Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Pump-Pipe Alignment

Piping issues directly affect a pump's life and its performance. With an initial, common-sense
investment and proper attention to details, the pumps will last longer, with fewer failures of seals,
shafts, bearings and couplings. More equipment uptime and less lost production will result in
significant cost savings and fewer headaches.

1. Occassionally, anchors (only if NO thermal growth, which is rare) can


be used for the pump piping.
At this point the pipe should be securely anchored just before the last spool, to prevent future
growth toward the pump’s flanges. The piping lay out should not be finalized until certified
elevation drawings are received from the engineering group or from the pump vendor. Once the
final certified drawings are received, the final isometrics can be completed and the piping takeoff
can be performed.

The delivery of the equipment can either be early or it can be late in arriving at the site. When the
equipment is late it is critical to have certified elevation prints of the equipment. The certified
prints ensure that the isometrics required for the piping takeoffs can be made without impacting
the construction schedule. If the equipment is early, it will arrive at the site before the construction
team needs it for installation. Preparations must be made for long-term storage. Using oil mist
lubrication is customary to keep the equipment in as-shipped condition while it is stored. The
pressurization of the bearing housing and the casing with just 10 to 20 H2O pressure prevents
moisture and contaminants from entering the sealed areas and damaging the components. In
addition, early delivery of equipment to the site allows for the verification of the actual
measurements.

2. Rough Alignment Phase


Note that the motor and the pump are not yet coupled and the baseplate is still sitting free, not
grouted.

A. Correct configuration - Sliding support does not keep the piping from sliding up/away.
B. Piping is restrained (cannot slide up/away) with high thermal expansion loads.

C. "Anchor" will allow pipe to expand toward/into the pump. This is a problem, causing high axial
loading

3. Baseplate Leveling Pads and Grout Location


Once rough alignment has been completed, remove the equipment (pump, motor gearbox) from
the baseplate. Level the baseplate to a maximum out of level of 0.025 inch (0.06 millimeter) from
end to end in two planes. Use machined pads as the base for the leveling instruments. Inspect the
foundation for cleanliness, and if not clean, use a solvent to remove grease and oil.

4. Typical Anchor Bolt and Leveling Wedges


Allow time for the cleaning substances to evaporate. Form the base using the appropriate
techniques to allow for the weight, temperature rise and fluidity of the grout material. Use epoxy
grout to secure the base, and allow the grout to cure, following the grout manufacturer’s
recommendations. This normally requires 24 hours at 80 F (27 C). Remove the forms and clean
all sharp residue and edges from the foundation

5. Potential bolt-bound Situation Due to Tight Clearances Between Bolt,


Feet and base
The rough alignment step, mentioned above, is critical to minimize the changes that will be
required to appropriately fit the piping to the pump. At the last stage, when the final spools are
installed, the final alignment will be achieved with small adjustments. This will minimize the
adjustments required on the motor feet/bolts. Unfortunately, motor hold-down bolts are often too
tight and allow for only small adjustments to the motor before becoming bolt bound.

Motor manufacturers could improve this situation significantly if motor feet were slotted by design
rather than drilled for bolts. Figure 5 shows the tightness of space available to insert the foot hold-
down bolt. This illustrates once again why good alignment at Step 3 can save time and the cost of
having to alter motor feet (which can be a nightmare) by slotting or reaming.
6. Reinstall the Pump and the Motor on the Baseplate.
Reinstall the pump and the motor on the baseplate. Rough align the equipment again, using a
reverse indicator, laser alignment or similarly accurate technique. It should now be easy to fine-
tune the motor movement within the allowable alignment target without becoming bolt bound.
This is possible because of completion of the rough alignment during Step 4. Note: Never install
shims under the pump feet. If the shims are lost or misplaced then alteration to the piping may be
required to get the pump within the required alignment specification. The normal procedure is to
place 0.125-inch (3.2-millimeter) thick shims under the motor feet. This allows for adjustments
that will be required during final alignment

7. Final Connection of the Suction Piping


Make up the final spool pieces for the suction and discharge spaces. Bring the piping to the pump
now

8. Final Piping
In figure, anchor is placed incorrectly. It will restrain the pipe from freely moving away from the
pump during thermal growth. The pipe will expand from the anchor into the pump. (see discussion
in Step 2)

As a final alignment step, bring the piping to the equipment; take final measurements, tack weld
the spools in place. At this time the spools can be removed and taken back to the hot work permit
area to finalize the weld. Leave a square and parallel gap between the flange faces. The gap should
be wide enough to accommodate the size of the gasket required, plus 1/16 - 1/8”, depending on
piping sizing. (This is the only distance over which the piping will be pulled. However, because it
is properly anchored before the spool pieces, this length is short, and stresses are
minimized). Final align the equipment, taking into account hot and cold operating conditions,
using two indicators on the pump shaft coupling area.
9. Overhead View of Motor and Pump
As the piping is tightened into place, the shaft must not be moved more than 0.002 inch (0.005
millimeter). Otherwise, modify the spool pieces until the piping misalignment is fixed. Several
conditions are common when piping is misaligned. Some of these conditions are the mechanical
seal and/or the bearings running hot and other component failures. A quick analysis of the failed
parts will clearly show the signs of piping misalignment. To make a final confirmation of the
symptoms, unbolt the piping while measuring the movement in the vertical and horizontal plane.
Again, piping that moves more than 0.002 inch (0.005 millimeter) must be modified to correct the
situation

10. Piping Alignment Verification


Place an indicator in the horizontal and vertical planes, using the motor and pump coupling.

Uncouple the pump and motor, while watching the indicators for movement. Start unbolting the
flanges, and continue watching for movement in the indicators. If the needle jumps more than
0.002 inch (0.005 millimeter) the piping has to be modified to improve the pump’s performance.

You might also like