[Variation by Instruction]
Sub-Clause 15.7 [Payment after
13.3.1(c) is the provision which requires the Termination for Employer’s Convenience]
Contractor, when carrying out a Variation
instruction, to provide the Engineer with a proposal Sub-Clause 15.6 in the new edition is a significant
for adjustment of the Contract Price. It specifically departure from the 1999 edition in that it gives the
sets out the right to include any costs resulting Contractor entitlement to claim “loss of profit and
from the omission of any work. In particular it other losses and damages suffered by the
allows the Contractor to claim loss of profit, and Contractor as a result of this termination”. Sub-
other losses or damage it suffers, when it has Clause 15.7 only refers to the obligation to pay the
agreed that work should be omitted to be carried amount certified under Sub-Clause 15.6. The
out by others. exception ought to have referred to Sub-Clause
15.6, though the intention is obvious. It is notable
A simple reading would say that the exception to that 15.6 only refers to “loss of profit and other
the normal exclusion is only intended to apply to losses and damages” whereas 1.15 allows claims for
the Contractor’s rights following an agreed “loss of profit, loss of any contract or any indirect
omission in circumstances where the omission was or consequential loss”. Thus, Sub-Clause 1.15
ordered so that the work could be carried out by appears to have the effect of expanding the
others. However, the exception is more widely categories of loss which might have been claimable
expressed. It does not seem possible to read it on a reading of Sub-Clause 15.6 standing alone.
down to prevent the Contractor claiming for loss of
profit etc. as part of the costs it incurs in the case of Sub-Clause 16.4 [Payment after
any omission. Termination by Contractor]

However Sub-Clause 13.3.1(c) does not only cover Sub-Clause 16.4 already includes a right to payment
omissions. It also covers all adjustments to the of loss of profit although it also refers only to “loss
Contract Price following variations. It would thus of profit or other losses or damages”. so, as with
seem arguable that the Contractor is entitled to Sub-Clause 15.7, there may be scope for a wider
include loss of profit etc. in all its Variation claim.
valuation proposals if there is a basis for it in the
circumstances. For example, a very substantial Sub-Clause 17.3 [Intellectual and Industrial
Variation, which the Contractor is required to carry Property Rights]
out on the basis of rates which cause it a loss, or
which force it to use resources which might have Under Sub-Clause 17.3 the Employer and the
been more profitably employed elsewhere, might Contractor each indemnify the other against any
open the door to a claim for the loss of profit etc. claims which may arise where the other faces a

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
LimitationOfLiability/GR/2018(1)/1/CLAL 2
www.corbett.co.uk
claim resulting from a breach of intellectual or However as far as the English Law is concerned, the
industrial property rights caused by the other. The Courts will recognise an express contractual
purpose of this exception is presumably to agreement that gross negligence (rather than mere
overcome any suggestion that the costs the negligence) will attract liability.
indemnified party faces are excluded as indirect or
consequential. The distinction between ordinary and gross
negligence is not easy to define in abstract terms
Limit on Total Liability and the authors of the SCL paper after considering
numerous authorities have suggested the following
This provision was in the 1999 edition and is to the set of tests.
same effect.
“52. However, where the term is not defined
Exclusion from Limits on Liability (which seems to be more usual), then we suggest
the authorities identify the following seven factors
This provision prevents the parties escaping from as relevant to determining whether “gross”
liability in the case of fraud, gross negligence, negligence has occurred:
deliberate default or reckless misconduct. The
term “gross negligence” has been added to the 2017 i. Was the nature of the error serious,
edition version. involving a high degree of risk?

This may have substantially different results ii. Was the conduct undertaken with an
depending on which Law applies to the contract. appreciationof the risks, but with a
blatant disregard of or indifference
In a very interesting treatment of the subject to an obvious risk?
recently presented to the Society for Construction
law in London2 the authors quoted a passage from iii. That disregard or indifference need not be
a Court of Appeal case Armitage v Nurse3 as conscious, or deliberate; it is sufficient that
follows: the reasonably competent professional in
the defendant’s position would have
“It would be very surprising if our law drew the considered the action or inaction to amount
line between liability for ordinary negligence and to a blatant disregard of or indifference to
liability for gross negligence. In this respect the relevant risk. Conscious
English law differs from civil law systems, for it disregard/recklessness will however
has always drawn a sharp distinction between be a likely aggravating factor, and
negligence, however gross, on the one hand and more likely to led to a finding of gross
fraud bad faith and wilful misconduct on the other negligence.
... we regard the difference between negligence
and gross negligence as merely one of degree ... iv. Were the potential consequences of
civil systems draw the line in a different place. The the action or inaction serious? The
doctrine is culpa lata dolo aequiparatur [gross more serious the consequences, the more
negligence is equal to fraud]; and although the likely the negligence will be gross.
maxim itself is not Roman the principle is
classical. There is no room for the maxim in the v. Had the same or similar consequences
common law.” 4 arisen out of the same or similar action or

2 3
Exclusions from Immunity: Gross Negligence and Wilful Misconduct, [1997] EWCA Civ 1279, [1997] 2 All ER 705, [1997] 3 WLR 1046
James Pickavance and James Bowling SCL October 2017 4
Armitage v Nurse Note 14 [1997] 3 WLR 1046 para [254]

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
LimitationOfLiability/GR/2018(1)/1/CLAL 3
www.corbett.co.uk
inaction before? In other words, was it a
repeat error?
Article Author
vi. How likely was it that the George Rosenberg6
consequence would occur? Again, the
more objectively likely it was to occur, the
more likely a finding of gross negligence.

vii. What precautions were taken (if


any) to prevent the consequence
occurring? The more obvious and modest
the steps, and the greater and more likely
the risk, the more likely it is that the Email: george.rosenberg@corbett.co.uk
conduct in question will veer towards gross
negligence.”

Thus the test to be applied under common law


systems before deciding whether a party can escape
from liability differs considerably from that under
civil systems. In the former a high degree of
negligence will make a party liable but in the latter
only fraud will enable them to escape. It may well
be that some common law and civil systems apply a
different test and parties will need to take local
legal advice before deciding what the limitation on
exclusion means in practice.5

Quite apart from this surprising change it should be


noted that the exclusion probably does not prevent
a Contractor faced with a non-consensual omission
by the Engineer in order to allow the Employer to
have the works carried out by others from claiming
loss of profit. Such an omission is forbidden under
Sub-Clause 13.1 unless the Contractor agrees. It
would therefore be a breach of contract on the
Employer’s part and any loss recognised in
damages. Since the breach would be deliberate the
Employer would not be entitled to protection from
a claim for loss of profit.

5 In the Guidance included in the 2017 edition FIDIC notes that “under such an act or omission. It involves materially more want of care than
a number of legal systems (notably in some common law jurisdictions) mere inadvertence or simple negligence.” Although one might wonder
the term ‘gross negligence’ has no clear definition and, as such, is often what the difference is between “serious reckless disregard” and “reckless
avoided in legal documents.” In the general commentary on the disregard”, it would seem to be sensible to include a definition of what is
definitions it is suggested that a typical additional definition might be meant by “gross negligence” and this definition has the benefit of
“Gross Negligence means any act or omission of a party which is improving the level of certainty.
6
contrary to the most elementary rules of diligence which a conscientious The contents of this article should not be treated as legal advice. Please
employer or contractor would have observed in similar circumstances, contact the lawyers at Corbett & Co before acting on or relying upon
and /or which show serious reckless disregard for the consequences of anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
LimitationOfLiability/GR/2018(1)/1/CLAL 4
www.corbett.co.uk
Clause 2: The Employer
Written by Edward Corbett 1

Clause 2 now has 6 sub-clauses:

Employer’s claims has been removed to clause 20;


and new provisions 2.5 [Site Data and Items of
Reference] and 2.6 [Employer-Supplied Materials
and Employer’s Equipment] have been added.

The obligations to provide possession, access and


assistance with permits etc.are essentially the same,
as are the consequences of failure to do so. The
main change to clause 2.4 [Employer’s Financial
Arrangements] is that the Employer now sets out
his arrangements in the Contract Data; and the
Contractor can only request evidence of ability to
pay if those arrangements change, there is non-
payment or there are variations in excess of 30% or
a single variation over 10%.

Clause 2.5 has gathered Employer’s obligations


from clauses 4.7 (re survey points) and 4.10 (re site
data) of the 1999 forms in a worthy effort to place
all such obligations in clause 2.

Clause 2.6 says, rather pointlessly, that if the


Employer’s Requirements specify that materials
and equipment are to be provided by the Employer,
he should provide them. The Contractor is to take
responsibility for equipment used.

Article Author
Edward Corbett 2

Email: edward.corbett@corbett.co.uk

1
Edward Corbett is a Director at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at edward.corbett@corbett.co.uk
2
The contents of this article should not be treated as legal advice. Please contact the lawyers at Corbett & Co before acting on or relying upon anything stated
in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
TheEmployer/EC/2018(1)/2/CLAL www.corbett.co.uk
Clause 3: The Engineer
Written by Victoria Tyson1

The main changes: Employer’s consent and The purpose of this drafting is to accelerate the
neutrality resolution of Variation challenges and give the
Employer more budget certainty and control. If the
The main changes in Clause 3 are the express Contractor fails to give such Notice “immediately”
provisions in Sub-Clause 3.2 [Engineer’s Duties and “before commencing any work related to the
and Authority] that the Engineer is not required to instruction” it will be in breach of the Contract
obtain the Employer’s consent before the Engineer entitling the Employer to damages if the Engineer
exercises its authority under Sub-Clause 3.7 has suffered a loss. There is a lack of express
[Agreement or Determination], and that the wording to indicate that it would also amount to a
Engineer must act “neutrally” when exercising its time-bar.
duties under Sub-Clause 3.7 [Agreement or
Determination]. Dictionary definitions suggest The Engineer must respond to the Contractor’s
that “neutrally” is similar in meaning to the words Notice within 7 days of receiving it, by giving a
“independently” or “impartially” found in the Notice confirming, reversing or varying the
FIDIC Red Book 4th edition and the FIDIC Yellow instruction. Curiously, the Engineer’s response
Book 3rd edition. However, the drafting committee does not need to address the Variation question, it
believe that by using a different word it will avoid just needs to confirm, reverse or vary the
the difficulties raised in the interpretation of instruction. The Contractor is expressly “bound by
independently or impartially in the FIDIC 3rd and the terms of the Engineer’s response”. If the
4th editions. This remains to be seen. The intention Engineer does not respond within the prescribed
is that “the Engineer treats both Parties even- time the instruction is deemed to be revoked.
handedly, in a fair minded and unbiased
manner”2. At the FIDIC Users’ Conference London, December
2017, Michael Sergeant identified the risk of an
Instructions and Variations impasse where the Contractor thinks the work is a
Variation and will not carry it out unless the
Another significant change is the Contractor’s right Engineer issues a formal Variation Instruction, but
under Sub-Clause 3.5 [Engineer’s Instructions] to the Employer/Engineer thinks the work is not a
“immediately” and “before commencing any work Variation and will not issue a Variation Instruction
related to the instruction” give Notice to the because the Employer will have to pay. It seems
Engineer that an Engineer’s instruction which is that the intention of the drafting committee is for
“necessary for the execution of the Works” but is the Parties to proceed with the work, and leave the
not expressly stated to be a Variation, constitutes: argument as to whether or not the instruction
constituted a Variation to be resolved under the
• a Variation, or claims procedure. Therefore, if the Engineer
• involves work that is already part of an existing confirms the instruction but the Contractor
Variation, or remains of the opinion that it constitutes a
• does not comply with applicable Laws, or Variation the Contractor would need to proceed
• will reduce safety of the Works, or with the work (so as not to be in breach of contract)
• is technically impossible. and pursue a claim under Sub-Clause 20.1.
However, this is not expressly stated in Clause 3

1
Victoria Tyson is a director at Corbett & Co. International Construction Lawyers Ltd. She can be contacted at victoria.tyson@corbett.co.uk.
2
Guidance for the Preparation of Particular Conditions, page 21, Sub-Clause 3.7.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
TheEngineer/VT/2018(1)/3/CLAL 1
www.corbett.co.uk
(there is no reference to Clause 20), will cause delay reasons for the dissatisfaction. The 28-day time
and may be an unsatisfactory process particularly bar is not waivable under Sub-Clause 20.2.5
for the Contractor who will have more negotiating [Agreement or determination of the Claim]. Under
power at the start of a project when the Employer is Sub-Clause 21.4.1 [Reference of a Dispute to the
keen to proceed with the Works. DAB] the dispute must then be referred to the
DAAB within 42 days of a NOD, failing which the
Time Limits NOD lapses and the determination becomes final
and binding. Again, there is no waiver.
A further important change concerns the time an
Engineer has to make a fair determination under Other changes to note include:
Sub-Clause 3.7.3 [Time limits]. There are now two
separate 42-day periods in this clause, (i) 42 days • The Engineer must now be a “professional
for the Engineer to give Notice of the Parties engineer” with suitable qualifications,
Agreement if agreement is achieved, and if no experience and competence. He/she must also
agreement is reached (ii) a further 42 days for the be fluent in the ruling language. (Sub-Clause 3.1
Engineer to give Notice of the Engineer’s [The Engineer].) It has been suggested that the
Determination. Consequently, the time in which new provisions may pose difficulties for those
the Engineer must make a determination is now 84 Employers who like to appoint project managers
days. This is an improvement to the open ended (who are generally less expensive than
FIDIC 1999 editions, where the Engineer was professional engineers) in to the role. Further, it
obliged to (i) respond to a claim or any further is important to note that professional engineers
particulars supporting a previous claim with who are members of recognised institutions will
approval, or with disapproval and detailed be bound by certain codes of conduct. There is
comments under Sub-Clause 20.1 within a single no express requirement for the Engineer to be
42-day period, and (ii) make a fair determination based at Site for the whole time the Works are
under Sub-Clause 3.5 for which there was no time- being executed.
limit. These FIDIC 2017 time limits may be
amended if proposed by the Engineer and accepted • In the FIDIC 4th edition there was provision for
by the parties. If the Engineer does not give the an Engineer’s Representative. The Engineer’s
Notice either (i) the Claim is rejected, i.e. it is Representative was removed from the FIDIC
resolved against the claiming Party, or (ii) the 1999 but has been reintroduced into the FIDIC
matter to be agreed or determined is deemed to be 2017. (Sub-Clause 3.3 [The Engineer’s
a Dispute which may be referred by either Party to Representative].) The Engineer may appoint a
the DAAB for its decision under Sub-Clause 21.4 project manager in to this role. The Engineer’s
[Obtaining DAAB’s Decision] without the need for Representative must be based at the Site for the
NOD. whole time the Works are being executed and
therefore a prudent Engineer might appoint a
Under Sub-Clause 3.7.5 [Dissatisfaction with the deputy Engineer’s Representative in order to
Engineer’s determination] the Engineer’s minimise the impact of any unforeseen
determination becomes final and binding unless a absences. There is no express requirement that
dissatisfied Party gives a Notice of Dissatisfaction the Engineer's Representative be fluent in the
(NOD) to the other Party (c.c. the Engineer) within ruling language defined in Sub-Clause 1.4, as the
28 days after receiving the Engineer’s Engineer is required to be under Sub-Clause 3.2
determination under Sub-Clause 3.7.2 [Engineer’s [Engineer’s Duties and Authority], and the
Determination] (or corrected version thereof) assistants are required to be under Sub-Clause
stating that it is a “Notice of Dissatisfaction with 3.4 [Delegation by the Engineer] (unless the
the Engineer’s Determination” and setting out the Engineer’s Representative is also an assistant).

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
TheEngineer/VT/2018(1)/3/CLAL 2
www.corbett.co.uk
• The Engineer may delegate duties and authority
Article Author
to act to assistants (such as design engineers,
other construction professionals, technicians, Victoria Tyson3
inspectors and/or specialist independent
engineers and/or inspectors appointed to
monitor and review the execution of the Works).
It is likely that such assistants will have a major
role in the achievement of a successful project
and be given whatever formal title is considered
by the Engineer to be appropriate. However,
the Engineer may not delegate authority to act
Email: victoria.tyson@corbett.co.uk
under Sub-Clause 3.7 [Agreement or
Determinations] and/or issue a Notice to
Correct under Sub-Clause 15.1 [Notice to
Correct]. (Sub-Clause 3.4 [Delegation by the
Engineer].)

• The Employer may now immediately replace the


Engineer on a temporary basis if the Engineer is
unable to act as a result of death, illness,
disability or resignation. (Sub-Clause 3.6
[Replacement of the Engineer].)

• If an error of a typographical, clerical or


arithmetical nature is found in the
determination or, remarkably, a signed
agreement between the parties, the Engineer
may correct it. (Sub-Clause 3.7.4. [Effect of the
agreement or determination].)

• The new wording at Sub-Clause 3.8 [Meetings]


is a development of the optional clause found in
the FIDIC 1999 editions, now covering both
future work and/or other matters in connection
with the Works. The Engineer is obliged to take
a record of the meeting but there is no
requirement that the Contractor or other
attendees agree this record. Therefore, the
Contractor or other attendees should point out
any differences in the record from their
understanding of the meeting promptly and in
writing.

3
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
TheEngineer/VT/2018(1)/3/CLAL 3
www.corbett.co.uk
Clause 4: The Contractor
Written by Taner Dedezade 1

The main changes to Clause 4 are: Management and Compliance Verification


Systems] retain the same character as the 1999
• The requirement in Sub-Clause 4.1 edition but have become enhanced and more
[Contractor’s General Obligations] that the prescribed in the 2017 edition.
fitness for purpose obligation must be defined
in the Employer’s Requirements (and not • As with the 1999 edition, Sub-Clause 4.10 [Use
elsewhere in the Contract) and in the absence of of Site Data] and 4.12 [Unforeseeable Physical
a definition for purpose, the obligation will be Conditions] need to be considered together.
“ordinary purpose”; Important parts of Sub-Clause of 4.10 have
been cut and pasted into a new Sub-Clause 2.5.
• The ability in Sub-Clause 4.2 [Performance There is an increased obligation to give
Security] for the Employer to instruct the information about the effects of climatic
Contractor to increase or decrease the conditions at the Site in Sub-Clause 4.10(b). In
Performance Security in the event of Variations relation to Sub-Clause 4.12 which hinges on the
that result in an accumulative increase or concept of unforeseeability, it should be noted
decrease by more than 20% of the Contract that there has been a change in the timing in
Price. the definition of Unforeseeable. The benchmark
of the ‘date for submission of the Tender’ has
• In Sub-Clause 4.3 [Contractor’s been replaced by the ‘Base Date’ in both the
Representative], the Contractor’s definition of Unforeseeable and in Sub-Clause
Representative shall be responsible for issuing 4.12.5.
and receiving Notices and other
communications under Sub-Clause 1.3. • Sub-Clause 4.15 [Access Routes], allocates more
risk to the Contractor in the 2017 edition as
• In Sub-Clause 4.4 [Subcontractors], it is now now the Contractor must take “all necessary
possible for a percentage to be included in the measures to prevent any road or bridge from
Contract Data setting out the limits of being damaged by the Contractor’s traffic or
subcontracting. by the Contractor’s Personnel”. There is a new
entitlement for a Contractor to claim time and
• Sub-Clause 4.5 [Nominated Subcontractors] money if the extent of non-suitability or non-
has been expanded but restricted to availability of an access route arises as a result
circumstances in which Plant, Materials, works of changes to that access route by the Employer
or services are to be purchased by the or a third party after the Base Date.
Contractor from a nominated subcontractor
under Sub-Clause 13.4(b) [Provisional Sums].

• In Sub-Clause 4.6 [Co-operation], the 2017


edition affords the Contractor a claims
opportunity if it suffers delay and/or incurs
Cost.

• Sub-Clauses 4.7 [Setting Out]; 4.8 [Health and


Safety Obligations] and 4.9 [Quality

1
Taner Dedezade is a Barrister at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at taner.d@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
TheEngineer/TD/2018(1)/4/CLAL www.corbett.co.uk
Article Author
Taner Dedezade 2

Email: taner.d@corbett.co.uk

2
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
TheEngineer/TD/2018(1)/4/CLAL www.corbett.co.uk
Clause 5: Design
Written by Taner Dedezade 1

The main changes to Clause 5 are as follows:


• In Sub-Clause 5.8 [Design Error], a new
• Sub-Clause 5.1 [General Design Obligations] procedure has been put in place that provides
has been slightly enhanced by specifying with that if errors, omissions, ambiguities,
more particularity the qualifications required of inconsistencies, inadequacies or other defects
designers and stating in terms that designers are found which were previously the subject of a
need to be qualified and entitled under the No-objection, then the process set out for a
applicable law. The key change is structural in failure under Sub-Clause 5.2.2 should be
that part of the clause has been extracted and engaged, hence giving the Contractor a process
moved into Sub-Clause 1.9 [Errors in the for revising and re-submitting the Contractor’s
Employer’s Requirements]. Documents.

• Sub-Clause 5.2 [Contractor’s Documents] in the


Article Author
1999 edition was one of the longest clauses
taking up just over one page (at pages 20 and Taner Dedezade 2
21) with the last sentence of the clause
(appearing in isolation on the top of page 22)
stating “Any such approval or consent, or any
review (under this Sub-Clause or otherwise),
shall not relieve the Contractor from any
obligation or responsibility”.

Under the 1999 edition, in relation to


documents submitted to it for approval, the Email: taner.d@corbett.co.uk
Engineer essentially had 3 options: 1) rejecting
the document for approval; 2) approving the
document with comments; 3) approving the
document without comments. In the 2017
edition, the meaning of the clause remains the
same, with enhanced definitions and sub-
headings, the key change being a change in
emphasis of terminology: there is now an
absence of the use of the word “approval” and a
move to “No-objection”.

Within the review period, the Engineer has


been given two options: 1) finding that the
Contractor’s Document fails to comply with the
Employer’s Requirements; or 2) giving No-
objection (although he may include comments
concerning minor matters which will not
substantially affect the Works).

1
Taner Dedezade is a Barrister at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at taner.d@corbett.co.uk
2
The contents of this article should not be treated as legal advice. Please contact the lawyers at Corbett & Co before acting on or relying upon anything stated
in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
Design/TD/2018(1)/5/CLAL www.corbett.co.uk
Clause 6: Staff and Labour
Written by Gabriel Mulero Clas 1

The 2017 Clause 6 is largely the same as its • The role of the health and safety officer
1999 counterpart. However, it contains (accident prevention officer in FIDIC 1999) has
some notable additions and differences, the been slightly emphasised.
most glaring of which is the addition of a
new type of staff/labourer to the • The importance of fluency in the language of
Contractor’s Personnel called Key communications has been reinforced.
Personnel in Sub-Clause 6.12.
• The Engineer now has the added right to
It only applies if such personnel are specified in the request the removal of personnel who have
Employer’s Requirements and the important aspect engaged in corruption or fraud or who have
of this provision is not what this type of personnel been employed from the Employer.
does but that their appointment and presence is
strictly regulated. • The Contractor’s obligations to maintain
records have been enhanced and include
They are named in the Tender and substitutions Personnel, Equipment, Plant, Materials and
and dismissals need the Engineer’s consent. They Temporary Works and must specify work
also need to be based on Site for the whole period activity, location and day of work.
of the Works. This is perhaps to avoid too much
change of important employees of the Contractor
and to ensure that their focus is on the project at Article Author
hand. Gabriel Mulero Clas2
Other changes include:

• The 1999 edition prohibited the Contractor


from hiring of the Employer’s Personnel in Sub-
Clause 6.3 and the 2017 edition has imposed
the same obligation on the Employer and the
Engineer vis-à-vis the Contractor.
Email: gabriel.muleroclas@corbett.co.uk
• The Contractor’s obligation to follow
employment laws including wages and working
hours has become clearer.

• If work needs to be carried out outside normal


workdays and working hours, the Contractor
now needs to give Notice to this effect.

1
Gabriel Mulero Clas is a Lawyer at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at gabriel.muleroclas@corbett.co.uk
2
The contents of this article should not be treated as legal advice. Please contact the lawyers at Corbett & Co before acting on or relying upon anything stated
in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
StaffAndLabour/GMC/2018(1)/6/CLAL www.corbett.co.uk
Clause 7: Plant, Materials and Workmanship
Written by George Rosenberg 1

Clause 7 deals with a variety of issues There is now an express right for the Contractor to
relating to Plant Materials and proceed to cover up work or material which would
Workmanship. All sub clauses have been otherwise need to be inspected if the Engineer does
subject to some change – in several cases of not respond to the Contractor’s notice advising that
significance. an inspection may be carried out, or the Employer’s
Personnel do not make the inspection at the
Manner of Execution (7.1) notified time.

The 1999 edition only applied the obligations under Testing by the Contractor (7.4)
7.1 to manufacture of Plant, production and
manufacture of materials and generally to the In addition to previous provisions the Contractor is
execution of the Works. It is now extended to cover now required to provide the temporary supplies of
manufacture, supply, installation, testing and electricity and water necessary for any testing and
commissioning and/or repair of Plant, the his staff must be competent enough to ensure the
production, manufacture, supply and testing of tests are carried out properly.
Materials, and all other operations and activities
during the execution of the Works.Bullet point text. The Contractor is required to give Notice to the
Engineer of the time and place it plans to test. This
Samples (7.2) is to be given at a reasonable time to enable the
Employer’s Personnel to attend. This is a change
The 1999 edition inappropriately required samples from the 1999 edition but the only indication in the
to be submitted for testing in the same way as Clause that it is Employer’s Personnel rather than
documents. This has not been fully remedied. A the Engineer who will attend. Later provisions all
detailed process is set out in 7.5 where a sample is refer to the Engineer and indeed impose sanctions
rejected on inspection but no time limits or process if he does not appear. There is clearly an error
for inspection or provision for re-submission where either here or in the later provisions. Whereas the
the issue is not one which would lead to rejection 1999 edition required the Contractor and the
on the basis of a defect is provided. Engineer to agree the times and places for testing,
the Contractor now simply notifies the Engineer
Inspection (7.3) giving a reasonable time.

As in the 1999 edition Notices of availability for A new provision requires the Engineer to issue a
inspection have to be provided to the Engineer, but VO where he wants the Contractor to change the
the inspections are carried out by the Employer’s location or timing or details of specified tests. The
Personnel. use of a VO may be appropriate where there are
additional tests to be carried out and, perhaps,
An express power to make records and take where there is a significant change to the location
photographs and video recordings has been added. or timing of tests. However, the VO procedure is a
time consuming and complex one and it is difficult
Access is now required to be provided in a safe to see why most changes could not be initiated by
manner. simple instruction. Indeed, the following
paragraph provides for that. It is not clear which

1
George Rosenberg is a Consultantat at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at george.rosenberg@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
PlantMaterialsAndWorkmanship/GR/2018(1)/7/CLAL www.corbett.co.uk
provision is intended to apply. It appears that at 7.6) or give a Notice of Rejection. In the latter case
least as far as timing is concerned, the Engineer has Sub-Clause 11.4(a) [Failure to Remedy Defects]
an option as to whether to proceed by Notice or comes into play. “Fail” is normally an absolute term
Variation. If this is the case, the Engineer is but this would make nonsense of the Sub-Clause
probably best to avoid the use of the Variation and presumably “fail” here is intended to mean
power, as this introduces rights to object which “fail in whole or in part”.
could complicate the process.
This allows the Employer to carry out the necessary
The Engineer formerly was required to give at least work to recover its reasonable costs.
24 hours’ notice of his intention to attend the tests.
This has been extended to 72 hours. There was no provision in the 1999 edition for the
Employer to act in this way, so this provision
The Employer is now given the right to claim Costs remedies a gap.
where these are incurred as a result of a delay of the
Contractor. In the case where the Contractor complies with its
obligations and remedies the work, the Engineer
In an error which has been carried over may ask for a “retest”. This can only refer to an
uncorrected from the 1999 edition, in the event of item whose defects were discovered as a result of a
the failure of the Engineer to attend at the time test. This final paragraph cannot therefore allow
notified he is deemed to be present. However, a retesting where the process has had to be initiated
subsequent paragraph states that if he has not as a result of an examination, inspection, or
attended the tests he is deemed to accept them as measurement. However the Engineer would be
accurate. Thus there seems to be no provision by entitled to re-initiate the process under Sub-Clause
which the Engineer may be deemed to have 7.5 – for which there is no automatic cost
accepted the tests as accurate. entitlement for the Employer - or exercise its rights
under Sub-Clause 7.6.
Defects and Rejection (7.5)
Remedial Work (7.6)
In the 1999 edition this provision did not elaborate
on what would happen if the Contractor failed to This Sub-Clause provides an alternative remedy
remedy rejected inspected items. The remedies where the Engineer does not reject the faulty
have been substantially elaborated. element. It is similar to the 1999 equivalent but in
addition to the 1999 remedies the Contractor may
The process through which the Engineer has to go now be required to repair or remedy any Plant or
to seek a remedy where defective items are found Materials (rather than remove as previously) or any
on inspection has been formalised – now requiring other work (rather than remove and re-execute as
a formal Notice from the Engineer and a formal previously). This changes the character of the
proposal from the Contractor. This will then be remedy from one for situations where tests etc have
reviewed by the Engineer who may (within 14 days) been failed to one which may also be applied where
give a Notice of the extent to which the proposal there is damage to the works. One reason for this
does not comply with the Contract. There can be a change is that this sub-Clause is now to be activated
further exchange. If the Engineer does not give his under a cross-reference in Sub-Clause 11.1
14 day notice there is a deemed Notice of No- [Completion of Outstanding Work and Remedying
objection. Defects] which applies during the DNP and thus
also to damage.
If the Contractor fails to submit a proposal or fails
to carry it out, there is provision for the Engineer to Sub-Clause 7.6 now entitles the Contractor to Cost
instruct the Contractor as to what he should do (see and time where the cost of remedying the loss or

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
PlantMaterialsAndWorkmanship/GR/2018(1)/7/CLAL www.corbett.co.uk
damage results from an act by the Employer and Sub-Clause 11.4(a) [Failure to Remedy Defects]
where there is an Exceptional Event under Sub- limits the costs to those reasonable and also states
Clause 18.4. that the Contractor shall have no responsibility for
the work. This seems to indicate, by contrast that
The “repair” right overlaps and adopts a slightly the Contractor may have responsibility for the
different policy compared with Sub-Clauses 17.1 Employer’s work under Sub-Clause 7.6 and there is
and 17.2 which impose on the Contractor an doubt as to whether the Employer’s recoverable
obligation to take full responsibility for the care of costs need be reasonable.
the Works up to completion or termination. Sub-
Clauses 17.1 and 17.2 only apply where the damage A provision in the 1999 edition which allowed the
to be remedied arises from a failure to care for the Engineer to instruct the Contractor to carry out any
works. The obligation there is absolute and does work which was urgently required for safety
not require a notice except where one of the reasons has now been limited to a right to instruct
excluded events set out in Sub-Clause 17.2 apply. remedial work only. Presumably non-remedial
The list of excluded events there is less work urgently required for safety reasons will now
comprehensive in some ways and more in others have to be instructed by a Variation (a process
than the possible range of Exceptional Events. which is not much use in an emergency situation
and which may be difficult to enforce, given the
Unlike this Sub-Clause, the procedure under Sub- changes to Clasue 13.).
Clause 17.2 requires a VO in those circumstances
where the loss or damage is the result of an In a significant shifting of risk from the Contractor
excluded event and, depending on the valuation to the Employer, whereas the 1999 edition required
procedure to be applied under Sub-Clause 13.3.1, the Contractor to bear the risk of all remedial work
the cost to the Employer may be more or less than a ordered under this Sub-Clause, provision is now
simple Cost plus Profit calculation under this Sub- made for it to recover its Cost 2 where the work is
Clause. necessary because of some act of the Employer or
Employer’s Personnel or an Exceptional Event.
Where the remedial work is required as a result of The provision remains valuable to the Employer.
damage to the Works caused by the Employer or Aside from its value under this Sub-clause, it may
Exceptional Events, Engineers should therefore be a valuable remedy where the Contractor does
consider but be careful about making use of this not repair damage as required under Sub-Clause
power. It is much simpler, but it may be more 17.1 and 17.2.
costly to the Employer than if they follow the
provisions of Sub-Clauses 17.1 and 17.2. However Ownership of Plant and Materials (7.7)
the provision will need to be invoked where the
Contractor fails to carry out repair obligations The rules on passing of property, which under the
under Sub-Clause 17.2. That Sub-clause does not 1999 edition applied “to the extent consistent with
provide a remedy for this situation. the Laws of the Country” now apply “to the extent
consistent with mandatory requirements of the
The consequence of the Contractor not carrying out Laws of the Country”. This clarifies a doubt which
the work is (in the same terms as under the 1999 previously existed as to what the position would be
edition) that the Employer may do the work itself at if the Laws of the Country offered an alternative but
the Contractor’s cost where the fault is that of the non-mandatory solution.
Contractor. Like the 1999 edition there is no
limitation to reasonable cost. A similar right under

2
In contrast to the equivalent provision under the Defects Notification
Period (11.3(a)) there is no requirement that this cost be reasonable.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
3
PlantMaterialsAndWorkmanship/GR/2018(1)/7/CLAL www.corbett.co.uk
The previous rules as to when ownership passed
have now been extended to provide that ownership
passes when the Contractor is paid the amount
determined for the Plant and Materials under Sub-
Clause 14.5. As the review of Sub-Clause 4.5
explains this payment will in many cases be
substantially delayed. Further only 80% the
amount determined is included in an IPC (the
balance will only be paid when the Plant or
Materials are incorporated into the Works). Thus,
this extension is not likely to have much effect.

Article Author

George Rosenberg 3

Email: george.rosenberg@corbett.co.uk

3
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
4
PlantMaterialsAndWorkmanship/GR/2018(1)/7/CLAL www.corbett.co.uk
Clause 8: Commencement, Delays and Suspension
Written by Taner Dedezade 1

The main changes to clause 8 are: 8.1 [Commencement of the Works]

• The enhanced Programme requirements in The only notable change in this Sub-Clause is that
Sub-Clause 8.3 [Programme]; in the 2017 edition there is a requirement that the
Engineer gives 14 days’ notice to the Contractor
• The introduction of an Advance Warning stating the Commencement Date, whereas in the
mechanism in Sub-Clause 8.4 [Advance 1999 edition, there is only a 7-day notice period.
Warning];
8.2 [Time for Completion]
• In Sub-Clause 8.5 [Extension of Time for
This clause is unchanged save for the omission of
Completion]:
reference to the achieving of the Tests on
Completion (which is dealt with in the new
o A major change from the 1999 edition is
definition of Sub-Clause 10.1) and so did not need
that, now, a Sub-Clause 20.2 notice is not
to be dealt with in Sub-Clause 8.2 of the 2017
required when applying for an extension of
edition.
time stemming from a Variation;
o further definition of exceptionally adverse 8.3 [Programme]
climatic conditions in Sub-Clause 8.5;
Whilst readers would be forgiven for initially
• The key change to this clause is the inclusion of thinking that the programming requirements
a final paragraph which provides that Sub- would be lessened as there is reference to
Clause 13.3.1 [Variation by Instruction] shall submitting “an initial programme” in the 2017
apply to revised methods including acceleration edition and a “detailed time programme” in the
methods. This is a major change and appears to 1999 edition, the degree of prescription given in the
be limited only to the Engineer being able to 2017 edition is far greater. The 1999 edition had no
instruct acceleration “to reduce delays resulting guidance on how detailed the plan should be. The
from causes listed under Sub-Clause 8.5”. 2017 edition has most notably tried to narrow that
gap by including a new requirement in Sub-Clause
• The new carve out relating to Sub-Clause 8.8 8.3 (g) that “all activities (to the level of detail
[Delay Damages]. The first paragraph of Sub- specified in the Employer’s Requirements),
Clause 8.8 makes it clear that there is a cap on logically linked and showing the earlier and later
Delay Damages as stated in the Contract Data. start and finish dates for each activity, the float (if
The last (new) paragraph makes it clear that the any) and the critical path(s)”. There is now even an
cap will be lifted in the case of fraud, gross invitation for the Employer to specify the
negligence, deliberate default or reckless programming software in the Employer’s
misconduct by the Contractor. Requirements and an electronic copy of the
Programme that needs to be provided.

Clause 8, in more detail: There is an express provision in the 2017 edition


that removes the ambiguity in the 1999 edition that

1
Taner Dedezade is a Barrister at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at taner.d@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
CommencementDelaysAndSuspension/TD/2018(1)/8/CLAL www.corbett.co.uk
no Programme can now constitute a notice under 8.4 [Advance Warning]
Sub-Clause 20.1.
This new clause requires both parties to give
There is a more elaborate mechanism in the 2017
advance warning to each other of any known or
edition requiring Notice to be given when actual
future events which may adversely affect: the work
progress differs from the Programme and a 14-day
of the Contractor’s Personnel; and the performance
time period for the Contractor to issue a revised
of the Works when completed; increase the
Programme but no stipulated consequence for a
Contract Price and/or delay the execution of the
failure to comply with that time-period. As with the
Works or Section (if any). The mechanism then
1999 edition, therefore, there is no periodic update
suggests that, if appropriate, the Engineer invites
required of the programme but see Sub-Clause
the Contractor to put forward a variation proposal
4.20(a).
to avoid or minimise the effects of the notified
There is a new provision in Sub-Clause 8.3(b) of the event. There is no sanction provided in the event of
2017 edition that requires the Contractor to add a failure to comply with this provision. It would
into its programme the dates the Employer is to seem that this is an attempt by FIDIC to bring in
give right of access in accordance with the Contract the concept of ‘partnering’ into the FIDIC contract
Data. If there are no dates in the Contract Data and to get the parties to co-operate with each other
then the Contractor must set out the dates that the before delay claims start to surface and positions
Contractor requires the Employer to give right of start to become entrenched. It may be that this
access to and possession of (each part of) the Site. clause could be used in conjunction with Sub-
Clause 21.3 [Avoidance of disputes].
In Sub-Clause 2.1 it provides that in the absence of
any times set out in the Contract Data, the 8.5 [Extension of time for Completion]
Employer shall give the Contractor right of access
An important change to this clause is that a Sub-
to, and possession of, those parts of the Site “within
Clause 20.2 Notice (previously 20.1 notice) is no
such times as may be required to enable the
longer required if a Contractor is seeking an
Contractor to proceed in accordance with the
extension of time resulting from a Variation.
Programme or, if there is no Programme at the
time, the initial programme submitted under Sub- The five grounds for extension of time remain. Sub-
Clause 8.3”. Clause 8.5 (c) exceptionally adverse climatic
conditions has been enhanced and Employer-
Late possession is an Employer Risk Event allowing
Supplied Materials has been added to
the Contractor to claim time and money. It was
unforeseeable shortages in Sub-Clause 8.5(d).
often the case with the 1999 edition that Sub-
Clause 2.1 would be enhanced/amended by the Concurrent delay has not been addressed in the
Employer so as to remove the risk that a Contractor clause save to state in the new last paragraph of
would simply claim time and money as soon as they Sub-Clause 8.5 that should the parties wish to deal
found out that they did not have full access from with it, they should do so in the Special Provisions.
the outset of the project. Whether this additional The Guidance section refers to the possibility for
requirement in Sub-Clause 8 was an attempt to the parties to make reference to the SCL protocol.
distort the risk allocation in the contract or whether See the last paragraph of Sub-Clause 17.2 for an
it will effectively deal with this issue is inconsistent approach. In that clause, there is
questionable, as I expect every Contractor will reference to apportionment.
simply set out in its programme that they require
all possession from the Commencement Date.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
CommencementDelaysAndSuspension/TD/2018(1)/8/CLAL www.corbett.co.uk
8.6 [Delays caused by Authorities] of Work] provide enhancements but neither are
material.
There is no change to this clause save to include
“private utility entities”.

8.7 [Rate of Progress] Article Author


Taner Dedezade 2
The key change to this clause is the inclusion of a
final paragraph which provides that Sub-Clause
13.3.1 [Variation by Instruction] shall apply to
revised methods including acceleration methods.
This is a major change and appears to be limited
only to the Engineer being able to instruct
acceleration “to reduce delays resulting from
causes listed under Sub-Clause 8.5”. The only other
change is the inclusion of the reference to Sections. Email: taner.d@corbett.co.uk

8.8 [Delay Damages]

The key change to this clause is the inclusion of the


new final paragraph. The first paragraph of Sub-
Clause 8.8 makes it clear that there is a cap on
Delay Damages as stated in the Contract Data. The
last (new) paragraph makes it clear that the cap will
be lifted in the case of fraud, gross negligence,
deliberate default or reckless misconduct by the
Contractor.

8.9 – 8.13

Aside from the change in heading in Sub-Clauses


8.9, 8.10 and 8.11 which now state that these
clauses relate to Employer’s Suspension, there are
no fundamental changes in these clauses. In Sub-
Clause 8.9 [Employer’s Suspension], there is an
additional requirement to state the date and cause
of the suspension. In Sub-Clause 8.10
[Consequences of Employer’s Suspension], whereas
previously, the Contractor was entitled to Cost only,
now there is an entitlement to Cost Plus Profit. In
Sub-Clause 8.11 [Payment for Plant and Materials
after Employer’s Suspension], there are additional
requirements for proving an entitlement for
payment for Plant and Materials. Both Sub-Clauses
8.12 [Prolonged Suspension] and 8.13 [Resumption

2
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
3
CommencementDelaysAndSuspension/TD/2018(1)/8/CLAL www.corbett.co.uk
Clause 9: Tests on Completion
Written by Edward Corbett 1

The Contractor must now prepare a detailed not envisage the valuation of “omitted” work
test programme with timing and resources. which has been performed, albeit defectively.

The Engineer reviews it and the result is a NONO,


deemed or actual, which permits the tests to begin. Article Author
This should help to remove some of the Edward Corbett 2
uncertainties that often can surround tests on
completion.

Clause 9.2 deals with delayed tests, whether the


delays are caused by the Employer or Contractor. If
the tests are “unduly delayed” by the Employer or
Engineer or by a cause for which the Employer is
responsible, it says clause 10.3 “shall apply”.
Email: edward.corbett@corbett.co.uk
This was problematic in 1999 and has not been
fixed. Clause 10.3 provides a threshold of 14 days of
prevention and does not refer to undue delay. A
delay is “undue” presumably if it is not justified; the
issue is the cause rather than the duration of the
delay. So would an unjustified delay of, say, a week
entitle a contractor to the remedies in clause 10.3,
including a Taking-over Certificate? I suppose the
answer is that the clauses need to be read together
and “undue delay” has to be taken to mean 14
continuous or discontinuous days as provided in
clause 10.3.

• Clause 9.2 also provides more procedures


including three Notices. These may prove
beneficial.

• Failure to pass Tests on Completion under


clause 19.4 has been expanded to include
rejection of a Section rather than of the whole
Works. If rejected, the Employer is meant to
recover his money as if the rejected Section had
been omitted under clause 13.3.1. This may
create difficulties as the variations clause does

1
Edward Corbett is a Director at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at edward.corbett@corbett.co.uk
2
The contents of this article should not be treated as legal advice. Please contact the lawyers at Corbett & Co before acting on or relying upon anything stated
in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
TestsOnCompletion/EC/2018(1)/9/CLAL www.corbett.co.uk
Clause 10: Employer’s Taking Over
Written by Andrew Tweeddale 1

The main changes in Clause 10 are the Other changes to note include:
express reference in Sub-Clause 10.1
[Taking Over the Works and Sections] to • “Part” has now become a defined term meaning
the supply of As-Built Records, Operation “a part of the Works or Section (as the case
and Maintenance Manuals and Training as a may be) which is used by the Employer and
requirement of Taking Over. deemed to be taken over under Sub-Clause
10.2.”
• In the 1999 Yellow Book the requirement to
• That when the Taking Over of Part of the Works
provide training and these documents was
occurs the Engineer must immediately issue a
hidden in Sub-Clauses 5.5 to 5.7. This express
Taking-Over Certificate for this Part, which
reference is then coupled with a requirement
identifies the outstanding work to be completed
for the Engineer to issue a Notice of No-
(including Tests on Completion) and/or defects.
objection for the As-Built Records and the
Operation and Maintenance Manuals. • In Sub-Clause 10.3 [Interference with Tests on
Completion], the 14 day period of prevention
There cannot be a deemed Taking Over under
can either be a continuous period or multiple
Sub-Clause 10.1 without these Notices. The
periods which total more than 14 days.
second main change is the addition of the words
in Sub-Clause 10.3 [Interference with Tests on • The referral of a claim for an Engineer’s
Completion], of the failure to carry out any Determination, under Sub-Clause 3.7, has been
“performance test that is not possible due to omitted from Sub-Clause 10.3.
available operating conditions during trial
operation”. • Sub-Clause 10.4 has not been changed; however
the requirement to reinstate all parts of the Site
The unavailability of operating conditions may is now expressly dealt with in Sub-Clause 11.11.
not be due to the fault of the Employer; for
example, there may have been a drought which
resulted in water levels being too low for the
testing of a dam. However, where this occurs Article Author
then, subject to the Contractor issuing a Notice, Andrew Tweeddale 2
there will be a deemed Taking Over of the
Works or Section. Interestingly, because of the
changes in drafting of Sub-Clause 10.1, it
appears that deemed Taking Over occurs even
without the As-Built Records, Operation and
Maintenance Manuals and Training.

Email: andrew.tweeddale@corbett.co.uk

1
Andrew Tweeddale is a Director at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at andrew.tweeddale@corbett.co.uk
2
The contents of this article should not be treated as legal advice. Please contact the lawyers at Corbett & Co before acting on or relying upon anything stated
in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
EmployersTakingOver/AT/2018(1)/10/CLAL www.corbett.co.uk
Clause 11: Defects After Taking Over
Written by George Rosenberg 1

While the general shape of the Clause has gives a right to the Employer to an
been left unchanged, it has been extension of the DNP where the fault is that
substantially elaborated. Many of these of the Employer.
changes do increase its clarity, but some of
the interfaces with other changed Clauses in The negatives:
the Contract produce outcomes which were
perhaps not intended. • There is a cross reference to Sub-Clause 7.5
[Defects and Rejection] to make it apply
The positives: when defects or damage have occurred and
there is a need to remedy. Sub-Clause 7.5 is
• In several Sub-Clauses where the 1999
not well adapted to this situation
edition was not specific about the needs for
• The allocation of cost when the loss or
notices and periods, detailed provisions
damage is not the Contractor’s
have been included.
responsibility now cross-refers to Clause
• There is reference to a DNP for Parts.
13.3.1 [Variation by Instruction] and this
• A suspension which is the fault of the may cause some confusion and raises the
Contractor no longer prevents the extension possibility that the previously unrestricted
of the DNP. Employer right during the DNP to have
• The consequences of failure to remedy have defects and damage remedied and sort out
been elaborated and, from the Contractor’s the costs consequences later has been
point of view slightly ameliorated. undermined.
• There are clearer time limits and there are • The previous position that the contract
provisions to deal with delay or failure to could be terminated and the cost recovered
meet time limits on the Employer’s part. by the Employer where a part of the Works
could not be used for its intended purpose is
Change of risk allocation:
now dealt with as though it were an
• Delay by Employer may entitle the omission, but the consequences of this are
Contractor to Costs plus Profit (in the light of Sub-Clause 13.3.1) confusing.
• Liability for loss or damage to Plant is now • The provisions allowing the Employer to
limited to 2 years after expiry of DNP omit or terminate where the works do not
• The Employer is entitled to recover cost of perform as intended do not clarify what the
reinstating and cleaning the Site, if the intention is. This contrast with the re-
Contractor fails to do so. worded definition of Fit for purpose in Sub-
• The Contractor is for the first time entitled Clause 4.1.
to compensation where it is denied timely • There are some examples of unclear
access to the Site to carry out repairs. drafting which may open the meaning to
• Suspension of work on erection of Plant or dispute.
delay in delivery of materials no longer

1
George Rosenberg is a Consultant at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at george.rosenberg@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
Defects After Taking Over/GR/2018(1)/11/CLAL www.corbett.co.uk
Sub-Clause 11.1 [Completion of Outstanding as review by the Employer. As a result, an
Works and Remedying of Defects]: elaboration of procedure which ought to have been
helpful now creates a confusion which was not
In wording which effectively adopts the same intent previously present.
as the 1999 equivalent provision, the Contractor
may be required by the Employer to remedy all However even this would not have entirely solved
defects or damage occurring during the DNP. the problem. the relevant paragraphs of Sub-Clause
Whereas previously this only referred to the DNP 7.5 rely for their workings on the power of the
for the Works or a Section it now sensibly includes Engineer to instruct (a power which the Contract
the DNP for a Part. gives exclusively to the Engineer (see Sub-Clause
3.5)) under Sub-Clause 7.6 [Remedial Work] and
However, although the language in Sub-Clause 11.1 creates rights for the Contractor to claim
appears to be unequivocal, a provision in Sub- compensation in the case the need for the remedial
Clause 11.2 (see below) may limit this obligation in work is caused by the Employer or Exceptional
a way which did not previously apply. Events. In contrast Sub-Clause 11.2 provides for
such compensation where the cause is “other” than
This Sub-Clause is elaborated by setting out a the list included (all faults of the Contractor).
procedure when the Employer discovers a defect or Thus, the compensation rights under Sub-Clause
Damage. This requires a joint inspection, a 7.6 may be more limited than under 11.2. It is not
proposal by the Contractor and then a process for clear which will apply.
remedying the defect by cross reference to Sub-
Clause 7.5 [Defects and Rejection]. The 1999 Further under Sub-Clause 7.5, where a Contractor
Edition merely required the Employer to notify the does not follow an Engineer’s instruction, the
Contractor and later provisions (which have been Employer has the right to have the work carried out
largely duplicated in the 2017 edition) then dealt at the cost of the Contractor. It is not clear why it is
with the Contractor’s obligations and what would necessary to cross refer to Sub-Clause 7.5 for this
happen if the Contractor failed to abide by them. purpose as later provisions of Clause 11 cover the
same ground.
The notification and joint inspection provisions are
useful additions, but the cross-reference to Sub- The paragraphs imported into Sub-Clause 11.1 from
Clause 7.5 merely creates confusion. Sub-Clause 7.5 also allow the Engineer, by Notice,
following a proposal from the Contractor to reject
Sub-Clause 7.5 provides for a proposal to be the design, Plant Materials or workmanship and
Reviewed by the Engineer. It should be noted that the paragraph refers back to Sub-Clause 11.4(a).
“Review” is a defined term and refers to a This allows the Employer to remedy the defects at
procedure carried out by the Engineer. the Contractor’s cost. This cross-reference works.

Thus, Sub-Clause 7.5 gives powers to the Engineer Finally, the Sub-Clause 7.5 power requires the
(which is of course appropriate where the Works Contractor to carry out any subsequent re-testing,
are still underway) but does not give powers to the whereas Sub-Clause 11.4(a) allows the Employer to
Employer, who is in charge during the DNP. do the re-testing. It may be that the requirement
Presumably the intent is that “Employer” be that the Contractor only carry out the re-testing
substituted for “Engineer” (both in Sub-Clause 7.5 where it has done the remedial work but this is not
and in the definition of “Review” but this is not clear.
spelled out. The result is therefore, arguably, that
the Sub-Clause 7.5 procedure (despite being cross In summary the use of the cross-reference to Sub-
referred to) cannot be applied. It would have been Clause 7.5 creates considerable confusion. It would
better if Sub-Paragraph 11.1 had said that, for this have been much clearer if, rather than relying on a
purpose “Engineer” should be read as “Employer” remedial provision drafted to deal with a situation
under Sub-Clause 7.5 and “Review” should be read which occurred during the carrying out of the

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
Defects After Taking Over/GR/2018(1)/11/CLAL www.corbett.co.uk
Works, Sub-Clause 11.1 had incorporated its own It may be arguable that the unqualified obligation
bespoke procedure. An attempt to avoid confusion under Sub-Clause 11.1(b) to remedy all defects or
by setting out a more elaborate procedure and, at damage overrides the right to object to a variation,
the same time, to save words by cross-referencing but this is by no means clear. Thus, what seems on
has failed. the face of it to be an unqualified right for the
Employer to have the Contractor remedy all defects
Sub-Clause 11.2 [Cost of Remedying and damage, may in fact be limited.
Defects]:
The way this cross reference has been worded is in
The sense of this Sub-Clause generally remains as contrast to Sub-Clause 11.4 (c) which instead of
before. However, there is one deliberate change requiring that Sub-Clause 13.3.1 be applied, states
and one which results (again) from ill thought that it shall be deemed to have been applied and
through cross referencing. As noted above, the the consequences of that are to follow. This would
interface between Sub-Clause 7.5 and Sub-Clause have been a better approach.
11.1 also raises a doubt as to whether the
circumstances in which the Contractor is required Sub-Clause 11.3 [Extension of Defects
to bear the cost may have been modified. Notification Period]:

The deliberate change is that the final circumstance Whereas the 1999 edition allowed an extension
under which the Contractor is said to be wherever the defects or damage affected the Works,
responsible for the cost of remedying defects has the provision has now been critically altered so as
been changed from to only allow the Employer an extension where the
“failure by the Contractor to comply with any defect or damage is the result of one of the acts of
other obligation.” the Contractor listed in Sub-Clause 11.2(a)-(d).
to
“failure by the Contractor to comply with any It is also made clear that the extension of a DNP
other obligation under the Contract.” may not extend more than 2 years beyond the
expiry of the DNP stated in the Contract data.
This potentially reduces the Contractor’s risk.
By reference to Sub-Clause 1.1.27 which defines
The accidental change results from the changes to DNP, that period is either as stated or 1 year. Thus,
Sub-Clause 13.3.1 [Variation by Instruction]. The unless a general provision is inserted in the
1999 edition simply cross referred to the variation Contract stating that the DNP for any Part will be
procedure to deal with the situation where the the same as for a Section or the Works, it can be
remedial work was not to be carried out at the assumed that the DNP for a Part (which by
Contractor’s cost. Now the cross-reference is to the definition does not exist at the time the Contract
Variation instruction procedure. In this case it is a Data is written) will be 1 year, even if the Works or
deeming provision – it is to treated “as if such work Section in which it is included had been agreed to
had been instructed by the Engineer.” This is be longer.
workable under Sub-Clause 13.3.1. However Sub-
Clause 13.1 limits the power to give a variation As with the 1999 edition, a period of suspension is
instruction (see commentary on Clause 13) and not to have the effect of lengthening the DNP
some of the new limits are quite likely to impact period. It starts when it would otherwise have
here, allowing the Contractor to refuse to carry out started. However, this has now been qualified so
the quasi-variation. For example, the limitation on that a suspension which was the fault of the
the right to instruct Unforeseeable varied work is Contractor no longer has this effect. The starting
very likely to apply. How can a Contractor be date has also been modified. Whereas previously it
expected to foresee that the Employer will damage was the date on which the DNP for any particular
the works during the DNP? Plant or Materials would have expired, now it is the
date on which the DNP for the Works would have

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
3
Defects After Taking Over/GR/2018(1)/11/CLAL www.corbett.co.uk
expired. Thus, Sections and Parts have been 2. Where the Employer chooses not to accept
overlooked and a suspension which only applies to the damaged or defective work.
a Part or a Section may no longer fail to extend the
DNP if the Works as a whole have not been (a) The Employer may “require the
suspended.
Engineer to treat any part of the Works
Sub-Clause 11.4 [Failure to Remedy which cannot be used for its intended
Defects]: purpose(s) under the Contract … as an
omission as if such omission had been
This Sub-Clause provides for what happens if the instructed under Sub-Clause 13.3.1.”
Contractor unduly delays remedying any defect or
damage. It has moved in favour of the Contractor The reference to “cannot be used for its
because, under the 1999 edition, it could have been intended purpose(s)” is unfortunate. It
read to apply whatever the cause of the delay. will be remembered that this was the
wording of Sub-Clause 4.1 in relation to
A Notice has to be provided by the Employer and fitness for purpose under the 1999
the reasonable time given must now take account of edition and that the 2017 edition now
all relevant circumstances. defines intended purpose by reference
to the Employer’s requirement and
The consequence of failing to meet this demand has ordinary purposes. This welcome
now been modified as follows: clarification has, for some reason, not
been incorporated here. The same
1. Where the Employer chooses to accept the problem relates to the alternative
damaged or defective work remedy of termination as discussed
below.
(a) If there is any retesting required this will be
carried out by the Employer at the This is another cross reference to Sub-
Clause 13.3.1, so one must refer to that
Contractor’s cost.
Sub-clause to see what it means. The
provision, in this case does not require a
(b) The previous right for the Employer to variation order, but only requires the
require the Engineer to agree or determine Engineer to act as thought there had
a reasonable reduction in the Contract Price been a variation order.
has been replaced by a right under Sub-
Clause 20.2 Cross referring to Sub-clause 13.3.1, it
needs to be remembered that an
a. to claim Performance Damages (if
omission made in order to enable the
these are included in the Contract). Employer to carry out the Works is not
b. If there are no Performance permitted. Thus, the right to apply the
Damages to claim for the price to be present provision cannot apply where
reduced. The amount of the this is the Employer’s intention. Should
reduction is now said to be “in full the Employer not intend to remedy the
satisfaction of this failure only” and omission itself, the only element of Sub-
Clause 13.3.1 which expressly deals with
the amount shall be only “as omissions is that relating to the
appropriate to cover the reduced Contractor’s proposal. As noted in the
value to the Employer as a result of commentary on Clause 13, it is not clear
the failure”. whether the Engineer is obliged to
consider this in setting a valuation. If
the Engineer is so required the

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
4
Defects After Taking Over/GR/2018(1)/11/CLAL www.corbett.co.uk
Contractor is entitled to some The change to policy is that the notice can now be
compensation for the omission which given if “the Contractor considers” it necessary.
would be offset against any reduction in Previously the right was to be judged objectively,
the price. but this seems to give the Contractor more
influence over the decision.
(b) Alternatively, the Employer may
terminate the Contract as a whole with The Notice now required to be given includes
immediate effect “if the defect or details of what needs to be done, where it will be
done, how it will be transported, proposals for
damage deprives the Employer of
inspections and testing and how long the process
substantially the whole benefit of the will take. Although it is likely the Employer would
Works.” The normal termination have asked for all this information anyway before
procedure under Sub-Clause 15.2 is giving consent, it provides a useful check-list.
bypassed. As with the 1999 edition the
Employer is then entitled to a refund Sub-Clause 11.6 [Further Tests after
plus other costs. The new provision Remedying Defects]:
departs significantly from the 1999
While the previous provision required the Engineer
edition in that the right to terminate to decide whether any tests needed to be repeated,
then applied if a major part of the this Sub-Clause is now limited to Tests on
Works could not be used and also gave a Completion and Tests After Completion and now
right to terminate the Contract in requires the Contractor to provide a Notice setting
respect of the part which could not be out proposed tests. Thus, there is no reference to
used. the tests which may be required under Sub-Clause
7.4. This may leave a gap. For example, if there
Thus as a result of this new combination of has been physical damage to a structure which has
remedies, the Employer’s right to terminate is been repaired during the DNP, there is unlikely to
limited but a new right to treat part of the Works as be a Test on Completion or Test After Completion
omitted largely fills the gap. In principle this is a but there might be tests specified elsewhere in the
welcome change and introduces an element of Contract. The Engineer can either agree or give its
workable flexibility. Unfortunately, the wording of own instructions. These instructions may be for
the omission provision leaves some doubt about any tests which demonstrate that the Works comply
precisely how it is intended to work. It is with the Contract and may thus fill the gap
particularly unfortunate that no yard-stick for mentioned above. However, the Engineer will be
“intended purpose” or “whole benefit” has been required to give these instructions without the prior
introduced here. proposal from the Contractor.

Sub-Clause 11.5 [Remedying of Defective There is a default provision allowing the Engineer
Work Off Site]: to give the instruction if the Contractor fails to
provide the proposal.
The Sub-Clause (like that in the 1999 edition)
allows the Contractor, with the Employer’s consent, Sub-Clause 11.7 [Right of Access After
to carry out some remedial work on Plant off-site. Taking Over]:
The policy of this Sub-Clause remains unchanged,
with one exception. Without departing from policy, Again, this follows the policy of the 1999 edition but
but in a useful procedural requirement, it elaborates with one minor change and one
introduces a Notice requirement when the substantial one and some detailed procedural
Contractor wishes to remedy off site. requirements.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
5
Defects After Taking Over/GR/2018(1)/11/CLAL www.corbett.co.uk
The minor change is that the Contractor’s right of There is now a provision deeming that the
access now extends to 28 days after issue of the Performance Certificate has been issued if the
Performance Certificate whereas before it expired Engineer has not done so within 28 days after the
on issue of the PC. DNP is complete and the relevant documents
supplied. The deemed Performance Certificate only
The major change is that the Contractor is now comes into effect after a further 28 days.
entitled to claim Cost plus Profit if the Employer
delays access. Sub-Clause 11.10 [Unfulfilled Obligations]:

The Notice requirements require reasonable Like the equivalent 1999 provision, both parties
advance notice with details of what is required. The remain liable after the issue of the PC for any
Employer is entitled to propose a reasonable unfulfilled obligations. However, this is now
alternative date, but is deemed to give consent to limited to 2 years for Plant after the end of the DNP
the Contractor’s requested date if it does not for that Plant, unless this is prohibited by law or in
propose an alternative within 7 days. case of fraud, gross negligence, deliberate default or
reckless misconduct.
Sub-Clause 11.8 [Contractor to Search]:
Presumably the reference to “prohibited by law” is
This is again similar to that in the 1999 edition but intended to catch situations where the law provides
with a procedural addition and a remedy for the for a mandatory period of liability.
Employer if the Contractor fails to meet its
obligation. Sub-Clause 11.11 [Clearance of Site]:

Under the 1999 edition the Engineer could This Sub-Clause extends the 1999 version by
“request” a search for causes of defects. Now the including an obligation to reinstate and clean. In
Engineer “instructs”. This instruction will include a view of this extension the Employer is given the
date which, in the absence of agreement, must be right to recover the cost of reinstatement and
complied with. cleaning if the Contractor does not do so.

If the Contractor does not carry out the instructed The right to sell items left on the Site is now limited
search the Employer may do so and recover its to those situations where this is “permitted by the
reasonable costs. applicable law”. It is not clear what is meant here.
It would have been clearer to say “not prohibited by
Sub-Clause 11.9 [Performance Certificate]: mandatory law”

The Performance Certificate is to be issued when


the Contractor has “fulfilled the Contractor’s
obligations” under the Contract. The 1999 edition
equivalent stated the test as “completed his
obligations”. It is not clear what difference the
change in wording means.

The PC now has to be issued not only to the


Contractor and Employer but also to the DAAB.
Whereas, previously, it was only a precondition
that all Contractor’s Documents had been supplied,
it is now also a requirement that the Engineer has
given a Notice of No-objection to the as-built
records.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
6
Defects After Taking Over/GR/2018(1)/11/CLAL www.corbett.co.uk
Article Author
George Rosenberg 2

Email: george.rosenberg@corbett.co.uk

2
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
7
Defects After Taking Over/GR/2018(1)/11/CLAL www.corbett.co.uk
Clause 12: Tests after Completion
Written by George Rosenberg 1

Clause 12 deals with Tests after Completion. requirements. If they are not, they may not be
able to operate and thus test it to its required
• It is more common overall for Tests on efficiency and the test results will be
Completion to be the final test required rather misleading. Indeed, if they are the same people
than Tests after Completion. However, tests who have been running the plant for some time,
after completion are commonly required for their lack of competence may have contributed
process and power contracts. There may, for to any short-fall in performance.
example be a requirement for a “reliability” test
during a period of initial functioning. • In the event that the Contractor disagrees with
Sometimes the tests are required to be carried the results and can identify any lack of
out in different seasons of the year to test competence on the part of the Employer’s
functioning under different conditions – testing team, it will be able to take issue with
whether from weather or load. the results of the Tests. Since the competence
of the testing staff is an element of the
• Thus, by definition, the Plant is likely to be requirement for testing, the mere fact that the
under the control of the Employer by the time Employer’s testing staff do not meet the
the Tests are to be carried out. The Yellow Book standard required ought to be sufficient
thus assumes that the tests will be carried out argument to say that the Employer is not
by the Employer, although the results will entitled to rely on the tests. This is even
potentially lead to obligations being imposed on without proving that the Plant would, if
the Contractor. properly tested, have met the required
standards.
• There are few changes from the 1999 edition
but these few are significant. • A further and sensible new provision requires
that the tests be carried out in accordance with
• There is a new obligation for the Employer’s the Employer’s Requirements and the O&M
staff who carry out the test to both competent Manuals to which the Engineer has given (or
and able to carry out the tests properly. This is “deemed to have been given” sic 2 ) a Notice of
significant. No-objection under Clause 5.7.

• By the time these tests are carried out, the • The tests are (as before) to be carried out in the
relevant element of the Works will have been presence of the Contractor if the Employer or
completed and operational and obviously any the Contractor so requests.
tests carried out by people who do not meet
these qualifications may be of doubtful value. • There is new provision enabling the timing of
This is a serious issue where the Works include Tests after Completion to be provided for in the
complex Plant, because, at least immediately ER’s and for the Engineer (previously the
after the time of taking over, it is quite possible Employer) to provide the Contractor with
that the Employer’s staff (probably those who notice of the date and a programme for the
will eventually run the Plant) may not be timing. Given that the tests are to be carried
sufficiently experienced to meet the out by the Employer, not by the Engineer and

1
George Rosenberg is a Consultant at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at
george.rosenberg@corbett.co.uk 2 This appears to be an error as the Notice of no-objection is given by, not to, the Engineer.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
TestsAfterCompletion/GR/2018(1)/12/CLAL www.corbett.co.uk
the Engineer is not expected to be present, it is Failure to Pass Tests after Completion (12.4)
not clear why the Engineer has replaced the
Employer in this provision. One of the options under the equivalent 1999 Sub-
Clause was for the Contractor to pay any prescribed
Delayed Tests (12.2) non-performance damages. He would then be
released from any obligation to remedy the
There are no changes. discovered shortfall in performance. The redrafted
Sub-Clause gives the Employer the option as to
Re-testing (12.3) whether or not to demand this payment. Thus, the
previous escape route for the Contractor to avoid
The previous provision regarding re-testing (12.3) having to carry out remedial works may be closed
is now said to be subject to Sub-clause 12.4 [Failure off.
to Pass Tests after Completion]. Clause 12.4 allows
for the imposition of Performance Damages or for The process for the Employer to seek payment of
the Contractor to remedy the non-performance the Performance Damages requires a Claim under
discovered in the tests. The effect of making 12.3 Clause 20.2. This is a very significant change from
subject to 12.4 appears to be quite significant as it the previous position because the claim is now
now seems to be possible for the Employer to by- subject to the 28 day condition precedent. Once
pass the Contractor’s right and obligation under the Employer knows the tests have failed he must
Sub-Clause 11.1 to remedy defects and simply levy make his claim, otherwise he will lose the right to
Performance Damages. Performance Damages altogether. As noted above
the provision for re-testing is subject to Clause 12.4
Should the Employer not choose to go straight to a and it seems arguable that the 28 day period for
demand of damages there is another anomaly. claiming Performance Damages may start as soon
Sub-Clause 12.4 gives the Contractor an option to as the failure to pass the test under 12.3 is
remedy defects. The conditions under which an apparent, even if the Employer decides to insist on
11.1 remedy has to be carried out are different from a remedy under 11.1. Although (as noted below)
those under 12.4. Under the latter (which is Sub-Clause 12.4 goes on to give the Contractor the
especially designed to deal with the situation where option to seek to remedy any deficiencies, such a
the Employer is in occupation and operating) the request by the Contractor would not seem to give
Employer is entitled to delay access to the Employer further time to make his claim for
accommodate its operational requirements. There Performance Damages.
is no equivalent provision in 11.1
Payment of Performance Damages is said to lead to
Should remedy be required by the Employer under the result that the works are deemed to have passed
Sub-Clause 11.1 [Defects Liability], the 1999 the Tests after Completion.
provision allowed either party to request repeated
tests under 12.1 – i.e. as a Test on Completion and The second part of Sub-Clause 12.4 is unchanged
thus carried out by the Employer. The new from the 1999 edition but it is necessary to discuss
provision now provides that the repeated testing the implications of the change to the first part of
provisions in Clause 11.6 shall apply instead. the Sub-Clause. When payment of Performance
Although 11.6 requires tests to be carried out in Damages was a Contractor option it was logical to
accordance with Clause 12, notices are given not by provide (as an alternative) that the Contractor
the Employer, but by the Engineer and are directed could proceed to remedy any issues at its own
to the Contractor not to the Employer (who will expense. This is what the second part envisages.
carry out the tests). Since the choice of whether or not to claim
Performance Damages is now that of the Employer,

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
TestsAfterCompletion/GR/2018(1)/12/CLAL www.corbett.co.uk
it is much more difficult to see how the Sub-Clause
works. If the Employer does not claim Performance
Damages (whether accidentally or deliberately), the
Contractor will remain liable under the general
principles of damages for default, to meet the
Employer’s resulting losses. Thus, what was
previously a choice now becomes an obligation and,
unless the Contractor prefers to face a general
damages claim 3 it will be obliged to remedy the
defects.

Article Author
George Rosenberg 4

Email: george.rosenberg@corbett.co.uk

3 4
Since Performance Damages are a liquidated sum it would be possible, The contents of this article should not be treated as legal advice. Please
at least under English law, to argue that they provide a cap on liability for contact the lawyers at Corbett & Co before acting on or relying upon
damages, even though the Employer no longer seeks them. anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
3
TestsAfterCompletion/GR/2018(1)/12/CLAL www.corbett.co.uk
Clause 13: Variations and Adjustments
Written by George Rosenberg 1

The Power to Vary and its Limitations foresee. It is thus difficult to see how any variation
at all could fail to be caught by this test.
While the process of ordering a variation has not
changed dramatically, the 2017 edition Two significant limitations now expressed for the
substantially clarifies the limits on (some may say first time allow the Contractor to object where the
“additionally limits”) the Engineer’s power to vary. variation may adversely affect its ability to meet
health and safety and environmental protection
Under the 1999 and all earlier editions, the power obligations
to vary was expressed in open-ended terms and it
was left to the underlying law to say whether or not The final provision may also have unexpcted
this power was limited. Most legal systems do consequences. This is set out in Sub-paragraph
recognise that variations cannot depart 13.1(e) which allows the Contractor to object where
significantly from the original scope of the contract. the variation “may adversely affect the
Under English Law there is probably an implied Contractor’s obligation to complete the Works so
term, based on the concept of business efficacy, that they shall be fit for the purpose(s) for which
that instructions should be reasonable and not they are intended in accordance with Sub-Clause
stray ‘outside the Contract’. However, this was not 4.1 [Contractor’s General Obligations].”
spelled out and always left room for argument. Sub-Clause 4.1 imposes on the Contractor the
obligations:
In a change which will be welcome to Contractors
they are now given an express right to object when • To execute the Works in accordance with the
the varied work was “Unforeseeable having regard Contract. This would normally require
to the scope and nature of the Works described in obedience to VO’s, but Sub-Paragrpah 13.1(e)
the Employer’s Requirements.” This is a provision creates an exception.
that is capable of dramatically changing the concept
of what may be the subject of a Variation under the • To ensure that “when completed the Works
contract. “Unforeseeable” is defined in Sub-Clause shall be fit for the purposes for which they are
1.1.87 as “not reasonably foreseeable by an intended as defined and described in the
experienced contractor by the Base Date”. “Base Employer’s Requirements”.
Date” is the date 28 days before submission of
tender. Sub-Clause 13.3.1. adds the additional gloss The language here is different from that used in the
that regard must be had to the scope and nature of 1999 Edition and, in the context of Variations, this
the Works as described in the Employer’s causes important consequences. The 1999 Edition
Requirements. required the Works, when completed to be fit for
the purposes “as defined in the Contract”. As a
While an experienced contractor will assume that Variation changed the effect of the Contract, the
there will be some variations during the course of fitness for purpose obligation adjusted accordingly.
the Works, he would have to be possessed of quite It can be seen that, under the 2017 edition a
extraordinary foresight to know what each one of Variation, would have to specifically amend the
these would be. By definition a variation is likely to Employer’s Requirements if it were intended to
be something which the Employer, advised impact the purpose for which the Works are
(hopefully) by an experienced engineer also did not

1
George Rosenberg is a Consultantat Corbett & Co. International Construction Lawyers Ltd. He can be contacted at george.rosenberg@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
VariationsAndAdjustments/GR/2018(1)/13/CLAL www.corbett.co.uk
intended. In the absence of a change to the Objections by the Contractor
Employer’s Requirements, a change which affects
the ability of the Contractor to achieve the purpose There is also a new and clarified procedure for
intended as defined in the Employer’s objection by the Contractor. Unusually for the 2017
Requirements is a ground to refuse to comply with edition there are no clear time limits for this
the Variation instruction. process. The Contractor must give notice
“promptly” and the Engineer must also respond
Thus, where the Engineer is faced with an objection “promptly”.
under ground (e), one way of dealing with it would
be to vary the Employers’ Requirements so that the Some of the value for the Contractor is taken out of
Contractor, while carrying out the Variation, can the provision as the Engineer is given the option to
still comply with them. cancel confirm or vary the instruction which will
then be treated as a Variation, even if it in fact
Sub-Clause 1.1.33 [Employer’s Requirements] continues to exceed the Engineer’s powers.
defines the term and includes the document
included in the Contract and “any additions and If the Engineer chooses to cancel, there is clearly no
modifications to such documents in accordance problem. If he chooses to vary and the Contractor
wih the Contract.” still finds there is an objection, there seems to be no
reason why the Contractor cannot again give notice.
However Sub-Clause 3.2 prevents the Engineer However, if the Engineer chooses to confirm the
from amending the Contract or “to relieve either instruction, this effectively means that it is rejecting
Party of any duty, obligation or responsibility the Contractor’s assertions. There will thus be a
under or in connection with the Contract.” dispute between the parties as to whether or not the
Contractor’s complaint is valid.
There is thus a question as to whether a Variation
can override Sub-Clause 3.2 by empowering the As the right to refuse is an absolute one, a brave
Engineer to vary the Employer’s Requirements Contractor might continue to refuse to perform the
(which in this case would have the effect of Variation. The safer course will be to continue and
relieving the Contractor of one of its obligations carry out the Variation instruction. In those
under the Contract.) circumstances the Contractor will certainly have
put the Engineer on notice that the Variation is
There is nothing in Sub-Clause 13 which says this likely to be costly and/or cause significant delay or
and it therefore has to be assumed that the that the adequacy of the final product will be
Engineer cannot amend the Employer’s adversely affected unless the Contractor makes
Requirements. other changes in order to achieve safety, its
guarantees or fitness for purpose obligations, for
In order to overcome this difficulty, the Employer the Cost of which it intends to claim.
will need to attempt to reach agreement with the
Contractor and enter a supplemental agreement. The additional cost may arguably be included as
This puts great bargaining power into the part of the valuation of the Variation (see below) or
Contractor's hands and may mean in practice that a may only be claimable on the basis of an allegation
variation which may require a change to the that the Engineer has exceeded his authority. It is
Employer’s Requirements is not possible. particularly important for the Contractor to take
care in these circumstances. As will be seen below,
the valuation of a Variation takes place without the
need for the Contractor to give a notice under
Clause 20.2. However, a claim for breach of

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
VariationsAndAdjustments/GR/2018(1)/13/CLAL www.corbett.co.uk
contract does require a Clause 20.2 Notice. Thus, if The Process of Variation
a Contractor has given notice and the Engineer has
confirmed the instruction, the Contractor should The 1999 edition provided that VO’s could be
immediately give notice under Clause 20.2 commenced by either a direct instruction or by a
(repeating what it has said in its notice under the request for proposal followed by instruction. The
present Sub-Clause and adding any additional 2017 edition follows the same model.
relevant information) so as to set the basis for a
claim for additional payment and an extension of Valuation of Variations
time if the Engineer later declines or fails to include
the additional costs in its valuation of the VO. Following an instruction to vary, the Contractor is
required to provide details of his planned reosurces
Variation as an Instruction and emthods, an execution programme and any
need to time extension and its proposal for
There is a linkage with Sub-Clause 3.5 [Engineer’s adjustment to the Contract Price.
Instructions]. This is because a Variation is one
form of instruction. 3.5 now contains a welcome Price Proposal – to be Taken into Account?
clarification (in this case probably more welcome to
the Employer than to the Contractor) of what the The obligation to submit a price proposal is set out
Contractor may do if he considers an instruction in Sub-Clause 13.3.1(c). This Sub-Clause is one of
which the Engineer does not call a Variation in fact the few in the contract which is said by Sub-Clause
amounts to a variation. In that case he must, 1.15(b) to leave open liability on the part of the
immediately and before commencing work, give Employer for loss of profit, loss of any contract or
notice to the Engineer and the Engineer has 7 days any indirect or consequential loss or damage. It
to confirm, reverse or vary the instruction. would seem therefore that the Contractor is entitled
to include such losses and damages in its proposal.
The requirement of “before commencing work”
may be hard to comply with in practice, particularly This is therefore one way in which a Contractor can
in the common situation where a co-operative seek compensation for a loss caused to it by an
Contractor begins work on an urgent Variation on Unforeseeable variation or by other abuse by the
the basis of a promise by the Engineer that a formal Engineer of its power to vary. However, the right
VO will follow. As with Cause 13.1, it is not clear goes further than that. As will be seen below the
what is to happen if the Engineer confirms an valuation methods open to the Engineer are very
instruction as not being a Variation when it should restrictive and do not, in some instances, allow it to
have been a Variation. take into account price increases which may have
occurred since the Tender. Even a legitimate VO
Where an instruction is not stated to be a Variation, may be costly to the Contractor in ways beyond the
Clause 3.5 also adds additional rights to objection direct cost of the work itself – for example if it
to those in Clause 13.1 – the Contractor can object means that it has to use resources which it would
on the basis that the instruction does not comply otherwise have been able to deploy more profitably
with applicable Laws or is technically impossible. elsewhere.
Quite why these grounds of objection are not
applied to Variations also is unclear. There will be If the Engineer is required to take the proposal into
some interesting arguments to come on the account in making its valuation, this opens the door
consequence of this omission from the limits on the some very substantial claims from contractors.
power to vary. However, the remainder of Sub-Clause 13.3.1 does
not explicitly answer the question as to whether the

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
3
VariationsAndAdjustments/GR/2018(1)/13/CLAL www.corbett.co.uk
Engineer is required to take account of costs etc days to give his determination. However, these 84
included in the proposal in its eventual evaluation. days may have expired before the Cost plus
The answer as to whether or not the Engineer has information necessary to make the determination is
this obligation is perhaps found again in Sub- available.
Clause 1.15(b). If a proposal does not create a
liability, why would there be a need to exclude it The Engineer may be faced with the impossible
from the general prohibition on imposing liability dilemma of whether to issue a determination
for loss of profit etc.? It appears that the without the necessary information or to fail to
assumption is that the Employer will be required to make a determination at all. In either case the
take the proposal into account. issue may then become a dispute to be referred to
the DAAB. It is not clear whether the DAAB has the
Further support for this position comes from the power to take into account the Cost information
fact that Sub-Clause 13.3.1(c) is the only place which may have finally become available before it,
where the Contractor’s right to compensation in the in turn, is obliged to reach a decision. Indeed, in
case of an agreed omission is to be found and, if it the case of a major Variation it is quite possible that
were not to be taken into account in the valuation it the DAAB itself will not have enough information
would be meaningless. even assuming it can take into account the
information which has become available in the
Method of Valuation meantime. The same problem continues into the
arbitration process.
The 1999 edition was notably vague about how the
Engineer was to go about valuing the variation and These problems can be resolved by the Engineer by
this often led to argument. One approach under demands for further information before a decision
the 1999 (and earlier editions) would have been to is given or by agreement of the parties to extend the
assess the value using the tender as a comparator. time limits for determination. Time only starts to
Alternatively, the new work could have been valued run once all requested information has been
on the basis of Cost plus profit. The new edition received from the Contractor (a real incentive for
sets out two methodologies. One applies where the Contractor to respond promptly). However,
there is no schedule of rates and prices (not Engineers will need to be very alert to the need to
unusual in a D&B contract) and one where there is. demand full particulars of actual costs so as to
In the former case valuation is on a Cost plus basis. avoid time starting to run for their determinations.
In the latter the rates are to be used unless there is
no relevant item, in which Cost plus again applies. The Engineer is obliged to assess a provisional rate
for interim payments pending agreement or
The new valuation methodology where there are no determination. This is a new provision which is
rates and prices comes as a surprise as it ties the welcome and at least ensures that the Contractor
Engineer’s hands to a method which may will receive some of his entitlement.
substantially favour one party or the other when
tendered prices would previously have been used as In this situation, there is one specifically relevant
the basis. consequence of the new-found “neutrality” of the
Engineer in reaching determinations. Unlike the
The valuation of the variation is (as before) fixed by situation under the 1999 and previous editions, the
an Engineer’s Determination. This may have what valuation is no longer made by the Engineer acting
is probably an unintended consequence when Cost as agent of the Employer. Thus, for the first time,
plus has to be applied. Under the new time limits the Employer has equivalent rights to the
set out in Sub-clause 3.7 [Engineer’s Contractor to challenge a valuation of a variation
Determinations] the Engineer has a maximum 84 made by the Engineer.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
4
VariationsAndAdjustments/GR/2018(1)/13/CLAL www.corbett.co.uk
There is a provision of Clause 14 which might have As with the 1999 edition the Engineer is not
been better placed in Clause 13 and of which permitted to use a Variation Order to omit work
Engineers need to be aware. Clause 14.15(b) which is to be carried out by others. The new
provides that where a variation is valued the edition clarifies this by making it impermissible for
amount to be paid in different currencies must be work to be omitted where the intention is for the
specified and this must be done by reference to the Employer himself to carry out the same work.
expected currency proportions of the Cost of the
varied work. This is a sensible provision in There is now express provision for the parties to
principle but assumes that valuation can be done agree on the omission of work. In these
before the actual work has been carried out and circumstances the Contractor is entitled to propose
that all Variations are valued on Cost (which, as an amount of compensation for loss of profit or
noted above, they are not). other compensation for the omission. There is
some doubt as to what will happen if the Contractor
Notices fails to include such a proposal. Indeed, there is no
direction to the Engineer to consider this element
There is now no requirement for the Contractor to of the proposal. Rather unfortunately, where there
give notice under Clause 20.2 if it wishes to seek an is no agreement on the omission there is no express
extension of time consequent on a Variation. This right to propose such an amount. However, an
has always been the case for valuations but is now omission in order to carry out the works by
expressly stated for time as well. It should be someone else would be a deliberate breach of
noted, however, that this exemption from the contract and under Sub-Clause 1.15 is excluded
requirement to give notice does not apply to the from the general prohibition on claims for loss of
other provisions of Clause 13 (Provisional Sums, profit and indirect or consequential loss.
Daywork, Adjustments for Changes in Laws).
Variation by Request for Proposal
Under these latter provisions it may be arguable
that the Contractor is obliged to give notice, even in The 1999 edition gives the Engineer the option to
order to get its entitlement for cost adjustments. It ask for a proposal prior to instructing a variation.
is certainly required for applications for extensions The new procedure is spelt out more clearly but
of time. A trap for the unwary Contractor who may does not change the process significantly. As before
be lulled into a false sense of security by the lack of there is no general provision for compensation for
a need for such notice for Variations proper. the Contractor to be compensated for the (possibly
considerable) cost of preparing a proposal.
Prolongation and Disruption arising from
Variations However, there is now an exception to this in the
situation where the Engineer does not give consent
As with the 1999 edition there is no provision for to a proposal. Contractors should note that, unlike
compensation for prolongation or disruption costs the right to evaluation of payment, this right is not
arising from variations. It remains the case exempt from the requirement for a Sub-Clause 20.2
therefore that it is very arguable that in the absence Notice.
of specific provision, these costs will not be
compensable. Indeed, if there was any room for Value Engineering
argument under the earlier edition, this is now
removed by the prescriptive provisions about the Value engineering under the Yellow and Silver
way in which variations are to be valued. Books was thankless under the 1999 forms.
Omissions Under the Red Book, the Contractor could earn
50% of the net benefit. Here all the forms leave it to

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
5
VariationsAndAdjustments/GR/2018(1)/13/CLAL www.corbett.co.uk
the Special Provisions to set out any sharing of “the truncated by the time the Contractor takes to issue
benefit, costs and/or delay”. However even where his Clause 20.2 Notice. In the case of applications
these are set out the Engineer is not obliged to take for extensions of time, time may start at a different
them into account, only to “include consideration” point, so the Engineer’s time limits may expire on
of them when he issues a Variation. This is very different days.
vague language. If the Engineer’s “consideration”
leads it not to include any sharing in its ultimate Adjustments for Changes in Law
valuation there seems to be no basis for a change
either through the Sub-Clause 3.7 procedure or • As under the 1999 edition, the Contractor may
through a DAAB. be entitled to compensation in money or time
for the consequences of changes in law.
Provisional Sums
• The scope of what may be considered Changes
There is new provision allowing the Engineer to in Law is expanded beyond what was included
require the Contractor to produce quotations from in the 1999 Edition and now includes:
suppliers. - The Laws of the Country
- Not only judicial or government
Daywork interpretation of such Laws but also their
implementation.
The process for dealing with quotations is usefully - Permits, permissions, licenses or approval
spelled out in more detail. obtained by the Employer or the Contractor.
These are not limited to those of the
Daywork is described in the sub clause as a Country.
Variation and the cost consequences (though not
time) in cases of disagreement are, for the first • The last of these may be the most significant as
time, to be determined under Clause 3.7. it will extend to planning and environmental
requirements and may potentially apply to
Whereas the Contractor is entitled to have the value matters arising outside the Country. In
and time consequences of other variations addition, in an international project, the
determined under Clause 3.7 without the Contractor is as likely to be affected in another
requirement for a notice under Clause 20.2, there is country as in the country where the Works are
no such exception in the case of Dayworks. actually being performed – much of the
Contractors are going to have to be very careful to manufacture may be taking place off-shore and
ensure that they adapt to the new procedure by materials and labour may well be being
giving Clause 20.2 notices whenever they need to procured elsewhere and may be affected by
have dayworks valued and/or require an extension regulatory requirements off-shore. The
of time. application of this provision to such permits
licenses or approvals thus represents a
Sensibly (and in contrast to the procedure for other potentially significant change to the balance of
Variations), time for the Clause 3.7 determination risk.
starts to run from when any disputed dayworks are
completed and their value can easily be • It should be noted that permits obtained by the
determined. However, there is no special Employer are at the expense of the Contractor
provision dealing with the start of the 28-day (Clause 1.13(b)). Thus the Contractor will need
period for giving Notice under Clause 20.2. The to be vigilant to check whether a permit may be
effect appears to be that the Engineer’s time for the result of a change of law and the cost thus
considering any disputed valuations will be reimbursable.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
6
VariationsAndAdjustments/GR/2018(1)/13/CLAL www.corbett.co.uk
• In contrast to the 1999 edition, the Employer is
Article Author
now given the right (subject to a Clause 20.2
Notice) to recover any benefit which the George Rosenberg 2
Contractor may have received as a result of any
changes in Laws.

• Unlike in the case of Variations, there is no


waiver of the requirement to give Notice under
Clause 20.2 when seeking time or money
compensation.

• Finally, there is a new provision which enables


either the Contractor or the Engineer to trigger Email: george.rosenberg@corbett.co.uk
a Variation where a change in Laws requires an
adjustment to the execution of the Works.
There is no fixed time limit for giving such
notice. The term used is “promptly”, but the
starting point for such “prompt” notice may be
subject to some controversy. Nothing is said
about what happens if a party fails to trigger
such a Variation and it may well be that the
general right for the Contractor to be
compensated in Cost and time for such changes
will mean that (subject to timely notices) the
Contractor will be entitled to compensation
even if it does not trigger a Variation.

Adjustment for Changes in Cost

The 1999 edition included detailed methodology for


the calculation of such changes. This is now
omitted, and the parties are expected to include
their methodology in a schedule to the Contract
(without which the right to adjustment will not
apply).

2
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
7
VariationsAndAdjustments/GR/2018(1)/13/CLAL www.corbett.co.uk
Clause 14: Contract Price and Payment
Written by George Rosenberg 1

This important clause sets out the method of of Retention Money and the amount which the
payment, certificates and release from Employer is entitled to be paid for use of
liability. Temporary Utilities.

The overall methodology has not changed but there Presumably because Sub-Clause 21.4.3 requires
are several procedural adjustments and some that any money awarded by a DAAB shall be paid
inconsequential tidying. Some of the procedural without the requirement for any certification or
changes will be welcomed by Contractors but Notice, there is (in contrast to the 1999 Edition) no
several will entail further delay in payment to the specific reference to such amounts in the list of
items which are to be included in the Statement.
Contractor. There is a determined effort to ensure
Nonetheless, Contractors should include such
that all claims are dealt with during the contract
amounts as this will bring into effect the right to
period or very shortly thereafter. interest under Sub-Clause 14.8, running from the
date of the decision. There is no provision for
Advance Payment Guarantee (14.2) payment of interest unless a DAAB award is
included in this way.
There is a new sub-clause specifically dealing with
advance payment guarantees. The most significant A new requirement has been added to the detail
change (a very useful one for the Employer) is that that the Contractor is required to provide. This
where a guarantee has to be extended and the stated as “sufficient detail for the Engineer to
Contractor fails to do so, the Employer may call it investigate these amounts”. While this is obviously
in to the extent that any part of the advance a useful and sensible requirement it has significant
payment has not been repaid. implications.

The Advance Payment is to be made within 35 days For the first time an element of subjectivity is
of the Contractor’s providing his application included in the requirements. It is quite possible
together with the Performance Guarantee and that the Engineer and the Contractor will disagree
Advance Payment Guarantee. This contrasts with about what is “sufficient” or what the Engineer
42 days under the 1999 edition. needs to investigate any amounts claimed.

Interim Payments (14.3) Should there be such a disagreement and the


Engineer demands additional information, the time
The 1999 edition referred to applications for for payment under Sub-Clause 14.7 does not start
interim payment certificates. This terminology is to run until the relevant information has been
now gone. Now there is a Statement which is then received (there will, arguably, be a short-fall in the
followed by the IPC. (the term “IPC” is used supporting documents). Not only may the
throughout). Contractor be paid later than it would otherwise be
entitled, but it will also be limited in any claim for
The statement was formerly required in 6 paper financing charges under sub clause 14.8.
copies. Only 1 hard “original” is now required, Unfortunately, it is not uncommon for Engineers to
coupled with an electronic copy. be slow in issuing IPC’s, especially when the
There then follows a list of the items which have to Employer is having payment difficulties.
be included in the Statement. These have been The Contractor would be very unwise not to comply
expanded to include Provisional Sums, any release with any demands for additional information, even

1
George Rosenberg is a Director at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at george.rosenberg@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
ContractPriceAndPayment/GR/2018(1)/14/CLAL www.corbett.co.uk
if it considers the demands unreasonable, but, even the Schedule of Payments was based. If the
then, there may be a consequent delay in payment. Schedule simply provides for fixed payments on a
monthly basis there will be the possibility of a
It will be difficult for the Contractor to do anything dispute as to what progress was assumed in the
which will speed payment in these circumstances (a Schedule of Payments. The Contractor’s principal
Notice under Sub-Clause 16.1 would be a drastic obligation is to complete on time, not necessarily to
but possible remedy) but it will have the basis of a conform to the programme and it is arguable that if
claim for Financing Charges. To gain these it will
it decides to change the way in which it will achieve
need to initiate a dispute under Sub-Clause 20.2 –
timely completion this does not mean that the
a time-limited right so notice needs to be given
within 28 days of the Engineer wrongly refusing to agreed schedule of payments is inappropriate.
accept additional information as sufficient for it to
investigate. Where there is a Schedule of Payments, payments
for Plant and Materials intended for the Works (see
However, it should be noted that Sub-Clause 14.6.2 next Sub-Clause 14.5) is disapplied. There is no
requires the Engineer to issue an IPC even in the equivalent provision in the 2017 Silver Book and it
absence of such information, but making a suitable is difficult to see how Sub-Clause 14.5 can work in
deduction to reflect his concerns. (See also the this situation.
discussion under 14.7)
Plant and Materials Intended for the Works
Schedule of Payments (14.4) (14.5)

Under the 1999 edition, the Engineer was entitled Like the 1999 edition, the 2017 edition allows the
to revise a payment schedule only if progress was parties to agree that Plant and Materials may be
less than expected. Now he may amend it if it paid for when shipped or delivered. The Contractor
“differs”. This opens the way to bringing payments simply provides the evidence in his application for
forward if the Contractor is making better than payment and the amount should then eventually be
expected progress. Unfortunately, there is no included in the IPC. Under the 1999 edition the
provision for the Contractor to trigger this word “determination” was used without cross
correction process. However, the trigger date for reference to the (then) Clause 3.5. Once that
the purposes of the Engineer’s Sub-Clause 3.7 determination was made the amount could be
process is when the difference is first “found by the included. Presumably in the interests of
Engineer”. Presumably the Contractor can tell the clarification the Clause now refers to Clause 3.7
Engineer and thus makes sure he/she “finds” it. Determination.
This has the consequence that the Engineer has up
Under Sub-Cause 3.7. however, the time allowed to
to 84 days to make a decision which previously
the Engineer to make its decision is 42 days and the
would have been made immediately and it will no
decision only starts the payment process, so it may
longer be possible to include the amount in the next
be up to 70 days before a change takes effect.
IPC. Even then there will be another 56 days delay
Where the Engineer decides to invoke the process before payment. In addition, the amount to be
(most likely when progress is slower than that on included in the IPC is only 80% of the value of the
which it considers the Schedule of Payments was
based) the Contractor at least has the advantage
that it is entitled to be consulted and that the
Engineer must act neutrally and fairly.

There will be a question of how the Engineer can


determine that progress differs from that on which

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
ContractPriceAndPayment/GR/2018(1)/14/CLAL www.corbett.co.uk
items. 2 It is thus probable that by the time the A further welcome addition from the point of view
application is dealt with under Clause 3.7 the items of Contractors is that the Engineer is now obliged
will have been installed so this causes further cash- to explain why amounts are withheld.
flow issues. The provision was intended to give the
Contractor some early payment but as amended it Where Engineers find significant errors or
achieves the opposite. discrepancies in the Statement they now have a
right to adjust the amount certified to take account
In a sensible and practical change, the requirement of the extent to which this has prejudiced or
for a bank guarantee before the Engineer proceeds prevented a proper investigation. This does not
to determine a payment has been replaced with a amount to a licence simply not to include amounts
promise of a guarantee, but with eventual payment in respect of items where there may have been such
being conditional on the guarantee being provided. an error. All the Engineer is entitled to do is “take
account” of the error. This must be something
Note that (even if the parties have agreed to apply other than simply failing to consider material which
this provision) Sub-Clause 14.4 excludes its contains errors. Presumably this is not intended to
operation when payment is made against a detract from the obligation to act fairly, but exactly
Schedule of Payments rather than against what it will mean in practice remains to be seen.
measured interim payments.
The IPC also includes any amounts determined
Issue of IPC (14.6) under Sub-Clause 3.7. Although there is no specific
statement to this effect here, this provision in fact
The Clause now provides, as a condition precedent, reflects another considerable improvement from
that the Contractor has appointed the Contractor’s the Contractor’s point of view. Virtually all
Representative. employer claims now pass through the Sub-Clause
3.7 procedure, so the situation which prevails under
Content of IPC (14.6.1) the 1999 edition where a deduction is sometimes
made for an Employer claim before the Contractor
The Contractor is now entitled to a copy of each IPC has the opportunity to argue the point has now
and it is specified that the Engineer must explain been remedied.
any differences between the amount applied for
and the amount Certified. Contractors will be very Correction or modification of IPC (14.6.3)
pleased to have an entitlement to this information.
There is a welcome new provision setting out in
It is interesting to note that the requirement for the detail what the Contractor is entitled to do if he
Engineer remains to issue the FPC for such amount does not agree with the IPC. Following the
as he “fairly” considers due, so that while Sub- Contractor’s submissions, the Engineer has an
Clause 3.7 has moved from “fair” to “neutral”, the opportunity to include corrections in the IPC. If he
halfway house of fairness remains in place here. does not do so, or the Contractor still remains
(Clause 14.13 includes the same requirement for unhappy, he is entitled to entitled to ask the
issue of the FPC). Engineer to deal with the matter under Sub-Clause
3.7. There is no time-limit on the Contractor
Withholding (amounts in) an IPC making this request.

2
Note that under Sub-Clause 7.7 property in Materials and Plant does not
pass until they are fully paid for, so this 80% provision means that the
Contractor retains ownership far longer than one might expect.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
3
ContractPriceAndPayment/GR/2018(1)/14/CLAL www.corbett.co.uk
Although the 3.7 process is lengthy in the context of be included in a Statement for an IPC. This
payment, the clear right for a Contractor to pursue inevitably means at least a 56 day delay in refund.
this procedure in the face of a difficult Engineer will
be welcomed by Contractors. Statement at Completion (14.10)

Payment (14.7) This has always been required to include any


amounts the Contractor considers to be due. The
As before the Employer’s time for payment runs particular categories are now spelled out in detail –
from when the application is made by the including claims still being considered by the
Contractor. This is 56 days for all IPC’s except the Engineer and the DAAB. These are only given as
Final Payment Certificate. Confusingly the Sub- examples but the list contains considerable gaps –
Clause includes two separate time limits for for example amounts where an NOD is likely to be
payment under IPC’s – 56 days after Engineer issued and amounts which are about to be
receipt for normal ones and 28 days after Employer challenged in arbitration.
receipt where the IPC is issued as result of a
Partially Agreed Final Statement under Clause Draft Final Statement, Agreed Final
14.13. The FPC is payable 56 days after its receipt Statement and Partially Agreed Final
by the Employer. Statement (14.11)

Delayed Payment (14.8) There are now three sub-clauses covering what was
previously in one sub-clause referring to the
As before interest is due on late payment. The rate application for a Final Payment Certificate. As
is calculated at 3% above variously defined base before the Sub-clause envisages a process under
rates which have been re-defined. Formerly the which the Engineer and the Contractor attempt to
base was the discount rate of the central bank of the agree on the figures for the FPC.
country of currency of payment. It is now based on
the rates charged to borrowers at the place for The significant change is the introduction of the
payment or, if there is no such rate, the rate in concept of a Partially Agreed Final Statement
country of the currency of payment (there should (PAFS). This is a Statement prepared by the
be some interesting debates about what rate should Contractor identifying amounts which (after
be paid where the currency of payment is the discussions with the Engineer) are agreed and
Euro!). those which are not agreed. This is a sensible
additional provision to avoid the situation where
Payment is now to be made without any
there is disagreement over the content of the Final
requirement for a notice from the contractor of any
Statement and the Engineer is forced to make a
sort. There is no time limit expressed and no
decision as to what he includes in the FPC.
provision for interest on late payment of such
interest. Contractors who fear late payment of As with as Agreed Final Statement, the
interest may be wise to included a claim in their consequence of a PAFS is that the Engineer
next Statement for inclusion in an IPC. proceeds to issue an FPC (14.13). However, the
payment consequences are different. In the case of
Release of Retention Money (14.9)
an FPC, Clause 14.7 requires payment 56 days after
This new provision marks a considerable negative receipt by the Employer. A PAFS does not lead to
change as far as Cotractors are concerned. Under an FPC but to an IPC which is to be paid 28 days
the 1999 edition payment was certified by the after receipt by the Employer.
Engineer outside the normal IPC process and
should have been made immediately. It is now to

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
4
ContractPriceAndPayment/GR/2018(1)/14/CLAL www.corbett.co.uk
Discharge (14.12) The opening words provide that following a
Partially Agreed Final Statement a Final Payment
The 1999 edition provided for a full and final Certificate is to be issued.
discharge by the Contractor which only took effect
once all outstanding claims had been satisfied. However, the final paragraph provides that in the
This has now been limited in that the discharge same case no FPC is to be issued, but there is to be
covers all agreed amounts but can only exclude another IPC. As noted above if this approach is
limited elements of the Contractor’s claims. followed, this IPC (unlike other IPC’s) is to be paid
28 days after receipt by the Employer rather than
The excluded items may only be items in respect of 56 days after its receipt by the Engineer.
which a DAAB or arbitration is “in progress”. Thus
claims still being dealt with by the Engineer under Cessation of Employer’s Liability (14.14)
Clause 3.7 cannot be excluded, nor can those which,
while still live, have not yet been made the subject As in the 1999 edition, the Employer’s liability is
of a DAAB or arbitration (notice not yet given, limited by reference to what is included in the Final
proceedings not yet commenced etc). Contractors Statement, unless something new arises after the
ought to be very reluctant to issue such a discharge, work is completed.
but it is a condition precedent to issue of the Final
Payment Certificate. The discharge will be deemed The 2017 edition contains an additional exemption
to have been submitted and will be effective even if for the Employer. Unless reference has been made
the Contractor fails to provide it so long as the in the Final Statement or Partially Agreed Final
amount certified in the Final Payment Certificate Statement, the Employer is absolved from any
has been paid and the Performance Security amounts which the Contractor might wish to claim
returned. Given that the FPC cannot be issued unless he makes a claim under 20.2 within 56 days
until the discharge is provided this provision is of receiving the Final Payment Certificate. Under
unworkable. the 1999 edition no such cut-off was provided.
Contractors will have to be sure to start all their
Issue of FPC (14.13) claims immediately.

The FPC is issued 28 days after the Final Statement As with the 1999 edition the cessation of the
or Partially Agreed Final Statement. This is as in Employer’s liability does not apply in the case of his
the 1999 edition, but the content of the statement indemnification obligations or in case of fraud,
now includes credit for any amounts paid under the deliberate default or reckless misconduct. To this
Performance Security and any balance due from the list (and to the Contractor’s possible advantage)
Employer. “gross negligence” has now been added.

The Sub-Clause now contains additional wording to The addition of “gross negligence” may have
deal with the situation where there is a Partially substantially different results depending on which
Agreed Final Statement (or the Engineer considers Law applies to the contract.
that the draft final Statement submitted is in fact a
Partially Agreed Final Statement). In a very interesting treatment of the subject
recently presented to the Society for Construction
Unfortunately (perhaps due to a drafting error) law in London 3 the authors quoted a passage from
there are two alternative approaches included with
no indication as to which is to apply.

3
Exclusions from Immunity: Gross Negligence and Wilful Misconduct,
James Pickavance and James Bowling SCL October 2017

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
5
ContractPriceAndPayment/GR/2018(1)/14/CLAL www.corbett.co.uk
a Court of Appeal case Armitage v Nurse4 as Article Author
follows:
George Rosenberg 6
“It would be very surprising if our law drew the
line between liability for ordinary negligence and
liability for gross negligence. In this respect
English law differs from civil law systems, for it
has always drawn a sharp distinction between
negligence, however gross, on the one hand and
fraud bad faith and wilful misconduct on the other
... we regard the difference between negligence Email: george.rosenberg@corbett.co.uk
and gross negligence as merely one of degree ...
civil systems draw the line in a different place. The
doctrine is culpa lata dolo aequiparatur [gross
negligence is equal to fraud]; and although the
maxim itself ls not Roman the principle is
classical. There is no room for the maxim in the
common law.” 5
On this basis it seems that in common law
jurisdictions all significant negligence prevents
parties from escaping from liability and under civil
systems only fraud will enable them to escape.

Currencies of Payment (14.15)

This adds two provisions to those in the 1999


edition. One provides for the way in which
currencies are to be allocated in valuing variations
(there is a comment on this in our treatment of
Clause 13). The other deals with the currencies in
which Performance Damages are to be paid.

4 6
[1997] EWCA Civ 1279, [1997] 2 All ER 705, [1997] 3 WLR 1046 The contents of this article should not be treated as legal advice. Please
5
Armitage v Nurse Note 14 [1997] 3 WLR 1046 para [254] contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.]

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
6
ContractPriceAndPayment/GR/2018(1)/14/CLAL www.corbett.co.uk
Clause 15: Termination by Employer
Written by Victoria Tyson 1

The main changes in Clause 15 are the new


grounds for termination: Mr Justice Akenhead’s words in Obrascon Huarte
Lain SA -v- Her Majesty’s Attorney General for
• Non-compliance with a final and binding Gibraltar [2014] 2 may have also prompted this
Engineer’s Determination (Sub-Clause change. Mr Justice Akenhead took the view that
15.2.1(a)(ii)) and a binding or final and under the FIDIC 1999 the specified time for
binding DAAB decision (Sub-Clause compliance within the Notice to Correct must be
15.2.1(a)(iii)) to the extent that such failure reasonable in all the circumstances prevailing at the
constitutes a “material breach” of the time of the notice. He gave the example that if 90%
Employer’s obligations under the Contract. of the workforce had gone down with cholera at
that time, the period given for compliance would
• Maxing out the Delay Damages (Sub-Clause need reasonably to take that into account, even if
15.2.1(c)). There is no requirement for the that problem was the Contractor’s risk. He
Delay Damages to have been actually emphasised that what is reasonable would be fact
deducted. It is not clear what the position sensitive. 3 So, whilst it is logical for the Contractor
would be if the Contractor claims an EOT and to specify what he knows he can do, it is likely that
it is granted by the DAAB or arbitrator after in practice much time will be spent arguing if it is
termination so that the Delay Damages are good enough.
reduced below the cap. Would the
termination then be unlawful? Non-compliance with a Notice to Correct entitles
the Employer to give Notice of intention to
Notice to Correct terminate, provided now that such failure
constitutes a “material breach” of the Contractor’s
Further important changes concern Sub-Clause 15.1 obligations under the Contract. (Sub-Clauses
[Notice to Correct]. Sub-Clause 15.1 is designed to 15.2.1(a)(i).) What constitutes a “material breach”
give the Contractor an opportunity and a right to is likely to be the subject of many disputes. So,
correct its previous and identified contractual while a failure by the Contractor to carry out “any
failure. Under the FIDIC 1999 edition it was obligation” under the Contract may lead to a Notice
generally understood that the Engineer would give to Correct, it is the failure to comply with the Notice
a Notice to Correct which specified what was to Correct itself, where such non-compliance
wrong, how to fix it, and a time within which to fix constitutes a material breach, which entitles the
it. Most arguments arose as to the specified time to Employer to terminate. Logically, it would make no
fix it. The new wording envisages a Notice to sense for non-compliance with the Notice to
Correct specifying what is wrong, the relevant Correct to be a material breach if the original
contract clause, and a time within which to fix it. breach which gave rise to the Notice to Correct was
How to fix the problem is now firmly in the not a material breach although this is not spelled
Contractor’s domain. Therefore, most arguments out in the drafting.
are likely to arise over the Engineer/Employer’s
objections to what the Contractor proposes to do to This “material breach” wording may have been
fix the problem in the time. prompted in part by Mr Justice Akenhead’s words

1
Victoria Tyson is a director at Corbett & Co. International Construction Lawyers Ltd. She can be contacted at victoria.tyson@corbett.co.uk.
2
Obrascon Huarte Lain SA -v- Her Majesty’s Attorney General for Gibraltar [2014] EWHC 1028 (TCC).
3
See, for example, Shawton Engineering Ltd v. DGP International Ltd [2005] EWCA Civ 1359 [69].

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
TerminationByEmployer/VT/2018(1)/15/CLAL www.corbett.co.uk
in Obrascon Huarte Lain SA -v- Her Majesty’s will have for wishing to terminate for convenience
Attorney General for Gibraltar [2014] 4 . In this will be that (i) the market has changed, (ii) it no
case Mr Justice Akenhead took the commercially longer needs the project, (iii) it has run out of
sensible view that that Sub-Clause 15.1 of the FIDIC money, (iv) it has found a cheaper contractor, or (v)
1999 related only to more than insignificant where it does not wish to argue his entitlement to
contractual failures by the Contractor, such as a terminate for cause.
health and safety failure, bad work or serious delay
on aspects of the work. This, he said, would need to Under Sub-Clause 15.6 [Valuation after
be established as an actual failure to comply with Termination for Employer’s Convenience] the
the Contract rather than something that may have Contractor must submit detailed supporting
not yet become a failure. Thus, trivial contractual particulars of the value of the work done and the
failures would not lead to contractual termination. amount of any “loss of profit or other losses and
Mr Justice Akenhead supported his view with damages” suffered by the Contractor as a result of
reference to various authorities. 5 He emphasised Sub-Clause 15.5 [Termination for Employer’s
that what is trivial and what is significant or serious Convenience]. The Engineer must then agree or
will depend on the facts and gave the example that determine the amount and then issue a Payment
1 day’s culpable delay on a 730 day contract or 1m² Certificate for the amount agreed or determined.
of defective paintwork out of 10,000m² good The wording “other losses and damages” is vague
paintwork would not, if reasonable and sensible and may have different meanings in different
commercial persons had anything to do with it, jurisdictions. It is perhaps less vague if read against
justify termination even if the Contractor did not Sub-Clause 1.15 [Limitation of Liability] (although
comply with the Sub-Clause 15.1 notice. Sub-Clause 1.15 only makes express reference to
Sub-Clause 15.7 [Payment after Termination for
Sub-Clause 15.2.2 [Termination] then gives the Employer’ Convenience]).
Contractor 14 days within which to remedy the
matter(s) described in the Notice of intention to Sub-Clause 15.7 [Payment after Termination for
terminate the Contract under Sub-Clause 15.2.1 6. Employer’s Convenience] is carved out from Sub-
Effectively, this gives the Contractor an extra 14 Clause 1.15 [Limitation of Liability] which states
days within which to comply with the Notice to that “neither Party shall be liable to the other
Correct. After the 14 days have expired the Party for loss of use of any Works, loss of profit,
Employer may then give a second Notice to the loss of any contract or for any indirect or
Contractor to immediately terminate the Contract. consequential loss or damage…”. Therefore,
liability for “loss of profit or other losses and
Termination for Employer’s Convenience damages” is not excluded and there is no overall
limit in respect of this on the Employer’s exposure.
Another significant change is the Employer’s This may make termination for convenience too
entitlement to terminate the Contract under Sub- expensive to be regularly operated in practice.
Clause 15.5 [Termination for Employer’s
Convenience] in order to execute the Works himself The Employer may not execute any part of the
or to arrange the Works to be executed by another Works or arrange (any part of) the Works to be
contractor. The most likely reason the Employer executed by any other entities until the Contractor

4 6
Obrascon Huarte Lain SA -v- Her Majesty’s Attorney General for Except that the Employer may terminate immediately if the Contractor
Gibraltar [2014] EWHC 1028. subcontract or assigns without agreement under sub-paragraph (f),
5 becomes bankrupt or insolvent etc. under sub-paragraph (g), or engages
Lord Diplock in Antaios Compania Naviera SA v Salen Rederierna AB
[1985] AC 191 at 201D; Hudson’s Building and Engineering Contracts in corrupt etc. practices under sub-paragraph (h). (Sub-Clause 15.2.2
(Twelfth Edition) at paragraph 8.056; Lord Steyn in Mannai Investment [Termination].
Co Ltd v Eagle Star Assurance Company Ltd [1997] UKHL 19.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
TerminationByEmployer/VT/2018(1)/15/CLAL www.corbett.co.uk
has been paid the amount due under Sub-Clause • The ground for termination in Sub-Clause
15.6 [Valuation after Termination for Employer’s 15.2.1(h) where the Contractor has engaged in
Convenience]. This sum must be paid within 112 corrupt, fraudulent, collusive or coercive
days (16 weeks) after the Engineer receives the practice at any time in relation to the Works
Contractor’s submission (Sub-Clause 15.7 or to the Contract. The wording is more
[Payment after Termination for Employer’s precise than that relating to the granting of
Convenience]). inducements or rewards etc. in the FIDIC
1999 editions. In the FIDIC 1999 editions the
Would the Contractor be entitled to any financing Employer was entitled to terminate if the
charges as a result of delayed payment by the Contractor gave or offered an inducement or
Employer? Financing charges apply only in respect reward etc. but there was no recipricol
of a failure to pay under Sub-Clause 14.7 arrangement. This has been resolved with
[Payment]. Sub-Clause 14.7 refers to IPCs (an identical wording in Sub-Clause 16.2.1(j).
Interim Payment Certificate defined as one issued
under Sub-Clause 14.6) and FPCs (a Final Payment • Clarification that termination requires two
Certificate defined as one issued under Sub-Clause notices, not just one except that the Employer
14.13). There is no express reference to a Payment may terminate immediately if the Contractor
Certificate issued under Sub-Clause 15.6. Perhaps subcontract or assigns without agreement
the Sub-Clause 15.6 Payment Certificate is intended under sub-paragraph (f), becomes bankrupt
to be classed as an IPC or FPC issued under Sub- or insolvent etc. under sub-paragraph (g), or
Clause 14 by way of its definition? It is not engages in corrupt etc. practices under sub-
immediately clear. paragraph (h). (Sub-Clause 15.2.2
[Termination].)
Other changes to note include:
• Clarification that remedying the default
• The additional wording in Sub-Clause 1.16 within 14 days removes the right to
[Contract Termination] which seeks to avoid terminate. (Sub-Clause 15.2.2
arguments in some countries that [Termination].) However, there appears no
termination can only take place with the way for the Contractor to remedy the event of
approval of the courts. It states, “Subject to reaching the maximum amount of Delay
any mandatory requirements under the Damages.
governing law of the Contract, termination
of the Contract under any Sub-Clause of • After termination, the Contractor must
these Conditions shall require no action of “comply immediately with any reasonable
whatsoever kind by either Party other than instruction included in a Notice given by the
as stated in the Sub-Clause”. Employer under this Sub-Clause (i) for the
assignment of any subcontract, and (ii) the
• The ground for termination in Sub-Clause protection of life or property or for the safety
15.2.1(g) [Notice] regarding bankruptcy and of the Works”. (Sub-Clause 15.2.3(a) [After
insolvency etc. has been widened. The termination].) In the FIDIC 1999 editions
the Contractor was only required to use “his
wording is identical to that under Sub-Clause
best efforts to comply with any reasonable
16.2.1(f) [Notice], except in relation to joint
instruction included in the notice”. In the
ventures. FIDIC 2017 editions it must do so without
qualification, and must do so immediately.
• The new unincorporated joint venture
provisions at Sub-Clause 15.2.1(g) [Notice].

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
3
TerminationByEmployer/VT/2018(1)/15/CLAL www.corbett.co.uk
Article Author
Victoria Tyson 7

Email: victoria.tyson@corbett.co.uk

7
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
4
TerminationByEmployer/VT/2018(1)/15/CLAL www.corbett.co.uk
Clause 16: Suspension and Termination by Contractor
16: Suspension and Termination by Contractor
Written by Victoria Tyson1

The main changes in Clause 16 are the new offered an inducement or reward etc. but
grounds for suspension and termination: there was no recipricol arrangement.

• Non-compliance with a final and binding Other changes to note include:


Engineer’s Determination and binding or
final and binding DAAB decision, to the • The additional wording in Sub-Clause 1.16
extent that such failure constitutes a [Contract Termination] which seeks to avoid
“material breach” of the Employer’s arguments in some countries that
obligations under the Contract. (Sub-Clauses termination can only take place with
16.1(d) and 16.2.1(d)). What constitutes a additional formalities such as the approval of
“material breach” is likely to be the subject of the courts. It states, “Subject to any
many disputes (see the commentary on mandatory requirements under the
Clause 15). governing law of the Contract, termination
of the Contract under any Sub-Clause of
• Non-receipt of a Notice of the these Conditions shall require no action of
Commencement Date under Sub-Clause 8.1 whatsoever kind by either Party other than
[Commencement of Works] within 84 days as stated in the Sub-Clause”. It probably
after receiving the Letter of Acceptance. (Sub- does not apply to the consequences of
Clauses 16.2.1(f)). This is development to termination.
ground (h) in the FIDIC Pink (MDB) Book
which states: “the Contractor does not • The ground for termination in Sub-Clause
receive the Engineer’s instructions recording 16.2.1(c) is no longer restricted to the non-
the agreement of both Parties on the payment of Interim Payment Certificates and
fulfilment of the conditions for the relates to a failure by an Employer to pay the
Commencement of the Works under Sub- advance, interim or final payment.
Clause 8.1 [Commencement of Works]”. It
protects the Contractor from the financial • The ground for termination in Sub-Clause
consequences of fluctuations in the rates and 16.2.1 (e) now requires that a substantial
prices during an extended delay to the start of failure to perform be a “material breach” of
the Works. the Employer’s obligations under the
Contract. (Sub-Clauses 16.2.1(e)).
• Engagement in corrupt, fraudulent, collusive
or coercive practice at any time in relation to • The ground for termination in Sub-Clause
the Works or to the Contract. (Sub-Clauses 16.2.1(f) regarding bankruptcy and insolvency
16.2.1(j).) This introduces parity between the etc. has been widened. The wording is
Employer and Contractor. The wording is identical to that under Sub-Clause 15.2.1(g),
identical to that under Sub-Clause 15.2.1(h). except in relation to joint ventures.
In the FIDIC 1999 editions the Employer was
entitled to terminate if the Contractor gave or

1
Victoria Tyson is a director at Corbett & Co. International Construction Lawyers Ltd. She can be contacted at victoria.tyson@corbett.co.uk.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
TerminationByContractor/VT/2018(1)/16/CLAL 1
www.corbett.co.uk
• Sub-Clause 16.4 [Payment after Termination
by Contractor] is carved out from Sub-Clause
Article Author
1.15 [Limitation of Liability] which states that
“neither Party shall be liable to the other Victoria Tyson2
Party for loss of use of any Works, loss of
profit, loss of any contract or for any
indirect or consequential loss or damage…”.
Therefore, liability for “loss of profit or other
losses and damages” is not capped and there
is no overall limit in respect of this. From an
Employer’s point of view, a termination
under Sub-Clause 15.2 [Termination for
Email: victoria.tyson@corbett.co.uk
Contractor’s Default] will be preferable to
termination under Sub-Clause 16.2
[Termination by Contractor].

In the FIDIC 1999 editions, if an Employer


realised the Contractor intended to
terminate, and good grounds existed for the
Contractor to terminate under Sub-Clause
16.2, the Employer may have sought to save
himself considerable expense by terminating
first for convenience under Sub-Clause 15.5
[Employer’s Entitlement to Terminate].

This doubtful strategy is even less attractive


in the FIDIC 2017 editions now that an
Employer who terminates under the new
Sub-Clause 15.5 [Termination for Employer’s
Convenience] is liable to pay the Contractor
for loss of profit or other losses and damages.

Further, under Sub-Clause 15.5 the


Employer’s termination takes effect 28 days
after the date on which the Contractor
receives notice or return of the Performance
Security (whichever is later). Whereas, under
Sub-Clause 16.2 the Contractor may
terminate 14 days after giving notice to the
Employer. So, it is still possible for the
Contractor’s termination to take effect first.

2
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
TerminationByContractor/VT/2018(1)/16/CLAL 2
www.corbett.co.uk
Clause 17: Care of the Works and Indemnities
Written by George Rosenberg 1

This Clause has been substantially re- Responsibility and Liability for the Care of
worked. The content of the former Clause the Works
17.6 [Limitation of Liability] has been
removed to Clause 1.15. The first two Sub-Clauses of Clause 17 deal
respectively with Responsibility for and Liability for
The Clause 17 Care of the Works obligations under Care of the Works.
the 1999 edition were useful as a statement of
allocataion of responsibility, but of limited The term “care of the Works” is nowhere defined,
significance in that many of the obligations but its meaning should be able to be understood
imposed on the Contractor in respect of its from the two sub-clauses. Under 17.1, the
responsibility for care of the Works and the liability responsibility entails rectifying any loss or damage
once responsibility had passed to the Employer which occurs during the period for which the
were also capable of being regulated under Sub- Contractor is responsible. Following this period,
Clause 7.6 [Remedial Work] (prior to completion) the Contractor is liable for any loss or damage
and under Clause 11 [Defects Liability] (after caused by it to the Works – either in this period or
completion). Despite considerable changes this as a result of something which occurred during the
position remains. period during which the Contractor was
responsible.
Where, after completion, the Contractor is
reluctant to meet his responsibilities, the Thus “care of the Works” seems to entail repair
temptation for the Engineer to use his Clause 11 during the period of responsibility (which itself
powers is now increased because, while action by involves taking the necessary steps to avoid the
the Engineer under Clause 17 (formerly on the basis need for such repair) and liability for loss or
of a “request”) now has to be through a Variation, a damage during the period subsequent.
similar result can be achieved by an instruction
under Clause 11. As can be seen from the The period during which the Contractor has the
commentary on Clause 13, and also below, the use responsibility for the care of the works generally
of Variations is fraught with potential problems. expires at the Date of Completion or earlier
termination, although it is extended for the care of
The Contractor’s Care of the Works responsibility is any work which is outstanding on the date of
substantially reduced compared with that under the completion until it is completed. This would cover
1999 edition because it does not now include any rectification of defects and snagging lists.
loss or damage caused by the Employer or
Engineer. The concept of Date of Completion is clear in
respect of Sections or the Works as a whole thanks
The Contractor and Employer indemnities relating to the definition of Date of Completion in Sub-
to personal injury and property claims, which were Clause 1.1.24. It means that the date will either be
formerly applicable in respect of all relevant claims, that stated in the TOC, a deemed completion date
now only apply to third party claims. under Sub-Clause 10.1 or a deemed taking over date
under Sub-Clause 10.2 and 10.3. The last sentence
of the first paragraph of Sub-Clause 17.1 passes the
responsibility to the Employer if a TOC for a

1
George Rosenberg is a Consultant at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at george.rosenberg@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
Section or a Part is issued or deemed to be issued. damage, once it occurs on its watch. The Employer
In respect of Parts, Sub-Clause 10.2 does not will probably be ill-equipped for this task
provide for the deemed issue of a TOC but does (especially if only a Section or Part has been taken
provide for a deemed taking over and a passing of over). The consequences will be considered below
responsibility to the Employer. It would have been in relation to the Employer’s remedies set out at the
helpful if Sub-Clause 17.1 had cross-referred to end of Sub-Clause 17.2
Sub-Clause 10.2.
Liability
However, Sub-Clause 10.3 deals with interference
with tests on completion and provides that, where Sub-Clauses 17.1 and 17.2 draw a boundary between
the Contractor is delayed by such interference, a period during which the Contractor is responsible
then, subject to the Contractor having given notice, and when it becomes merely liable. This is a
the Employer shall be deemed to have taken over concept many lawyers will find difficult to grasp,
the Works or a Section when the Works or Section because responsibility usually implies liability.
would otherwise have been completed. There is However, it is clear that this is the draftsman’s
thus a deemed taking-over but no deemed issue of a intention. The distinction seems to lie in the scope
TOC. It is clear that such a deemed taking over was of the responsibility laid out in Sub-Clause 17.1 by
not intended under Sub-Clause 10.3 to be the comparison with the scope of liability laid out in
equivalent of a deemed TOC as Sub-Clause 10.3(c) Sub-Clause 17.2. Under 17.1 the responsibility
requires the Engineer to issue a TOC. Thus it is entails repairing loss or damage, whereas under
possible that there will be no TOC or deemed TOC Sub-Clause 17.2 there is no strict definition. In
under Sub-Clause 10.3. Unlike Sub-clause 10.2 general legal terms, liability might mean an
there is no express provision for passing of obligation to repair but it would also mean paying
responsibility to the Employer. It is therefore damages consequent.
possible that the passing of responsibility will be
delayed or (in the event that the Engineer does not In making the distinction between responsibility
issue a TOC) may not occur at all. and liability, Sub-Clauses 17.1 and 17.2 also largely
absolve the Contractor from liability under Sub-
It should be noted that the third sentence of the Clause 17.1 (except to the extent that responsibility
first paragraph passes responsibility on the date of for repair can be regarded as a liability).
issue of the TOC – sometimes a date later than the
Date of Completion, so there appears to be an Quite why it this is necessary to set out a basis of
internal inconsistency within this first paragraph. liability in Clause 17, is not clear. The period of
Contractor liability coincides with the Defects
Sub-Clause 17.1 thus has the effect (subject to the Notification Period which has a comprehensive
above issues) of defining the period of the code for Contractor liability.
Contractor’s responsibility and the start of the
Employer’s responsibility. Sub-Clause 17.2 opens with a paragraph which
imposes liability on the Contractor where it causes
Employer’s Responsibility damage after the issue of a TOC, including where
the loss or damage resulted from something which
Once the Contractor ceases to be responsible for occurred before the TOC. What it specifically does
the care of the Works, responsibility shifts to the not do is impose liability for loss or damage which
Employer. The Sub-Clause does not explain the occurred before the TOC.
consequences of this, but by analogy with the
consequences of responsibility for the Contractor, it It should be noted that the period of liability begins
seems as though it becomes the Employer’s with the issue of TOC. According to the definition
responsibility to protect against and repair loss or of TOC in Sub-Clause 1.1.81 a TOC includes a

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
deemed TOC so there may, as outlined above, be accordance with Sub-Clause 1.15 [Limitation of
situations where the liability is delayed or does not Liability] there is no liability “for loss of use of any
come into effect. However, more importantly, Works, loss of profit, loss of any contract or any
there may be a gap between passing of other indirect or consequential loss”.
responsibility (Date of Completion) and
commencement of liability (TOC). This is because Excluded Events
a TOC is normally dated later than the date of
completion included in it. During this period the Sub-Clause 17.2 excludes the Contractor from
Employer will have responsibility, but the liability caused by a list of events. Several of these
Contractor will have neither responsibility, nor, at are included by reference to Sub-Clause 18.1
least under Sub-Clause 17.2, liability2. [Exceptional Events].

Assuming that responsibility is different from One of the 1999 events has been removed from the
liability, the Contractor will not benefit from the list (pressure waves caused by aircraft or other
cap on liability set out in Sub-Clause 1.15, should aerial devices travelling at supersonic speeds) and
the cost of repairs during the period of the following have been added:
responsibility, exceed the limits on liability set out
(a) Interference with any right of way, light, air
therein.
water or other easement which is the
Consequences of Liability unavoidable result of the execution of the
Works in accordance with the Contract.
If the Contractor is liable, as opposed to
responsible, it is no longer required under Clause (b) Faults in the design which an experienced
17 to remedy the loss or damage. Sub-Clause 17.2 contractor exercising due care would not have
does not say what is to happen. However, since this discovered 3.
situation occurs after the Completion, Clause 11
[Defects after Taking Over] applies. The (c) Rebellion, terrorism, revolution, insurrection
Contractor can be obliged to repair defects or military or usurped power, riot commotion or
damage. Sub-Clause 11.2 provides that the disorder and the encountering of munitions of
Contractor will bear the cost in a limited range of war are no longer limited to events within the
circumstances, all of which can be said to be country.
“caused by the Contractor” but which is certainly
not a comprehensive list of such causes. There may (d) Strike or lockout.
thus be situations where the Contractor has caused
a loss or damage and is thus liable under Sub- (e) Natural Catastrophes such as earthquake,
Clause 17.2, but would not be liable under Sub- tsunami, volcanic activity, hurricane or
Clause 11.2 for this cost. Presumably the remedy typhoon.
for the Employer lies in a claim for damages.
(f) any act or default of the Employer or Engineer
It is thus possible that, after TOC, but not before, and use or occupation by the Employer of any
the Contractor will be liable for damages resulting part of the Permanent Works unless otherwise
from loss or damage caused by it to the Works. specified in the Contract.
Such damages will be rather limited as, in

2 3
An act of negligence on the Contractor’s part would Such faults also give the Contractor the right under Clause 1.9 to a
probably create liability in this period, as does the Defects Variation, time and money. However the test in 1.9 takes account of cost
Notification Period (which begins on Completion) but it is a and time. It is not clear whether the omission of this qualification in
Clause 17.2 is intended to have any effect on the way the exemption
pity that there is such a lacuna. applies.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
3
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
There must be circumstances in which the sort of the above conclusions. If excluded events in Sub
intereference referred to in (a) is a result of clause 17.2 were not to apply during the
Contractor choice – through its design but it would Contractor’s period of responsibility there would be
seem that once the design (prepared by the an inconsistency.
Contractor) causes interference when carried out,
the risk shifts to the Employer. It is in any case However, if the excluded events are to be applied in
difficult to see how such intereference could full to the period of Contractor responsibility, this
influence care of the Works while the Contractor raises questions about the meaning of the words in
remains responsible, nor how it relates to damage Sub-Clause 17.1:
to the Works once responsibility has passed to the
Employer. “If any loss or damage occurs to the Works, Goods
or Contractor’s Documents during the period
This list is expressed to extend to Sub-Clause 17.2 when the Contractor is responsible for their care
liability, but, if the distinction between from any cause whatsoever except as stated in
responsibility and liability is as effective as is Sub-Clause 17.2 [Liability for the Care of the
apparently intended, would not extend to the Works], the Contractor shall rectify the loss or
period when the Contractor is merely responsible. damage at the Contractor’s risk and cost, so that
This would be a departure from the 1999 edition the Works, Goods or Contractor’s Documents (as
philosophy. Perhaps to overcome this problem, the case may be) comply with the Contract.”
Sub-Clause 17.1 makes the responsibility for care
applicable “except as stated in Sub-Clause 17.2.”. If the list of excluded events is taken out and, when
it is noted that the last item in the list is any act or
Although the second paragraph of Sub-Clause 17.2 default of the Employer or Engineer, all that seems
begins with the words “The Contractor shall have to be left of the Contractor’s responsibility is loss or
no liability whatsoever … for loss or damage … damage caused by the Contractor. This happens to
caused by any of the following events ….”, the be the same test as for liability under Sub-Clause
subjection of Sub-Clause 17.1 to 17.2 is presumably 17.2. The words “from any cause whatsoever”
intended to mean that in this sentence “liability” appear to have rather limited meaning. They
includes “responsibility”, whatever is intended certainly apply to acts by the Contractor, by third
elsewhere in Clause 17. This conclusion is bolstered parties unrelated to the contract and to the less
by sub-paragraph 17.2(ii) which is part of a extreme external events, such as normal climatic
provision (discussed below) which provides for a problems, but beyond that the responsibility is
sharing of liability where the loss or damage to the quite limited. The final scope will depend on what
Works is caused by a combination of one of the is meant by the incorporation of some of the
excluded events with “a cause for which the Exceptional Events from Sub-Clause 18.1. But,
Contractor is liable”. One of the remedies where even then, Sub-Clause 7.6, which, in circumstances
this occurs is EoT. Since, after TOC, EoT is where the Contractor does not spontaneously
irrelevant, it seems that here too, “liability” is repair loss or damage, allows the Engineer to
intended to mean the same as “responsibility”. require it to do so at its cost does not impose the
costs on the Contractor when Exceptional Events
The provisions of Sub-Clause 7.6 [Remedial Work] are the cause.
also confirm this position. Sub-Clause 7.6 allows
the Engineer, prior to TOC, to order the repair or Thus, before Completion, the Contractor’s
remedy works in various situations. The responsibility is probably limited to loss or damage
Contractor does not have to bear the cost where caused by itself, by unrelated third parties and by
there is an Exceptional Event, so this sub clause non-exceptional climatic events and, after TOC, its
reflects the same policy as appears to be reflected in liability is limited to events caused by itself.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
4
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
Incorporation of Exceptional Events incorporated into Sub-Clause 17.2 by paragraph (e)
is not a comprehensive list of Exceptional Events
Sub-Clause 17.2 includes in the list of excluded but only a series of examples. In Sub-Clause 18.1,
events “any of the events or circumstances listed each one is made subject to conditions 18.1(i) to (iv)
under sub-paragraphs (a) to (f) of Sub-Clause 18.1 – i.e. they must be (i) beyond a Party’s control; ii)
[Exceptional Events].” the Party could not reasonably have provided
against before entering into the Contract; (iii)
The next paragraph of Sub-Clause 17.2, however, having arisen, such Party could not reasonably have
then goes on to state: avoided or overcome; and (iv) is not substantially
attributable to the other Party. It then goes on to
“Subject to Sub-Clause 18.4 [Consequences of an state:
Exceptional Event], if any of the events described
in sub-paragraphs (a) to (f) above occurs and “An Exceptional Event may comprise but is not
results in damage to the Works … the Contractor limited to any of the following events or
shall promptly give a Notice to the Engineer.” circumstances provided that conditions (i) to (iv)
are satisfied.”
Sub-Clause 18.4 deals with the situation where an
Exceptional Event has caused the Contractor delay Thus, one can conclude that the examples (a) to (f)
or Cost. Sub-Clause 18.4 is, itself, subject to the have to be read subject to (i) to (iv). If that is the
requirements of Sub-Clause 18.2 [Notice of an case it is also arguable that 18.1 as a whole was
Exceptional Event] which requires the Contractor intended to be imported (which is the case under
to give notice where it “is or will be prevented from Sub-Clause 7.6).
performing any obligations under the Contract”.
This is a more limited application of Exceptional Thus, there are three possibilities:
Event than is intended by Sub-Clause 17.2. By
definition those events do not prevent the 1. The examples in Sub-Clause 18.1 are included
Contractor performing its obligations. They may on a stand-alone basis.
impose additional cost on it if there are repairs to
be carried out or there is a delay, but that is 2. They are subject to the pre-conditions in 18.1 (i)
different from “prevention”. Perhaps the to (iv)
subjugation of this paragraph of Sub-Clause 17.2 is
only intended to apply in those very limited 3. The whole of 18.1 is in fact incorporated which
circumstances where the Contractor is entirely would allow other Exceptional Events to apply.
prevented from meeting its obligations. It may be
intended to make it plain that in these The third seems unlikely, but possible. It is really
circumstances, there is no alternative required impossible to be sure which of (1) and (2) applies.
under Sub-Clause 17.2 of attempting to do the
impossible. It will also be applicable where the Item 17.2(d) sets a standard for an exception for the
Exceptional Event prevents the Contractor operation of forces of nature which is different from
performing its responsibilities or meeting its that which would be applied if it were an
liabilities for a limited period. Contractors will Exceptional Event. Unforseeability is dated by
need to be very careful to meet their notice reference to the Base Date (28 days before
obligations under Sub-Clause 18.2 and to not to submission of tender) whereas the Exceptional
rely on Sub-Clause 17.2 for all their Cost and time Events test applies at any time up to the entry into
recoveries. the Contract. This test in this sub-clause is also
different from that in Sub-Clause 8.5 should the
When reference is made to Sub-Clause 18.1, it can Contractor apply for an extension of time.
be seen the Exceptional Events list in (a) to (f) and

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
5
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
Variation Contractor’s responsibility/liability. An instruction
can hardly apportion this. It is not clear how the
The 4th paragraph of Sub-Clause 17.2 provides that Engineer is to cope with this.
if one of the excluded events has, in the
Contractor’s view, been the cause of damage to the It would have been better if either the Contractor or
works the Contractor may give a notice to the the Employer could have given the Notice or if the
Engineer who may then instruct what is to be done. Engineer was given an entitlement to issue an
This will then be treated as a Variation. instruction with the cost and time consequences to
be sorted out later. This is the position under Sub-
This has the odd result that the Contractor will Clause 7.6 which overlaps with Sub-Clauses 17.1
have a right to object for one or more of the reasons and 17.2 in that there may be need for repair during
set out in Sub-Clause 13.1. The first of these is that the period of responsibility. There will be
“the varied work was Unforeseeable having circumstances under which the Engineer prefers to
regard to the scope and nature of the Works make use of his/her powers under Sub-Clause 7.6
described in the Employer’s requirements.” Given (although it should be noted that the valuation
that the event will have been one of the excluded method under Sub-Clause 7.6 may be less
risks, this will often be the case. favourable to the Employer than that under Sub-
Clause 13.3.1 in respect of a Variation). It is also
This provision only applies in the case of damage – the case under Sub-Clause 11.1 [Completion of
not loss – in contrast to all other references in the Outstanding Work and Remedying Defects] where
two Sub-Clauses. It is easy to envisage a loss the Contractor’s obligation is triggered by a Notice.
situation. For example, material stored on site may
be stolen. The Contractor’s computer server may Where responsibility has shifted to the Employer
be damaged, leading to loss of important data. (especially where a Section or Part has been taken
There seems to be no remedy in this situation. over), the Employer may be ill-equipped to repair
any loss or damage not covered by the Contractor’s
The Contractor may not wish to give such a Notice. liability and may wish to rely on its right to vary
If a TOC has been issued and the damage is not under Sub-Clause 13.1 (which applies at any time
caused by the Contractor it will have neither up to the issue of the TOC for the Works as a whole
responsibility or liability. Event before that, the and will thus apply after a Section or Part is
effect of the excepted events is to exclude all complete) or its rights under Clause 11 [Defects
responsibility or liability, so it will be entitled to sit after Taking Over]. There may be circumstances
on its hands and do nothing. If it sees a financial where it prefers to use the Sub-Clause 13.1 power
advantage in doing nothing it will be entitled to act directly rather than relying on the power in Sub-
accordingly. Sub-Clause 8.5(c) already entitles the Clause 17.2.
Contractor to EoT for adverse climatic conditions.
Sub-clause 8.5(e) already entitles the Contractor to Contrast with the 1999 Edition
an extension of time where the delay is caused by
the Employer or Engineer. If the Works have been The equivalent 1999 provision gave the power to
completed, responsibility will have moved to the the Engineer to “require” such work to be done.
Employer unless the damage is caused by the Once the Contractor had done what it was required
Contractor, so 8.5(e) may again apply if the to do, it could claim compensation. The term
Employer is not remedying the problems. “require” sounds rather loose, but it works and
makes sense. The use of the term “instruction”,
If the Contractor does give a Notice and the though no doubt intended to create clarity, requires
Engineer is then required to issue an instruction, reference to be made back to Sub-Clause 3.5.
he/she may be faced with a difficult decision. The Whereas the equivalent in the 1999 edition (3.3)
damage may be a result of a combination of

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
6
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
allowed an instruction to be given for the execution effect, in that they are now limited to situations
of the Works or remedying of defects, the 2017 where the party claiming the indemnity is being
equivalent is limited to the execution of the Works. pursued by a third party. The consequences of this
This probably makes no difference if the instruction change are discussed below in the section on
is given during the period before TOC, or even Indemnities by Contractor (17.4) but they apply to
during the snagging period. However, it is clear all of Sub-Clause 17.3, 17.4 and 17.5 and have a
from Sub-Clause 11.1 that there is a distinction, consequential impact on Sub-Clause 17.6.
during the DNP, between defects, the remedy of
which would undoubtedly be part of the execution Indemnities by the Contractor and by the Employer
of the Works and damage, which is not necessarily. were formerly included together in the 1999
Thus, if there is damage caused by one of the edition. There are now two sub clauses dealing with
excluded risks, occurring during the DNP, the them and a third dealing with shared indemnities.
Employer will need to use his powers under Clause
11, rather than under Clause 17. There is room for As can be seen from the analysis below the scope of
confusion when a DNP has started for a Section or the indemnities has shrunk substantially and the
a Part and the whole of the Works is not yet Sub-Clauses are not likely to be much utilised.
complete as during this period both the Engineer
and the Employer will have functions running in Indemnities relating to Intellectual and
parallel. This will be particularly confusing if there Industrial Property Rights (17.3)
is a suggestion that damage is a result of something
caused by the Contractor prior to TOC. The Clause is closely based on that in the 1999
edition. However, there are four changes:
Shared Liability
• The indemnity only applies to third party
The final paragraph of Sub-Clause 17.2 deals with claims and;
the possible situation where the loss or damage
results from a combination of the excluded events • an express inclusion of legal fees and expenses,
and a cause for which the Contractor is liable. As and;
noted above this seems to be intended to read
• the Contractor is entitled to be indemnified
“responsible or liable”. The Contractor is then
where his alleged infringement was a result of
entitled to a proportion of EoT or Cost to the extent
his carrying out a Variation and;
that the excluded events contributed. This assumes
that the Contractor will rectify the loss or damage
• The Contractor is no longer required to
and then make a claim, but, as noted above, it may
indemnify the Employer where a claim arises
not be responsible/liable to rectify any element
from the proper use of the Works.
arising from the Exceptional Events. The provision
is, however a useful one in that it will encourage the Indemnities by the Contractor (17.4)
Contractor to act on its own initiative and attempt
to recover any relevant cost or EoT later. It is a pity These indemnities relate to injury to persons and
that it does not provide for this remedy even where damage to property other than the Works.
the cause is entirely a result of one of the Similar indemnities applied under the 1999 edition.
Exceptional Events. However, both the Contractor and Employer
indemnities are now limited to “third party” claims
Indemnities etc.

As discussed below, the majority of the indemnity The intention is presumably to prevent ether party
provisions have been significantly diminished in claiming against the other in respect of injury or
damage caused to their own staff or property. The

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
7
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
inclusion of the reference to “third party” initiated against the Employer by the owner may be
represents a considerable change to the contract’s covered by the indemnity.
risk profile. For example, in the case of the
personal injury indemnity, if an employee of the It is not clear why this change was necessary.
Employer or the Engineer under the 1999 Edition
was killed in circumstances where he or she was An error in the equivalent provision in the Gold
carrying out duties in relation to the Works, but the Book (where the provisions have considerable
Contractor was not in any way at fault, the similarity) has been corrected. The word “or” at the
Contractor would nonetheless have been held end of Sub-Clause 17.4(b)(i) has been replaced with
responsible. However, that employee is “and”.
“Employer’s Personnel”, not a third party, and
therefore the 2017 edition does not make the Indemnities by Employer (17.5)
Contractor responsible. The only claims now
covered by the indemnity will be those where a Again, the indemnity is limited to third party
third party is entitled to claim against the claims.
Employer. Under English law this might be the
case where the Employer has responsibility as the The Employer’s indemnity for personal injury only
occupier or has strict liability under worker injury applies where there has been fault on the part of
legislation. the Employer, its Personnel and agents. It does not
apply where the injury is the result of one of the
In the case of property damage, the indemnity (as Employer’s risks.
before) only applies to damage of property other
than the Works, but is again limited to third Under the 1999 edition (in addition to a situation
parties. In this case it is limited to loss attributable where it was at fault) the Employer indemnified the
to fault of the Contractor, its Personnel, their Contractor against personal injury on the basis that
agents and anyone directly or indirectly employed they were difficult or impossible to insure for
by them. There may be circumstances where an injury:
Employer has strict liability against a third party
for property damage and will wish to recover it i. resulting from the Employer’s right to have
from the Contractor. If the fault is that of the permanent works executed over under in or
Contractor, its personnel or agents, this remains a through any land and to occupy this land for
useful provision. However, the previous provision the permanent works,
enabled the Employer to claim against the
ii. which is the unavoidable result of the
Contractor for damages it, its Personnel and agents
suffered as a result of the fault of the Contractor, Contractor’s obligations to execute the
Contractor’s Personnel and agents. This right now Works and remedy any defects and
seems to be excluded. This will not make a great iii. resulting from something covered by a
deal of difference where the fault is that of the clause listed in Sub-Clause 17.3 [Employer’s
Contractor itself. However, where the fault is that Risks].
of a subcontractor or agent, the Employer will now
have to identify the party responsible and pursue None of these indemnifications now apply in
him or her. Where the victim is a member of the respect of personal injury. (i) and (iii) are excluded
Employer’s Personnel or an agent, they will have to in any event because they are (as they were)
pursue the claim themselves. Employer’s risks and a policy decision seems to
have been taken to exclude Employer’s risks from
There may be “third parties” who are closely the Employer’s indemnity. If it is indeed difficult
involved with the Works. For example, in the not- or impossible to insure these risks, it is difficult to
uncommon situation where the owner of the see why they have been removed from the
structure being built is not the Employer, claims Employer’s indemnity.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
8
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
The 1999 edition did not include any Employer’s The indemnity is limited to design obligations
indemnity for property damage. The new indemnity which result in the Works not being fit for purpose,
for property damage (other than the Works) does so is much narrower than the fitness for purpose
not apply where the Employer has caused the obligation in Clause 4.1. Further it an indemnity
damage through fault (for which it would be liable limited to circumstances where the failure is a
anyway, though not on the basis of indemnity) but result of acts, errors or omissions on the part of the
does apply where one the Employer’s risks is the Contractor whereas the fitness for purpose
cause. Thus, where fault is involved the Employer is obligation is not so qualified. Thus, unlike the
absolved from indemnification, but it is liable normal situation in respect of a fitness for purpose
where one of the no-fault events caused the claim. obligation, the burden of proof is shifted to the
Employer to demonstrate that the indemnity
This is again limited to third parties, so would only applies because of such acts errors or omissions.
apply if such third party had a claim against the Rather than rely on this rather limited indemnity, it
Contractor resulting from one of these events. This seems likely that Employers, faced with a product
again would only seem to be possible where the which is not fit for purpose, will rely on their rights
Contractor is under some form of strict liability. to claim damages for breach of Clause 4.1 or 5.3 4,
require remedy under Clauses 7.6 [Remedial Work]
Fitness for Purpose and 11 [Defects after Taking Over] and any
Performance Guarantee or make a claim for
Clause 17.4 now contains the following Contractor’s damages for breach rather than under the
indemnity which needs to be carefully considered. indemnity. It is therefore very difficult to see what
Unlike the other Contractor indemnities, it does not this fitness for purpose indemnity is intended to
only relate to third party claims. achieve.

“The Contractor shall also indemnify and When it was included in the draft of the Yellow
hold harmless the Employer against Book circulated for comment the draft included an
all acts, errors or omissions by the indemnity similar to the one now included and with
Contractor in carrying out the Contractor’s no cap on damages. This drew considerable
design obligations that result in the Works adverse comment including from many contractor’s
(or Section or Part or major item of associations who, in a joint letter stated:
Plant, if any), when completed, not being
fit for the purpose(s) for which they “If the current wording is allowed to stand,
are intended under Sub-Clause 4.1 it will impose a major additional risk upon
[Contractor’s General Obligations]”. international contractors and, in the case
of major infrastructure works or plants,
This (which originated in a slightly narrower form the losses that may be recovered could
in the Gold Book) represents a significant change to easily run into billions of euro and lead to
the way in which the Contractor’s fitness for insolvency, as claims under the indemnity
purpose obligation has been treated. On a free- will be uninsurable”.
standing basis, a breach of the fitness for purpose
obligation under 4.1 would normally lead to a Although the language of the originally drafted
liability based on consequences, rather than cause indemnity has changed this does not seem in itself
and thus whether the Contractor has been negligent to have made a significant difference. However, the
or not in failing to achieve its obligations will be general limits of liability are now allowed to apply.
irrelevant. Its only excuse might be if the failure to Despite the Contractors’ warning the indemnity is
achieve fitness for purpose was caused by an required to be insured.
Employer act.

4
This is a warranty that the completed works will be in
accordance with the documents forming the Contract.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
9
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
Shared Indemnities (17.6) deduction up to Completion or Termination is
100%. It may be less after Completion, but this
This is a new provision (developed from that in the seems unlikely as any event likely to lead to the
Gold Book) which purports to protect both the need for indemnification will most likely arise in
Contractor and the Employer against the full force respect of outstanding elements of the Works.
of the indemnity obligations imposed. The effect is The effect of the Sub-Clause therefore seems to be
very different for the Contractor from that for the to absolve the Employer almost entirely from
Employer. responsibility for its personal injury and property
indemnification responsibilities, limited as they
Where the claim under one of the indemnities is by already are.
the Employer against the Contractor but one or
more of the events listed in 17.2 (a) to (f) has
contributed to the damage which the Contractor is
required to indemnify the Employer, the liability is
Article Author
to be reduced proportionately to its effect. Whether
it is necessary to state this is arguable as Sub- George Rosenberg 5
Clause 17.2 already says that the Contractor shall
have no liability by way of indemnity if any of the
Employer’s risks are the cause.

17.2 (a) to (f) cover every fault of the Employer and


also include the no-fault events which were
formerly called “Employer’s Risks” and are now
“Exceptional Events”. Thus, the indemnity given
by the Contractor will be reduced to the extent one Email: george.rosenberg@corbett.co.uk
of these events applies. This makes sense but the
Sub-Clause is unclear as to whether the exception
to Employer’s liability included in the opening
paragraph to the list (a-f) in Sub-Clause 17.2 is
intended to apply.

The indemnity already covers cases where the


Employer has been negligent, wilful or has
breached the contract.

It is hard to see what is left to apportion.


Where the claim under one of the indemnities is
against the Employer the value of its indemnity is
to be reduced proportionately to the extent that any
event for which the Contractor is responsible under
Sub-Clause 17.1 may have contributed to the loss.
Sub-Clause 17.1 describes the Contractor’s
responsibility up to Completion or Termination as
“full”. This responsibility continues after
Completion in respect of any outstanding work. It
would therefore seem that the “proportionate”

5
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
10
CareOfTheWorksAndIndemnitiesGR/2018(1)/17/CLAL www.corbett.co.uk
Clause 18: Exceptional Events
Written by Edward Corbett 1

“Exceptional Events” has replaced “Force contractor of individual obligations that were
Majeure” and the provision is now clause 18 legally or physically impossible; or only of the
rather than clause 19 but otherwise little has Contract as a whole. It seems clearer that this is an
changed. all-or-nothing clause: if it is invoked, the result is

FIDIC appear to have decided that the term “force


majeure” brought with it too much baggage for Article Author
those using it in civil law jurisdictions. Many users Edward Corbett 2
have pre-conceptions about what force majeure is
and is not and perhaps did not consider what
FIDIC meant by the term. With the new term, users
should approach the provision with a more open
mind.

One result of the change in term is that the word


“exceptional” no longer features in the definition:
Force Majeure meant an exceptional event or Email: edward.corbett@corbett.co.uk
circumstance. Of course, it would seem perverse to
argue that an Exceptional Event did not have to be
exceptional; but it is also true that a defined term
means what it is said to mean, not whatever the
chosen term implies.

One improvement introduced into 18.1 is that


strikes and lockouts have been separated out. As
these might properly be regarded as the most
common form of event that entitle the Contractor
to both time and money, it is right that they are not
buried in the more exotic “riot” item.

The anomaly of having a list of events, all of which


give rise to time and money except for one remains.
The natural catastrophes item is still on the list.
Was there any real doubt that earthquakes,
tsunamis, volcanic activity, hurricanes and
typhoons were force majeure?

Clause 18.6 is Release from Performance under the


Law. The question in relation to the equivalent
clause of the 1999 form was whether it relieved a

1
Edward Corbett is a Director at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at edward.corbett@corbett.co.uk
2
The contents of this article should not be treated as legal advice. Please contact the lawyers at Corbett & Co before acting on or relying upon anything stated
in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
ExceptionalEvents/EC/2018(1)/18/CLAL www.corbett.co.uk
Clause 19: Insurance
Written by Richard Adams 1

The insurance requirements both in Clause between the Parties”. Hardly the language of
19 and the related tender information in the clarity.
Contract Data are now considerably more
prescriptive. There is a concern that even where the Parties
essentially remain within the outline of the Clause
The positive aspect may be that this will lead to a 19 terms, many typical insurance policies may well
more careful consideration of what in many not match the now much more specific
applications is a key aspect of the Contract. requirements within Clause 19. What remains to be
seen is whether or not those Parties will correctly
Against that there is a concern that the react and go down the memorandum/addendum
requirements here are now too prescriptive and do route. Failing that, the Clause 19 terms will apply
not allow more flexibility against the known and the scope for misunderstandings to arise is
potentially wide and varied applications of these very real. It seems a pity that the more fail safe
forms. The use of the term “insuring Party” in earlier way of dealing with this has now been lost.
Clause 18 of the 1999 edition, allowed for flexibility
In going to a more prescriptive basis, it is perhaps a
in the allocation of insurance obligations as
missed opportunity that Clause 19 did not at least
between the Parties. At the same time those
address the insurance requirements and
obligations applied with equal effect, depending on
implications against the possibility of:
the Party to which the obligations were assigned.
The new provisions in what is now Clause 19 have • Joint names insurance cover extending to all
done away with the “insuring Party” approach; parties for their Site interests, particularly
almost all the obligations are on the Contractor. In Subcontractors of any tier and other contractors
applications where that is not to be the intended of the Employer, as may be applicable.
position, it will now mean careful amendment to
Clause 19 itself. • The Works forming a part of a larger project, all
at or about the Site.
Furthermore, the earlier flexible approach also
allowed for the terms of what was then Clause 18 to • The presence of significant existing property of
be overridden by specific insurance terms agreed the Employer at or about the Site.
between the Parties before the date of the Letter of
Acceptance. That further flexibility is also now lost, To the extent applicable via the Contract Data, the
at least within the new Clause 19. The mechanism new requirements relating to professional
now lies in adding “memoranda” to the Letter of indemnity insurance in Sub-Clause 19.2.3 will
Acceptance; see the asterisked footnote against the deserve careful review by a tendering Contractor
heading on the form of the Letter of Acceptance, with his professional insurance advisor. The basis
and which incorrectly refers to Sub-Clause 1.1.51. It of the required cover, the absence of the usual
should refer to the defined term of “Letter of protection where such cover is no longer available
Acceptance” which is at Sub-Clause 1.1.50, and at reasonable market rates, and the requirement to
which does refer to the possibility of including, extend such professional indemnity insurance to
“annexed memoranda comprising agreements fitness for purpose, are likely to be problematic.

1
Richard Adams is a Consultantat Corbett & Co. International Construction Lawyers Ltd. He can be contacted at richard.adams@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
Insurance/RA/2018(1)/19/CLAL www.corbett.co.uk
In summary the more extensive and prescriptive
nature of Clause 19 and the associated Contract
Data is a positive development if the outcome is
that Parties will consider the requirements carefully
and take the necessary professional insurance
advice.

The potential downside is twofold; (i) the


provisions of Clause 19 may well need amending
even where the Parties intend to remain within its
structure, and (ii) the route to ensuring that such
amendment is properly incorporated into any
Contract is now not so clear and lacks the earlier
and more fail safe provision to allow amendments
specifically agreed between the Parties to prevail
over what is now Clause 19.

Article Author
Richard Adams2

Email: richard.adams@corbett.co.uk

2
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
Insurance/RA/2018(1)/19/CLAL www.corbett.co.uk
Clause 20: Employer’s and Contractor’s Claims
Written by Gabriel Mulero Clas 1

The 1999 Clause 20 has now been divided into Notice of Claim Fully detailed
Clauses 20 and 21 whereby Clause 20 refers to Claim
Claims and Clause 21 refers to Disputes and Time As soon as Within 84 days
practicable and after becoming
Arbitration. Another main upgrade is that within 28 days aware (or should
Employer’s Claims now need to follow the same after becoming have become
procedure. The main list of Employer’s and aware (or should aware) of the event
Contractor’s Claims is as follows: have become or circumstance, or
aware) of the event as agreed by the
a. Additional payment; or circumstance. Engineer.
Contents Written A statement of the
b. Reduction in the Contract Price; description of contractual and/or
event or other legal basis of
c. Extension of the DNP; and
circumstance, the Claim.
d. Extension of time. expressly
identified as a
Another main difference is the express distinction Notice.
between the Claims listed above and any other
Claim (Sub-Clause 20.1 (c)). The other Claims still If the Party fails to serve either the Notice of Claim
need to be determined by the Engineer under Sub- or the contractual/legal basis in the fully detailed
Clause 3.7, though they do not need to follow the Claim within the allotted time, the Notice will be
strict requirements of the Claims procedure deemed invalid and the Claim is time-barred. For
explained below. The starting point of the other the time-bar to bite, the Engineer must give Notice
Claims is not the event or circumstance, but the to the claiming Party within 14 days of (a) receiving
disagreement between the parties. The Notice only the Party’s Notice or (b) the lapse of the 84 days for
needs to be given as soon as practicable from this the fully detailed Claim. If the Engineer fails to give
point and contain details of the Party’s case and the either Notice, the Party’s Notice of Claim shall be
disagreement. The Notice is the only requirement deemed valid. Nevertheless, the other Party may, in
for the Engineer to issue its agreement or turn, give a subsequent Notice disagreeing with the
determination under Sub-Clause 3.7. deemed validity, in which case, the Engineer shall
review the issue in its determination. More
On the other hand, the main Claims must follow a importantly, if the Engineer issues its Notice
Claims procedure (Sub-Clause 20.2) consisting of a deeming the Notice of Claim invalid, the claiming
Notice of Claim, a fully detailed Claim, and the Party may include in its fully detailed Claim details
Engineer’s agreement or determination (pursuant of its disagreement or justification of the late
to Sub-Clause 3.7). This has not changed from the submission. Even if a 14-day Notice has been
1999 edition but the details of this procedure have. issued, the Engineer shall nevertheless agree or
More importantly, the content requirements that determine the substance of the Claim pursuant to
carry time-bar implications are rather specific. Sub-Clause 3.7 and include a determination on the
validity of the Notice.
These requirements are:
Therefore, the 2017 edition has added a time-bar
on the fully detailed Claim but has tempered this

1
Gabriel Mulero Clas is a Lawyer at Corbett & Co. International Construction Lawyers Ltd. He can be contacted at gabriel.muleroclas@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
EmployersContractorsAndClaims/GMC/2018(1)/20/CLAL www.corbett.co.uk
with the opportunity for the claiming Party to arguments that have not been put forth at the
object to the time-bar. The claiming Party can DAAB stage. Therefore, it is difficult to see why
either argue that the Notice of Claim or the fully specifying the contractual/legal basis at the fully
detailed Claim were served within their time limits detailed Claim stage is so important.
or submit a justification for its delay. The Engineer
may consider prejudice to the other Party and prior Other items:
knowledge by the other Party. However, • Contemporary records – Parties are ordered to
considering that the content requirements for keep contemporary records of the Claim, and
either the Notice of Claim or the fully detailed the Engineer may monitor and inspect these
Claim are so simple, it is hard to think of a records and instruct the Contractor to keep
justifiable reason why anyone would be late apart additional records.
from the usual difficulty of identifying the start of
the period. It will probably be easier to argue that • Additional particulars – Additional particulars
the Notice was not in fact served late, perhaps by are requested by way of Notice describing them
basing the argument on Mr Justice Akenhead’s and the reasons for requiring them. The
Obrascon judgement. Engineer must issue a response on the
contractual/legal arguments within 42 days and
Also, the Notice does not need reference to the Sub- then its agreement or determination once it
Clause on which it is based. However, as mentioned receives the additional particulars.
above, the fully detailed Claim requires a statement • Continuing effect – For Claims with continuing
of contractual/legal basis. With such scant content effect, the fully detailed Claim is interim and
requirement at each stage, it is arguable that the the Party must serve further interim particulars
fully detailed Claim is little more than a second at monthly intervals. These interim particulars
Notice of Claim. An Engineer will struggle to reach are not subject to the time requirements that
a determination of a claim based solely on a light apply to the first fully detailed Clam.
description of the event or circumstance and the
contractual/legal argument behind it. On most • IPC – Until a Claim is agreed or determined,
claims, the Engineer will need more details of the IPCs must include the amount that has been
cause and the effect of the Claim in order to reach a reasonably substantiated as due.
sensible determination. Therefore, the 2017 edition • Set-off – Employers can only set off against or
may give rise to Parties submitting scant Notices make any deduction from amounts due to the
and Claims followed by requests from the Engineer Contractor if they follow the claims procedure.
for additional particulars.

Furthermore, Sub-Clause 21.6 states that Parties Article Author


will not be limited in the arbitration “to the
evidence or arguments previously put before the Gabriel Mulero Clas2
DAAB […] or to the reasons for dissatisfaction
given in the Party’s NOD […]” Therefore, it appears
that in the arbitration stage the Parties can change
the contractual/legal basis of their Claims. Could
the other Party argue that it may be prejudiced if
the contractual/legal basis is changed? Surely not if
the arbitrator can decide on the Claim based on Email: gabriel.muleroclas@corbett.co.uk

2
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
EmployersContractorsAndClaims/GMC/2018(1)/20/CLAL www.corbett.co.uk
Clause 21: Disputes and Arbitration
Written by Sara Ehsani1

Clause 20 of 1999 Yellow Book which provide assistance and/or informally discuss
covered the multi-tier dispute resolution and attempt to resolve any issue or
provisions, has been divided into two parts disagreement.
in the 2017 Yellow Book, clause 20 and
clause 21. Clause 20 of 2017 Yellow Book - Reference of a dispute to the DAAB will be
now covers the Claims to the Engineer and
deemed to interrupt the applicable limitation
Clause 21 covers Disputes and Arbitration.
period unless prohibited by the law.
The dispute resolution mechanism in the 2017
Yellow Book still contains the following steps: - The amount awarded by the DAAB or the
Arbitral Tribunal to any party shall become
immediately payable without any certification
• Making a claim to the Engineer,
or Notice.
• Referring to the DAB,
• Attempting Amicable Settlement, and - The DAAB decisions are now expressly binding
• ICC Arbitration. on the Engineer.

- A Notice of Dissatisfaction (NOD) can be


The main differences introduced by the 2017 Yellow drafted in respect of parts of the DAAB’s
Book are as follows: decision. The parts specified in the NOD and
any parts affected by such part, are deemed to
- There is now a Dispute Avoidance/Adjudication
be severable from the rest of the decision. The
Board (DAAB) rather than a Dispute
rest of the DAAB’s decision shall be final and
Adjudication Board (DAB).
binding on the Parties.

- There is now a standing DAAB rather than an ad


- Non-compliance with the binding but not final
hoc DAB. The DAAB is appointed at the outset
decision of the DAAB can be directly referred to
unless Parties otherwise agree.
Arbitration under the 2017 Yellow Book and the
Arbitral Tribunal has the power to issue an
- If one Party refuses to sign a DAAB agreement
interim or provisional measure or an award
within 14 days of the other Party’s request to do
enforcing the decision. The provisional measure
so, then the appointing entity or official named
or an award is subject to the express reservation
in the Contract Data appoints the member after
that the rights of the Parties are reserved until
which the Parties and the member(s) are
the merits of the dispute are resolved by an
deemed to have signed the DAAB Agreement.
award.

- Similar to the 2008 Gold Book, a new sub-clause


- The amicable settlement period has been
for avoidance of disputes has been introduced.
reduced from 56 days to 28 days.
This allows the parties to ask the DAAB to

1
Sara Ehsani is a Lawyer at Corbett & Co. International Construction Lawyers Ltd. She can be contacted at sara.ehsani@corbett.co.uk

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
1
DisputesAndArbitration/SE/2018(1)/21/CLAL www.corbett.co.uk
Article Author
Sara Ehsani 2

Email: sara.ehsani@corbett.co.uk

2
The contents of this article should not be treated as legal advice. Please
contact the lawyers at Corbett & Co before acting on or relying upon
anything stated in this article.

Tel: + 44 (0)20 8614 6200


Fax: + 44 (0)20 8614 6222
Email: info@corbett.co.uk
2
DisputesAndArbitration/SE/2018(1)/21/CLAL www.corbett.co.uk

You might also like