DOE Power Project Registration Procedures
DOE Power Project Registration Procedures
Procedures
for
Energy Projects
Department of Energy
Empowering the Filipino
Process Flow for Conventional Power Projects
Department of Energy
Empowering the Filipino
Process Flow for Conventional Power Projects
Registration
Department of Energy
Empowering the Filipino
Process Flow for Conventional Power Projects
DOE EPIRA Law (RA 9136)
INVESTOR
Pre-
Registration Construction
Pre- Development
Registration Construction (Construction)
• LGU (Permits, Clearances)
• DOLE (Occupational Safety and Health,
Development
High Pressure Valves, Boilers, Moving
Equipment)
• BOC (Importation Clearance)
• NGCP (Connection Agreement,
Transmission Service Application,
Metering Service Agreement, Certificate
of Approval to Connect)
• ERC (Certificate of Compliance, Point-to-
Point Connection)
• PEMC (Certificate of Registration)
Department of Energy
Empowering the Filipino
Process Flow for Conventional Power Projects
Pre-
INVESTOR
Development Monitoring
Registration Construction
(Construction)
• LGU (Permits)
• NGCP
Development
• ERC
• TRANSCO
• BOI
• DOE
Department of Energy
Empowering the Filipino
Process Flow for Renewable Energy Power Projects
Pre-Development Development
[Construction & Commissioning]
Department of Energy
Empowering the Filipino
Process Flow for Renewable Energy Power Projects
Department of Energy
Empowering the Filipino
Process Flow for Renewable Energy Projects
EPIRA Law (RA 9136)
DOE Renewable Energy Law (RA 9513)
INVESTOR
Registration
& Application
Department of Energy
Empowering the Filipino
Process Flow for Renewable Energy Projects
EPIRA Law (RA 9136)
DOE Renewable Energy Law (RA 9513)
INVESTOR
Registration Pre-
& Application Development
Registration Pre-
& Development Conversion
Application
• Developer (Declaration of
Commerciality & Application of
Conversion)
DOE (Certificate of Confirmation
of Commerciality [CoCoc])
Department of Energy
Empowering the Filipino
Process Flow for Renewable Energy Power Projects
Department of Energy
Empowering the Filipino
Thank You!
Department of Energy
Empowering the Filipino
MILESTONE APPROACH MATRIX
(Pre-Development Stage)
MILESTONE
MILESTONE
RESC TYPE MILESTONE ACTIVITY COST REMARKS
PERIOD
(at 100%)
1. Completion of
Reconnaissance Geological
Surveys
Pre-Development
GEOTHERMAL 2. Mandatory Activities 12 months Php 6,500,000.00
a. LGU Endorsements
at 5 years
b. Licenses/Permits
Acquisition
1. Pre-Feasibility Study /
Reconnaissance Study
2. Detailed Topography
Survey
3. Completion of
Hydrological Study Pre-Development
HYDROPOWER 12 months Php 1,500,000.00
4. Field Based Investigation at 2 years
(NCIP)
5. Mandatory Activities
a. LGU Endorsements
b. Licenses/Permits
Acquisition
Department of Energy
Empowering the Filipino
MILESTONE APPROACH MATRIX
(Pre-Development Stage)
MILESTONE
MILESTONE
RESC TYPE MILESTONE ACTIVITY COST REMARKS
PERIOD
(at 100%)
1. Procurement of
meteorological mast
2. Installment of meteorological
mast Pre-Development
WIND 3. Land/rights acquisition
12 months Php 2,000,000.00
at 3 years
4. Mandatory Activities
a. Public Consultations
b. LGU Endorsements
1. Initial modelling and annual
energy yield estimates
2. Land/rights acquisition Pre-Development
SOLAR 3. Mandatory Activities
6 months Php 500,000.00
at 2 years
a. Public Consultations
b. LGU Endorsements
1. Pre-Feasibility Study/Prelim.
Resource Assessment
2. Detailed site Survey
3. Field Based Investigation Pre-Development
OCEAN (NCIP)
12 months Php 1,500,000.00
at 3 years
4. Mandatory Activities
a. LGU Endorsements
b. Licenses/Permits
Department of Energy
Empowering the Filipino
MILESTONE APPROACH MATRIX
(Development Stage)
Procurement of
Electromechanical Equipment Php 30,000,000.00 per
HYDROPOWER (EME) or Proof of Contract with
Year 5 to 6
MW
the supplier of EME
Department of Energy
Empowering the Filipino
MILESTONE APPROACH MATRIX
(Development Stage)
MILESTONE
MILESTONE
RESC TYPE MILESTONE ACTIVITY COST REMARKS
PERIOD
(at 100%)
Electromechanical Equipment Php 95,000,000.00
WIND Year 5 to 6
(At 80% completion) per MW
Biomass (Non-
Existing Facility) –
the Pre-
1. Site acquisition and pre-
Development stage
development activities Milestone: Php
Milestone : 6 is subsumed and
(groundwater test, soil and 7,000,000.00
months made part of the
geothechnical analyses) (fixed)
BIOMASS Development Stage
2. Licensing, Permits, and
Development : 3 already
Clearances Development: Php
years Biomass (Existing
3. Signed Feedstock Supply 100,000.00/MW
Facility) – this
Agreements
automatically goes
to Development
Stage
Department of Energy
Empowering the Filipino
MILESTONE APPROACH MATRIX
(Development Stage)
Procurement of
Electromechanical
Php 30,000,000.00 per
OCEAN Equipment (EME) or Proof of Year 5 to 6
MW
Contract with the supplier of
EME
Department of Energy
Empowering the Filipino
Registration/Setting-up a Company
Securities of Exchange Commission Certificate of Endorsement from DOE TIN & Registration
Department of Energy
Empowering the Filipino
Regulatory Requirement
(Pre-Dev’t Service Contract)
Proof of Compatibility with the existing Land Use Plan, Certificate of Non-Coverage /
DENR – EMB / LLDA / Ecozone Proof of Ownership or Authority over the Project Site, Environmental Compliance
Feasibility Study Certificate
Department of Energy
Empowering the Filipino
Regulatory Requirement
(Pre-Dev’t Service Contract)
Certificate of Non-Overlap /
National Commission on RE Service / Operating Contract – Certificate of
Certificate Precondition / Free Prior
Indigenous Peoples Registration, CNC/ECC, Endorsement from DOE
Informed Consent
Department of Energy
Empowering the Filipino
Regulatory Requirement
(Pre-Dev’t Service Contract)
DENR – FMB (starts at CENRO to SEC Registration, Initial IEE, Appropriate Clearance from NCIP, Special Land Use Permit, Tree
DENR Secretary) Endorsement from CENRO, PENRO and RED Cutting Permit
Department of Energy
Empowering the Filipino
Regulatory Requirement
(Development Service Contract)
Department of Energy RE Service / Operating Contract – Certificate of MOA for Establishment of Trust
(EPIMB) Registration, SEC Registration Account Host Communities
Department of Energy MOA for Establishment of Trust Account Host Certificate of Endorsement for ERC’s
(EPIMB) Communities Certificate of Compliance
Distribution Utility/ Electric RE Service / Operating Contract – Certificate of Power Purchase Agreement, RE
Cooperative Registration Supply Agreement
Notice of Plant Readiness and ERC Certificate of Testing Certificate of Endorsement for FIT (if
Department of Energy – REMB
and Commissioning applicable)
Department of Energy
Empowering the Filipino
Regulatory Requirement
(Development Service Contract)
Department of Energy
Empowering the Filipino