Method Statement Form: Method Statement For Excavation / Dewatering of FGD (Chimney)
Method Statement Form: Method Statement For Excavation / Dewatering of FGD (Chimney)
Activity Description:
Commencement of Activity:
13.09.2019 Duration of Activity:
3. Responsible Supervisor(s) Present At Work Place
Sump Systems
A Sump might be defined as, a pit in which water collects before being bailed or pumped
out. The pump suction will be dipped into a sump to remove the collected water.
any water will flow to it due to gravity. For construction projects water is removed from
Sump pumping is the most basic of the dewatering methods. In essence, It involves
allowing ground water to seep into the excavation, collecting it in sumps and then
pumping it away for disposal. Sumps are provided for two separate purposes, though the
To collect and discharge pumped water due to lowering of the groundwater for a shallow
excavation, also sump pumping may be required or gravity drainage to toe drains of
battered slopes.
Collected in the sumps is by means of pumping. Pumps will be strategically located along
Installation at site:
1. As mentioned in the attached plan firstly, the excavation will be started from the NGL-
will be provided to count the collapsible condition of the sandy soil. Finally, the
excavation will be done in 1:1 slope from El-222.000 to the bed level of the PCC i.e.
EL-219.925m while maintaining the offset of clear safe working space of 950 mm.
2. First of all we have to excavate a drain around the periphery of chimney raft.
south face of the plant connected through a peripheral drain of 250*250mm running
throughout the periphery of the chimney foundation with a clear offset of 200mm from
the edge of the PCC. This drain will be filled with 20 to 40mm aggregate to provide a
passage for seeping water to run through the channel and be collected in into the
collection sump.
4. This Pump will be connected to the discharge pipe connected to a suction pump
5. This procedure will continue till the completion of the chimney raft concreting.
6. While excavating the slopes care will be taken for the Absorber side with a safe
SAFETY:
ENVIRONMENT PROTECTION:
Diesels and Oils shall be restricted within drip trays to prevent contamination of the sand.
Waste Oil:
Oil Disposal units to be situated on site. waste oil to be removed as and when required by an
approved contractor.
Sound Pollution: