This document provides a project schedule for the construction of an elevated viaduct, ramps, and two elevated stations for the Delhi Metro Rail Corporation (DMRC) project CC50. It involves the design and construction of the civil structures including architectural finishes, water supply, sanitation, and drainage. The schedule outlines pre-construction activities from September 2013 to August 2015 including surveys, soil investigations, mobilization, setup of facilities, and design work, with the goal of completing the viaduct, ramps, and station structures.
This document provides a project schedule for the construction of an elevated viaduct, ramps, and two elevated stations for the Delhi Metro Rail Corporation (DMRC) project CC50. It involves the design and construction of the civil structures including architectural finishes, water supply, sanitation, and drainage. The schedule outlines pre-construction activities from September 2013 to August 2015 including surveys, soil investigations, mobilization, setup of facilities, and design work, with the goal of completing the viaduct, ramps, and station structures.
This document provides a project schedule for the construction of an elevated viaduct, ramps, and two elevated stations for the Delhi Metro Rail Corporation (DMRC) project CC50. It involves the design and construction of the civil structures including architectural finishes, water supply, sanitation, and drainage. The schedule outlines pre-construction activities from September 2013 to August 2015 including surveys, soil investigations, mobilization, setup of facilities, and design work, with the goal of completing the viaduct, ramps, and station structures.
PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and
Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works
ID Task Name Duration Start Finish 2014 2015
A S O N D J F M A M J J A S O N D J F M A M J J A S O 0 DMRC CC50 CONSTRUCTION PROGRAMME 628 days Fri 06-09-13 Tue 08-09-15 1 1 Preconstruction Activities 621 days Fri 06-09-13 Mon 31-08-15 2 1.1 Contractual Activities 29 days Fri 06-09-13 Wed 09-10-13 3 1.1.1 Issue of LOI by DMRC 0 days Fri 06-09-13 Fri 06-09-13 4 1.1.2 Notice to Proceed 0 days Mon 09-09-13 Mon 09-09-13 5 1.1.3 Commencement of Work 0 days Mon 09-09-13 Mon 09-09-13 6 1.1.4 Submission of Performance BG 0 days Thu 19-09-13 Thu 19-09-13 7 1.1.5 Submission of Power of Attorney 0 days Thu 19-09-13 Thu 19-09-13 8 1.1.6 Signing of Contract Agreement 0 days Wed 09-10-13 Wed 09-10-13 9 1.2 Client Deliverables 90 days Mon 09-09-13 Mon 23-12-13 10 1.2.1 Handover of Casting Yard/Contractor's Working Area 0 days Mon 09-09-13 Mon 09-09-13 11 1.2.2 Handover of un obstructed Working Area for Viaduct, station & interconnecting structure, 90 days Tue 10-09-13 Mon 23-12-13 12 1.2.3 Handover of Final Alignment Drawings 0 days Wed 11-09-13 Wed 11-09-13 13 1.2.4 Handover of Architectural Plan & Drawings -Stations 0 days Wed 11-09-13 Wed 11-09-13 14 1.2.5 Handing over of Survey Bench Mark & Issue of Co-ordinates 0 days Mon 09-09-13 Mon 09-09-13 15 1.2.6 Permission for Tree Cutting / transplantation within alignment 57 days Tue 10-09-13 Thu 14-11-13 16 1.2.7 Permission for Dismantling of structures within alignment 0 days Tue 17-09-13 Tue 17-09-13 17 1.2.8 Clearance of HT Line by concerned auth. Within the alignment 30 days Wed 23-10-13 Tue 26-11-13 18 1.3 Contractual Submittals 618 days Tue 10-09-13 Mon 31-08-15 19 1.3.1 Preparation & Submission of Quality Plan 0 days Mon 07-10-13 Mon 07-10-13 20 1.3.2 Preparation & Submission of Safety and Environment Management Plan 0 days Mon 07-10-13 Mon 07-10-13 21 1.3.3 Submission of Quarterly audit report of safety,quality and environment 204 days Tue 10-09-13 Mon 31-08-15 22 1.4 Submission of Construction programme, Establishing site office KD-01 0 days Wed 09-10-13 Wed 09-10-13 23 1.5 Survey & Set out Works 129 days Thu 12-09-13 Sat 08-02-14 24 1.5.1 Initial Survey and set out, fixing of coordinates 40 days Thu 12-09-13 Mon 28-10-13 25 1.5.2 Survey of Charted Utility (Tree , Electrical Post , HT Line , Building etc.) & sub of report 30 days Wed 18-09-13 Tue 22-10-13 26 1.5.3 Utility Identification & Submission of Report 60 days Mon 02-12-13 Sat 08-02-14 27 1.6 Soil Investigation 85 days Wed 11-09-13 Wed 18-12-13 28 1.6.1 Soil Investigation -From.Dwarka & Najafgar Depot 30 days Wed 11-09-13 Tue 15-10-13 29 1.6.2 Labr. Testing and submission of reports 70 days Sat 28-09-13 Wed 18-12-13 30 1.7 Mobilization and Setup 90 days Tue 10-09-13 Mon 23-12-13 31 1.7.1 Initial Staff Mobilization 30 days Tue 10-09-13 Mon 14-10-13 32 1.7.2 Finalize Casting Yard Layout 3 days Tue 10-09-13 Thu 12-09-13 33 1.7.3 Set Up of Site office, Laboratory , Store, cement godown 70 days Fri 13-09-13 Tue 03-12-13 34 1.7.4 Civil Wrks , Erec & Commission 1st batching Plant 45 days Fri 20-09-13 Mon 11-11-13 35 1.7.5 Civil Wrks , Erec & Commission 2nd batching Plant 50 days Sat 26-10-13 Mon 23-12-13 36 1.7.6 Set up of casting yard (Civil & Mechanical Works) 75 days Sat 21-09-13 Tue 17-12-13 37 1.7.7 Fabrication of 1st Segment/ I Girder Formwork 40 days Thu 24-10-13 Mon 09-12-13 38 1.8 Commission 1st batching Plant KD-02 (11-Nov-13) 0 days Mon 11-11-13 Mon 11-11-13 39 1.9 Commission 2nd batching Plant - KD-04 (23-Dec-13) 0 days Mon 23-12-13 Mon 23-12-13 40 1.10 Completion of 1st Formwork of segment production line for 0 days Mon 09-12-13 Mon 09-12-13 41 1.11 Design & Drawings 386 days Tue 10-09-13 Wed 03-12-14 42 1.11.1 Finalize Detailed Design Consultant 15 days Tue 10-09-13 Thu 26-09-13 43 1.11.2 Approval of Detailed Design Consultant 10 days Fri 27-09-13 Tue 08-10-13 44 1.11.3 Proposal of Proof Check consultant for checking of I girder design 0 days Sat 26-10-13 Sat 26-10-13 45 1.11.4 Approval of Proof Check consultant for checking of I girder design 0 days Wed 20-11-13 Wed 20-11-13 46 1.11.5 Submission of DBR - Viaduct 15 days Fri 27-09-13 Mon 14-10-13 47 1.11.6 Approval of DBR - Viaduct 7 days Tue 15-10-13 Tue 22-10-13 48 1.11.7 Submission of DBR - Stations 15 days Fri 27-09-13 Mon 14-10-13 49 1.11.8 Approval of DBR - Stations 7 days Tue 15-10-13 Tue 22-10-13 50 1.11.9 Submission of Span Arrangement Drawing (Based on Alignment GAD) 15 days Thu 12-09-13 Sat 28-09-13 51 1.11.10 Approval of Span Arrangement Drawing (Based on Alignment GAD) 7 days Mon 30-09-13 Mon 07-10-13 52 1.11.11 Initial Pile Design/Drg 52 days Wed 16-10-13 Sat 14-12-13 53 1.11.11.1 Submission of Design /Drg of Test Pile 45 days Wed 16-10-13 Fri 06-12-13 54 1.11.11.2 Approval of Design /Drg of Test Pile 7 days Sat 07-12-13 Sat 14-12-13 55 1.11.12 Pile /Pile Cap /Pier Design/Drg -Viaduct 140 days Mon 16-12-13 Tue 27-05-14 56 1.11.12.1 Submission Design / Drg Wrk Pile/ -Viaduct 75 days Mon 16-12-13 Wed 12-03-14 57 1.11.12.2 Approval Design / Drg Wrk Pile -Viaduct 75 days Tue 24-12-13 Thu 20-03-14 58 1.11.12.3 Submission Design / Pile Cap/Pier -Viaduct 100 days Thu 23-01-14 Mon 19-05-14 59 1.11.12.4 Approval Design / Pile Cap/Pier -Viaduct 100 days Fri 31-01-14 Tue 27-05-14 60 1.11.13 I-Girder, Parapet Design/Drg -Viaduct 57 days Wed 27-11-13 Fri 31-01-14 61 1.11.13.1 Submission Design / Drg I-Girder & Parapet -Viaduct 50 days Wed 27-11-13 Thu 23-01-14 62 1.11.13.2 Approval Design / Drg I-Girder & Parapet -Viaduct 50 days Thu 05-12-13 Fri 31-01-14 63 1.11.14 Super str. Works (Cross Girder, Pier Cap & Deck slab) Design/Drg -Viaduct 82 days Sat 18-01-14 Wed 23-04-14
BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)
Page 1 of 5
ITD CEMENTATION INDIA LTD
PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works
ID Task Name Duration Start Finish 2014 2015
A S O N D J F M A M J J A S O N D J F M A M J J A S O 64 1.11.14.1 Submission Design / Drg Sup.str works -Viaduct 75 days Sat 18-01-14 Tue 15-04-14 65 1.11.14.2 Approval Design / Drg sup. Str works -Viaduct 75 days Mon 27-01-14 Wed 23-04-14 66 1.11.15 Ramp 40 days Sat 14-12-13 Wed 29-01-14 67 1.11.15.1 Submission Design / Drg for Ramp 30 days Sat 14-12-13 Fri 17-01-14 68 1.11.15.2 Approval Design / Drg for Ramp 10 days Sat 18-01-14 Wed 29-01-14 69 1.11.16 Pile / Pile Cap/Footing /Pier & Column Design & Drg -Stations 141 days Wed 27-11-13 Fri 09-05-14 70 1.11.16.1 Submission of Framing Plan - Dwarka Station 15 days Wed 27-11-13 Fri 13-12-13 71 1.11.16.2 Approval of Framing Plan - Dwarka Station 7 days Sat 14-12-13 Sat 21-12-13 72 1.11.16.3 Submission Pile / Pile Cap/Footing /Pier & Column Design & Drg -Dwarka Station 90 days Tue 31-12-13 Mon 14-04-14 73 1.11.16.4 Approval Pile / Pile Cap/Footing /Pier & Column Design & Drg -Dwarka Station 90 days Wed 08-01-14 Tue 22-04-14 74 1.11.16.5 Submission of Framing Plan - Najafgarh Station 15 days Sat 14-12-13 Tue 31-12-13 75 1.11.16.6 Approval of Framing Plan - Najafgarh Station 7 days Wed 01-01-14 Wed 08-01-14 76 1.11.16.7 Submission Pile / Pile Cap/Footing /Pier & Column Design & Drg -Najafgarh Station 90 days Fri 17-01-14 Thu 01-05-14 77 1.11.16.8 Approval Pile / Pile Cap/Footing /Pier & Column Design & Drg -Najafgarh Station 90 days Sat 25-01-14 Fri 09-05-14 78 1.11.17 Superstructure Design & Drg -Stations 200 days Tue 15-04-14 Wed 03-12-14 79 1.11.17.1 Submission Superstr. Design & Drg -Dwarka Station 90 days Tue 15-04-14 Mon 28-07-14 80 1.11.17.2 Approval Superstr. Design & Drg -Dwarka Station 60 days Tue 29-07-14 Mon 06-10-14 81 1.11.17.3 Submission Superstr. Design & Drg -Najafgarh Station 120 days Fri 02-05-14 Thu 18-09-14 82 1.11.17.4 Approval Superstr. Design & Drg -Najafgarh Station 65 days Fri 19-09-14 Wed 03-12-14 83 1.12 Mix Design 90 days Fri 27-09-13 Thu 09-01-14 84 1.12.1 Finalize Mix Design for Piling 40 days Fri 27-09-13 Tue 12-11-13 85 1.12.2 Finalize Mix Design for-Precast 40 days Wed 09-10-13 Sat 23-11-13 86 1.12.3 Finalize Mix Design for Cast-in-situ 40 days Mon 25-11-13 Thu 09-01-14 87 1.13 Work Methodology 276 days Tue 08-10-13 Mon 25-08-14 88 1.13.1 Submission of Methodology for Piling by Rotary Piling Rig 15 days Tue 08-10-13 Thu 24-10-13 89 1.13.2 Approval of Methodology for Piling by Rotary Piling Rig 5 days Fri 25-10-13 Wed 30-10-13 90 1.13.3 Submission of Methodology for Pile Cap /Pier/Piercap 15 days Wed 25-12-13 Fri 10-01-14 91 1.13.4 Approval of Methodology for Pile Cap /Pier/Piercap 5 days Sat 11-01-14 Thu 16-01-14 92 1.13.5 Submission of Methodology for I Girder Casting & Stressing 15 days Tue 03-12-13 Thu 19-12-13 93 1.13.6 Approval of Methodology for I Grder Casting & Stressing 5 days Fri 20-12-13 Wed 25-12-13 94 1.13.7 Submission of Methodology for I Girder erection 15 days Fri 14-02-14 Mon 03-03-14 95 1.13.8 Approval of Methodology for I Girder erection 5 days Tue 04-03-14 Sat 08-03-14 96 1.13.9 Submission of Methodology for Parapet erection 15 days Fri 28-03-14 Mon 14-04-14 97 1.13.10 Approval of Methodology for Parapet erection 5 days Tue 15-04-14 Sat 19-04-14 98 1.13.11 Submission of Methodology for Initial Pile Load Test 15 days Thu 10-10-13 Sat 26-10-13 99 1.13.12 Approval of Methodology for Initial Pile Load Test 5 days Mon 28-10-13 Fri 01-11-13 100 1.13.13 Submission of Methdology for Cast insitu deck slab at Viaduct 15 days Thu 16-01-14 Sat 01-02-14 101 1.13.14 Approval of Methdology for Cast insitu deck slab at Viaduct 5 days Mon 03-02-14 Fri 07-02-14 102 1.13.15 Submission of Methdology for Construction of Ramp 15 days Sat 30-11-13 Tue 17-12-13 103 1.13.16 Approval of Methdology for Construction of Ramp 5 days Wed 18-12-13 Mon 23-12-13 104 1.13.17 Submission of Methdology for RCC works at Stations 15 days Tue 28-01-14 Thu 13-02-14 105 1.13.18 Approval of Methdology for RCC works at Stations 5 days Fri 14-02-14 Wed 19-02-14 106 1.13.19 Submission of Methdology for Construction of Substructures at Najafgarh Drain Portion 15 days Wed 18-12-13 Fri 03-01-14 107 1.13.20 Approval of Methdology for Construction of Substructures at Najafgarh Drain Portion 5 days Sat 04-01-14 Thu 09-01-14 108 1.13.21 Submission of Methdology for Integration of old and new viaduct at Dwarka Station 15 days Sat 02-08-14 Tue 19-08-14 109 1.13.22 Approval of Methdology for Integration of old and new viaduct at Dwarka Station 5 days Wed 20-08-14 Mon 25-08-14 110 1.13.23 Submission of Methdology for Casting of Precast parapet 15 days Tue 28-01-14 Thu 13-02-14 111 1.13.24 Approval of Methdology for Casting of Precast parapet 5 days Fri 14-02-14 Wed 19-02-14 112 1.13.25 Submission of Methdology for tests to be performed at Site Lab 15 days Thu 12-12-13 Sat 28-12-13 113 1.13.26 Approval of Methdology for tests to be performed at Site Lab 5 days Mon 30-12-13 Fri 03-01-14 114 1.13.27 Submission of Methdology for Load Test on I-girder 15 days Tue 28-01-14 Thu 13-02-14 115 1.13.28 Approval of Methdology for Load Test on I-girder 5 days Fri 14-02-14 Wed 19-02-14 116 1.13.29 Submission of Methdology for Load Test on Span 15 days Tue 08-04-14 Thu 24-04-14 117 1.13.30 Approval of Methdology for Load Test on Span 5 days Fri 25-04-14 Wed 30-04-14 118 1.14 Traffic Management 618 days Tue 10-09-13 Mon 31-08-15 119 1.14.1 Prepare traffic management plan -In Phases 40 days Fri 27-09-13 Tue 12-11-13 120 1.14.2 Submission of Plan -In phases 40 days Wed 09-10-13 Sat 23-11-13 121 1.14.3 Approval of Traffic Management Plan -In phases 40 days Mon 21-10-13 Thu 05-12-13 122 1.14.4 Making New Road/Strengthning of Existing Roads 618 days Tue 10-09-13 Mon 31-08-15 123 1.15 Test Pile Installation & Reports 116 days Mon 14-10-13 Wed 26-02-14 124 1.15.1 Mobilize Rig for Test Pile 0 days Mon 14-10-13 Mon 14-10-13 125 1.15.2 Install Initial Test Pile 20 days Mon 02-12-13 Tue 24-12-13 126 1.15.3 Pile Load Test & Submission of Report 50 days Tue 31-12-13 Wed 26-02-14 127 2 Casting of Precast Elements 443 days Mon 30-09-13 Fri 27-02-15 128 2.1 Submission of design of Thrust Block & Bed for Precast I-Girder 0 days Mon 30-09-13 Mon 30-09-13 129 2.2 Approval of design of Thrust Block & Bed for Precast I-Girder 3 days Mon 30-09-13 Wed 02-10-13 130 2.3 Casting of I - Girder 250 days Mon 13-01-14 Thu 30-10-14 131 2.4 Casting of Precast Parapet 320 days Thu 20-02-14 Fri 27-02-15
BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)
Page 2 of 5
ITD CEMENTATION INDIA LTD
PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works
ID Task Name Duration Start Finish 2014 2015
A S O N D J F M A M J J A S O N D J F M A M J J A S O 132 3 Casting of 1st Girder Segment- KD-06 (13-Jan-14) 0 days Mon 13-01-14 Mon 13-01-14 133 4 Construction of Viaduct 603 days Sat 05-10-13 Tue 08-09-15 134 4.1 Preparatory Works 265 days Sat 05-10-13 Sat 09-08-14 135 4.1.1 Barricading of Area 220 days Wed 27-11-13 Sat 09-08-14 136 4.1.2 Uncharted Utility Trenching & Detection 75 days Thu 05-12-13 Sat 01-03-14 137 4.1.3 Approval for removal/relocation of uncharted utilities 75 days Mon 23-12-13 Wed 19-03-14 138 4.1.4 Removal of Uncharted utility 90 days Tue 31-12-13 Mon 14-04-14 139 4.1.5 Tree Cutting & Transplantation 75 days Fri 15-11-13 Mon 10-02-14 140 4.1.6 Dismantling of structures/obstruction 60 days Sat 05-10-13 Fri 13-12-13 141 4.2 Mainline Viaduct - Piling 321 days Mon 06-01-14 Wed 14-01-15 142 4.2.1 Piling Z2 P5 & P4 - R1 10 days Fri 18-04-14 Tue 29-04-14 143 4.2.2 Piling Z3 P3 (Start of Dwarka Station) to P5A-R1 25 days Mon 26-05-14 Mon 23-06-14 144 4.2.3 Piling Z4 CP36 to P45 -R1 30 days Fri 27-06-14 Thu 31-07-14 145 4.2.4 Piling Z5 PP35 to P21 -R1 50 days Tue 05-08-14 Wed 01-10-14 146 4.2.5 Piling Z6 PP90B to P63 - R2 80 days Mon 06-01-14 Tue 08-04-14 147 4.2.6 Piling Z7 PP51 to P 46 - R2 20 days Mon 14-04-14 Tue 06-05-14 148 4.2.7 Piling Z8 PP91 to P 97-R2 25 days Fri 09-05-14 Fri 06-06-14 149 4.2.8 Piling Z9 P13 to P 6 -R3 25 days Fri 16-05-14 Fri 13-06-14 150 4.2.9 Piling Z11 P62 to P52-R3 30 days Tue 17-06-14 Mon 21-07-14 151 4.2.10 Piling Z12 P14 to P18 (Nallah Ph-1) -R1 20 days Fri 02-05-14 Sat 24-05-14 152 4.2.11 Piling Z13 P19 to P20 (Nallah Ph-2) -R4 10 days Sat 03-01-15 Wed 14-01-15 153 4.3 Completion of 1st Working Pile - KD-05 (06-Jan-14) 0 days Mon 06-01-14 Mon 06-01-14 154 4.4 Mainline Viaduct - Pile Cap 316 days Tue 04-02-14 Fri 06-02-15 155 4.4.1 Pile Cap Z2 P5 & P4 (3rd & 4th Set) (1st & 2nd set) 10 days Wed 04-06-14 Sat 14-06-14 156 4.4.2 Pile Cap Z3 P3 (Start of Dwarka Station) to P5A (1st & 2nd set) 30 days Mon 16-06-14 Sat 19-07-14 157 4.4.3 Pile Cap Z4 & Z7- P51 to CP36 (1st & 2nd set) 55 days Wed 23-07-14 Wed 24-09-14 158 4.4.4 Pile Cap Z8 PP91 to P 97 (1st & 2nd set) 30 days Fri 26-09-14 Thu 30-10-14 159 4.4.5 Pile Cap Z6 PP90B to P 63 (1st & 2nd Set) 100 days Tue 04-02-14 Fri 30-05-14 160 4.4.6 Pile Cap Z11 P62 to P52 (3rd & 4th set) 40 days Thu 03-07-14 Mon 18-08-14 161 4.4.7 Pile Cap Z9 P13 to P 6 (3rd & 4th set) 30 days Tue 19-08-14 Mon 22-09-14 162 4.4.8 Pile Cap Z5 PP35 to P21 (3rd & 4th set) 60 days Tue 23-09-14 Mon 01-12-14 163 4.4.9 Pile Cap Z12 P14 to P18 (Nallah Ph-1) (3rd & 4th set) 25 days Tue 20-05-14 Tue 17-06-14 164 4.4.10 Pile Cap Z13 P19 to P20 (Nallah Ph-2) 15 days Wed 21-01-15 Fri 06-02-15 165 4.5 Mainline Viaduct - Pier 324 days Wed 12-02-14 Tue 24-02-15 166 4.5.1 Pier P5 & P4 (3rd & 4th Set) (1st & 2nd set) 10 days Sat 21-06-14 Wed 02-07-14 167 4.5.2 Pier P3 (Start of Dwarka Station) to P5A (1st & 2nd set) 30 days Thu 03-07-14 Wed 06-08-14 168 4.5.3 Pier P51 to CP36 (1st & 2nd set) 55 days Sat 09-08-14 Sat 11-10-14 169 4.5.4 PierPP91 to P 97 (1st & 2nd set) 30 days Tue 14-10-14 Mon 17-11-14 170 4.5.5 Pier Z6 PP90B to P 63 (1st & 2nd Set) 100 days Wed 12-02-14 Sat 07-06-14 171 4.5.6 Pier Z11 P62 to P52 (3rd & 4th set) 40 days Mon 21-07-14 Thu 04-09-14 172 4.5.7 Pier Z9 P13 to P 6 (3rd & 4th set) 30 days Fri 05-09-14 Thu 09-10-14 173 4.5.8 Pier Z5 PP35 to P21 (3rd & 4th set) 60 days Fri 10-10-14 Thu 18-12-14 174 4.5.9 Pier Z12 P14 to P18 (Nallah Ph-1) (3rd & 4th set) 25 days Fri 06-06-14 Fri 04-07-14 175 4.5.10 Pier Z13 P19 to P20 (Nallah Ph-2) 15 days Sat 07-02-15 Tue 24-02-15 176 4.6 Mainline Viaduct - Pier Cap & Fixing of Bearings 325 days Sat 22-02-14 Sat 07-03-15 177 4.6.1 Pier Cap Z2 P5 & P4 (3rd & 4th Set) (1st & 2nd set) 10 days Sat 12-07-14 Wed 23-07-14 178 4.6.2 Pier Cap Z3 P3 (Start of Dwarka Station) to P5A (1st & 2nd set) 40 days Thu 24-07-14 Mon 08-09-14 179 4.6.3 Pier Cap Z4 & Z7- P51 to CP36 (1st & 2nd set) 65 days Tue 09-09-14 Sat 22-11-14 180 4.6.4 Pier Cap Z8 PP91 to P 97 (1st & 2nd set) 40 days Mon 24-11-14 Thu 08-01-15 181 4.6.5 Pier Cap Z6 PP90B to P 63 (1st & 2nd Set) 120 days Sat 22-02-14 Fri 11-07-14 182 4.6.6 Pier Cap Z11 P62 to P52 (3rd & 4th set) 45 days Fri 01-08-14 Mon 22-09-14 183 4.6.7 Pier Cap Z9 P13 to P 6 (3rd & 4th set) 35 days Tue 23-09-14 Sat 01-11-14 184 4.6.8 Pier Cap Z5 PP35 to P21 (3rd & 4th set) 70 days Mon 03-11-14 Thu 22-01-15 185 4.6.9 Pier Cap Z12 P14 to P18 (Nallah Ph-1) (3rd & 4th set) 35 days Wed 18-06-14 Mon 28-07-14 186 4.6.10 Pier Cap Z13 P19 to P20 (Nallah Ph-2) 15 days Thu 19-02-15 Sat 07-03-15 187 4.7 Mainline Viaduct "I" Girder Erection 337 days Sat 08-03-14 Mon 06-04-15 188 4.7.1 Mobilize Erection Crane 0 days Sat 08-03-14 Sat 08-03-14 189 4.7.2 I - Girder Erection PP90 to P63 125 days Mon 10-03-14 Fri 01-08-14 190 4.7.3 I - Girder Erection by P62 to CP36 70 days Sat 20-09-14 Wed 10-12-14 191 4.7.4 I - Girder Erection PP35 to P 21 & P13 to P6 55 days Thu 11-12-14 Thu 12-02-15 192 4.7.5 I - Girder Erection P5 & P4 (2) 6 days Fri 13-02-15 Thu 19-02-15 193 4.7.6 I - Girder Erection P3 (Start of Dwarka Station) to P5A 20 days Fri 20-02-15 Sat 14-03-15 194 4.7.7 I - Girder Erection P91 to P 97 20 days Sat 02-08-14 Mon 25-08-14 195 4.7.8 I - Girder Erection P14 to P18 (Nallah Ph-1) 30 days Fri 15-08-14 Thu 18-09-14 196 4.7.9 I - Girder Erection P19 to P20 (Nallah Ph-2) 10 days Thu 26-03-15 Mon 06-04-15 197 4.8 Start of Erection of I-Girder - KD-07 (10-Mar-14) 0 days Mon 10-03-14 Mon 10-03-14
BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)
Page 3 of 5
ITD CEMENTATION INDIA LTD
PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works
ID Task Name Duration Start Finish 2014 2015
A S O N D J F M A M J J A S O N D J F M A M J J A S O 198 4.9 Mainline Viaduct In-Situ Deck Slab 373 days Wed 26-03-14 Wed 03-06-15 199 4.9.1 In-situ Deck - PP-90B to P-63 115 days Wed 26-03-14 Wed 06-08-14 200 4.9.2 In-situ Deck - P62 to CP36 100 days Wed 15-10-14 Sat 07-02-15 201 4.9.3 In-situ Deck - PP35 to P 21 & P13 to P6 80 days Mon 05-01-15 Tue 07-04-15 202 4.9.4 In-Situ Deck - P4 (End of Dwarka Stn to Pier 36 of Viaduct) 30 days Tue 10-03-15 Mon 13-04-15 203 4.9.5 In-situ Deck - P3 (Start of Dwarka Station) to P5A 35 days Tue 17-03-15 Sat 25-04-15 204 4.9.6 In-situ Deck - P91 to P 97 30 days Wed 27-08-14 Tue 30-09-14 205 4.9.7 In-situ Deck P14 to P18 (Nallah Ph-1) 60 days Wed 01-10-14 Tue 09-12-14 206 4.9.8 In-situ Deck P19 to P20 (Nallah Ph-2) 30 days Thu 30-04-15 Wed 03-06-15 207 4.10 Mainline Parapet Erection 371 days Mon 21-04-14 Fri 26-06-15 208 4.10.1 Parapet Erection - PP90B (Ch:2348) to P63 (Ch:1672) 100 days Mon 21-04-14 Thu 14-08-14 209 4.10.2 Parapet Erection - P62 (Ch:1533) to CP36 (Ch:889.8) 100 days Sat 08-11-14 Wed 04-03-15 210 4.10.3 Parapet Erection - PP35 (Ch:844) to P 21 & P13 to P6 80 days Thu 29-01-15 Fri 01-05-15 211 4.10.4 Parapet Erection- P5(Ch:95) & P4(Ch:70) 15 days Fri 03-04-15 Mon 20-04-15 212 4.10.5 Parapet Erection - P3 (Ch:-70) (Start of Dwarka Station) to P5A (Ch:-250.497) 30 days Fri 10-04-15 Thu 14-05-15 213 4.10.6 Parapet Erection - P91 (Ch:2374.41) to P 97 (Ch:2524.41) 30 days Sat 20-09-14 Fri 24-10-14 214 4.10.7 Parapet Erection (Ch:320) to P18 (Ch:420) (Nallah Ph-1) -R3 30 days Sat 25-10-14 Fri 28-11-14 215 4.10.8 Parapet Erection Z14 P19 to P20 (Nallah Ph-2) -R3 10 days Tue 16-06-15 Fri 26-06-15 216 4.11 Start of Launching of Parapets - KD-08 (21-Apr-14) 0 days Mon 21-04-14 Mon 21-04-14 217 4.12 Partial access of the viaduct(minimum 1.5 km in one stretch for 0 days Mon 23-03-15 Mon 23-03-15 218 4.13 Full Access of Mainline Viaduct and ramps, for laying of track and 0 days Fri 26-06-15 Fri 26-06-15 219 4.14 Fix Expansion Joint & Railing /Misc Works 110 days Mon 04-05-15 Tue 08-09-15 220 4.14.1 Fixing of Expansion Joint 110 days Mon 04-05-15 Tue 08-09-15 221 4.15 Ramp Construction (220m length) 428 days Thu 30-01-14 Fri 12-06-15 222 4.15.1 Excavation 120 days Thu 30-01-14 Wed 18-06-14 223 4.15.2 Raft Construction 120 days Thu 06-03-14 Wed 23-07-14 224 4.15.3 Wall construction 120 days Thu 10-04-14 Wed 27-08-14 225 4.15.4 Deck Slab Construction 230 days Thu 15-05-14 Fri 06-02-15 226 4.15.5 Parapet Erection 230 days Thu 19-06-14 Fri 13-03-15 227 4.15.6 Misc Finishing Works 220 days Tue 30-09-14 Fri 12-06-15 228 4.16 Finishing Works 428 days Mon 28-04-14 Tue 08-09-15 229 4.16.1 R.C.C crash barrier around Pier 250 days Mon 28-04-14 Thu 12-02-15 230 4.16.2 Rain Water Harvesting pit & manhole constr. 250 days Mon 02-06-14 Thu 19-03-15 231 4.16.3 MS Railing and walkways on the both sides 300 days Fri 15-08-14 Thu 30-07-15 232 4.16.4 All other Balance Works reladed to Viaduct and elevated ramp 285 days Sat 11-10-14 Tue 08-09-15 233 4.17 Completion of entire viaduct work as per the contract -KD-11 (08-Sep-15) 0 days Tue 08-09-15 Tue 08-09-15 234 5 Construction of Stations 565 days Tue 19-11-13 Tue 08-09-15 235 5.1 Dwarka Station 489 days Fri 17-01-14 Mon 10-08-15 236 5.1.1 R.C.C Frame Works 394 days Fri 17-01-14 Tue 21-04-15 237 5.1.1.1 Z1 Station Piling (Dwarka Stn) - R1 75 days Fri 17-01-14 Mon 14-04-14 238 5.1.1.2 Pile Cap & Tie Beam Network 90 days Thu 27-02-14 Wed 11-06-14 239 5.1.1.3 Column upto bottom of Track Level Beam 118 days Sat 22-03-14 Wed 06-08-14 240 5.1.1.4 Backfilling PCC & Gradeslab 90 days Sat 22-03-14 Fri 04-07-14 241 5.1.1.5 Beams & Slab at Track Level 170 days Wed 09-04-14 Thu 23-10-14 242 5.1.1.6 Beams & Slab at Platform Level 100 days Wed 26-11-14 Sat 21-03-15 243 5.1.1.7 Track Supporting Structure 90 days Tue 06-01-15 Mon 20-04-15 244 5.1.1.8 Lift shaft , escalator pit 220 days Thu 07-08-14 Mon 20-04-15 245 5.1.1.9 Stair case from Concourse Level to Platform Level 120 days Sat 05-07-14 Fri 21-11-14 246 5.1.1.10 Interconnecting structure between old and new station 120 days Wed 03-12-14 Tue 21-04-15 247 5.1.2 Ancillary Building, Architectural & Finishing Works 318 days Tue 05-08-14 Mon 10-08-15 248 5.1.2.1 Masonary works for Operational , Signalling , telecommunication room, station control 150 days Wed 27-08-14 Tue 17-02-15 249 5.1.2.2 Architectural & Finishing works for Operational , Signalling , telecommunication room, 100 days Thu 27-11-14 Mon 23-03-15 250 5.1.2.3 Masonary Works for TOM Room & flooring with reqd cutting of raceways for fixing AFC 150 days Wed 10-12-14 Tue 02-06-15 251 5.1.2.4 Architectural & Finishing of TOM Room & flooring with reqd cutting of raceways for fixing AFC 120 days Tue 17-02-15 Mon 06-07-15 252 5.1.2.5 Masonary, Architectural & Finishing works for other area at concourse level & Platform Level 140 days Sat 28-02-15 Mon 10-08-15 253 5.1.2.6 RCC/Masonary of UG Tank , pump & Generator room 140 days Tue 05-08-14 Wed 14-01-15 254 5.1.2.7 Finishing works of UG Tank , pump & Generator room 70 days Thu 15-01-15 Mon 06-04-15 255 5.1.2.8 Site Development Works 130 days Tue 10-03-15 Fri 07-08-15 256 5.1.3 KD-01 - Partial access to E & M contractor (09-Feb-15) 0 days Mon 09-02-15 Mon 09-02-15 257 5.1.4 KD-02.1 - Completion of operartional rooms i.e. signaling room 0 days Mon 23-03-15 Mon 23-03-15 258 5.1.5 KD-03.1 - Completion of TOM room & flooring with required 0 days Mon 06-07-15 Mon 06-07-15 259 5.1.6 KD-04.1 - Completion of lift shaft & escalator pit (20-Apr-15) 0 days Mon 20-04-15 Mon 20-04-15 260 5.1.7 KD-05.1 - Completion of UG Tank , pump & generator room (06-Apr-15) 0 days Mon 06-04-15 Mon 06-04-15 261 5.1.8 KD-06.1 - Track supporting structure including track bed in station 0 days Mon 20-04-15 Mon 20-04-15 262 5.2 Najafgarh Depot Station 565 days Tue 19-11-13 Tue 08-09-15
BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)
Page 4 of 5
ITD CEMENTATION INDIA LTD
PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works
ID Task Name Duration Start Finish 2014 2015
A S O N D J F M A M J J A S O N D J F M A M J J A S O 263 5.2.1 R.C.C Frame Works 389 days Wed 05-03-14 Mon 01-06-15 264 5.2.1.1 Z10- Station Piling (Najafgarh Stn.)-R3 60 days Wed 05-03-14 Tue 13-05-14 265 5.2.1.2 Pile Cap / Footing 50 days Wed 09-04-14 Thu 05-06-14 266 5.2.1.3 Column upto Concourse Level 50 days Wed 14-05-14 Thu 10-07-14 267 5.2.1.4 Stair case from Ground Floor to Concourse Level 75 days Fri 11-07-14 Mon 06-10-14 268 5.2.1.5 Beams & Slab at Concourse Level 200 days Wed 18-06-14 Thu 05-02-15 269 5.2.1.6 Stair case from Concourse Level to Platform Level 75 days Fri 06-02-15 Mon 04-05-15 270 5.2.1.7 Column upto track level 130 days Wed 23-07-14 Sat 20-12-14 271 5.2.1.8 Beams & Slab at Track Level 200 days Fri 08-08-14 Sat 28-03-15 272 5.2.1.9 Beams & Slab at Platform Level 150 days Wed 29-10-14 Tue 21-04-15 273 5.2.1.10 Track Supporting Structure 90 days Tue 17-02-15 Mon 01-06-15 274 5.2.1.11 R.C.C lift shaft, escalator pit 220 days Thu 04-09-14 Mon 18-05-15 275 5.2.2 Ancillary Buildings, Architectural & Finishing Works 310 days Wed 27-08-14 Sat 22-08-15 276 5.2.2.1 Masonary works for Operational , Signalling , telecommunication room, station control 150 days Wed 01-10-14 Tue 24-03-15 277 5.2.2.2 Architectural & Finishing works for Operational , Signalling , telecommunication room, 120 days Tue 13-01-15 Mon 01-06-15 278 5.2.2.3 Masonary Works for TOM Room & flooring with reqd cutting of raceways for fixing AFC 150 days Wed 10-12-14 Tue 02-06-15 279 5.2.2.4 Architectural & Finishing of TOM Room & flooring with reqd cutting of raceways for fixing AFC120 days Tue 24-03-15 Mon 10-08-15 280 5.2.2.5 Masonary, Architectural & Finishing works for other area at concourse level & Platform Level 150 days Sat 24-01-15 Fri 17-07-15 281 5.2.2.6 RCC/Masonary of UG Tank , pump & Generator room 140 days Wed 27-08-14 Thu 05-02-15 282 5.2.2.7 Finishing works of UG Tank , pump & Generator room 75 days Fri 06-02-15 Mon 04-05-15 283 5.2.2.8 Site Development Works 70 days Wed 03-06-15 Sat 22-08-15 284 5.2.3 KD-01 - Partial access to E & M contractor (09-Feb-15) 0 days Mon 09-02-15 Mon 09-02-15 285 5.2.4 KD-02.2 - Completion of operartional rooms i.e. signaling room 0 days Mon 01-06-15 Mon 01-06-15 286 5.2.5 KD-03.2 - Completion of TOM room & flooring with required 0 days Mon 10-08-15 Mon 10-08-15 287 5.2.6 KD-04.2 - Completion of lift shaft & escalator pit (18-May-15) 0 days Mon 18-05-15 Mon 18-05-15 288 5.2.7 KD-05.2 - Completion of UG Tank , pump & generator room (04-May-15) 0 days Mon 04-05-15 Mon 04-05-15 289 5.2.8 KD-06.2 - Track supporting structure including track bed in station 0 days Mon 01-06-15 Mon 01-06-15 290 5.2.9 Miscellaneous Works 565 days Tue 19-11-13 Tue 08-09-15 291 5.2.9.1 Finishing Works (Stone, Tile works, Flooring, etc.) 80 days Mon 08-06-15 Tue 08-09-15 292 5.2.9.2 Plumbing Works (Water Supply, Drainage Sanitary etc.) 80 days Mon 08-06-15 Tue 08-09-15 293 5.2.9.3 Fire Doors 80 days Mon 08-06-15 Tue 08-09-15 294 5.2.9.4 Misc Works & Diversion of Unchartered Utilities & Other Arch Finishing Works 560 days Tue 19-11-13 Wed 02-09-15 295 5.2.10 KD-07 - Completion of Entire Works as per the Contract (08-Sep-15) 0 days Tue 08-09-15 Tue 08-09-15