Project identified in 48th CBRR

Directorate: Signal (Point 10 of Para 5 of DG’s letter No. R1/5/CBRR (48th) dt. 18.07.19)

1. Project Name Study of 25KV AC immunization for S&T installations.


2. Proposed by AM/Signal
3. Need/IR requirement To avoid execution problem related to RE work.
4. Expected benefits Faster execution of RE fitness work.
5. Execution Road Map i. Identification of problem for RE fitness in
consultation with CORE.
ii. Examination of problem to work out solution.
iii. Issue of EOI for Development as required.
iv. Development of item.
v. Field trials
6. Selection of Academic and Engaging existing LED signal manufacture through EOI.
industry partners
7. Project deliverables i. Making LED signal AC immunity independent of
component failure. It will increase limit of direct
feed to signals.
ii. Increase in limit of block working length in RE
area.
8. Expected timelines i. For problem which can be resolved by RDSO in
house: 6 months.
ii. Timeline for Long tern issue will be decided after
detailed examination.
9. Estimated project cost To be worked out.
10. Proliferation road Map After product development and field trail it will be
adopted in Indian Railway specially in RE fitness work.

Prepared by

(Ajay Verma) Approved by


Exe.Director/Sig-III

(Directorate Head)
Project identified in 48th CBRR

Directorate: Signal (Point 32 of Para 5 of DG’s letter No. R1/5/CBRR (48th) dt. 18.07.19)

S.No. Project details Remarks


1. Project name Modelling and validation of interlocking for Railway
Signalling System Phase-II
2. Proposed by: RDSO or RDSO
AM/Rly. Board
3. Need/IR requirements Automation in preparation of Signal drawing.
4. Expected benefits (both A software tool shall be developed which can:
tangible, non-tangible) a. Automatically generate SIP in CAD drawing format and
ready to use.
b. Automatically generate RCC without requiring any manual
change. To keep flexibility for different requirements, the
rules shall be customizable.
c. Automatically generate the application logic for all makes
of Electronic Interlocking (as far as possible). The circuit
templates shall be as per report on ‘Standardization of
circuits for Electronic Interlocking-2019’ which is
currently under preparation. Flexibility shall be provided in
the tool to allow minor change in template circuits in case
any standard is changed at later stage.
d. Automatically generate the CAD equivalent logic circuits
for the station.
5. Execution Roadmap a. Identification of requirements for advancing the tool suite
along with suitable test cases.
b. Initial software version
c. Testing the software on several yards of Indian Railways
d. Integration of software modules
e. Stabilisation of overall tool flow, report preparation and
handing over to Zonal Railways for use.
f. Selection of Academic and Academic Partner: IIT/Kharagpur.
Industry Partners Industry Partner: Will be taken in Phase-III if need is felt.
g. Project Deliverables Tool for automatically generation of SIP in CAD drawing,
RCC, application logic for all makes of Electronic
Interlocking (as far as possible) and CAD equivalent logic
circuits for the station.
a. Expected Timelines a. Identification of requirements for advancing the tool suite
along with suitable test cases- 4 months
b. Initial software version- 14 months
c. Testing the software on several yards- 4 months
d. Integration of software- 4 months
e. Stabilisation of overall tool flow, report preparation and
and handing over to Zonal Railways for use including
conducting Seminars/hands on practice.- 4 months
f. Estimated Project Cost 49.62 lakhs
g. Proliferation Roadmap Tool shall be handed over to Zonal Railways for use
including conducting Seminars/hands on practice

Prepared by Approved by
(M.M.Waris)
Jt.Director/Sig-III (Directorate Head)
Project identified in 48th CBRR

Directorate: Signal (Point 12 of Para 5 of DG’s letter No. R1/5/CBRR (48th) dt. 18.07.19):-

(i) Project Name: TCAS Phase II Project (Indian Railway Train Control System/ IRTCS) for
having features similar to ETCS Level 2 for higher speeds
(ii) Proposed by: AM/Signal Railway Board
(iii) Need/IR  Development of TCAS to match with features of ETCS Level-2 was
Requirements: envisaged by Honorable Railway Minister on 11.07.2018.
 The scope was to incorporate the functionalities like:
(i) Interfacing with EI
(ii) Interfacing with CTC
(iii) Remote introduction of TSR.
(iv) Development of suitable interfaces by TCAS manufacturers for their
onboard equipment so that a loco can work in TCAS & ETCS Level 2
territory.
(v) ETCS Level 2 manufacturers are also required to develop the interface
of TCAS after their system is put into operation in Indian Railways.
(iv) Expected Benefits: Tangible: Improvements in train operations and capacity augmentation.
Intangible: Efficient train operations and eliminates possibility of accidents
due to human failures.
(v) Execution Road Map 1. GCM Approval.
2. Development of TCAS for ETCS Level-2
(i) Identification of differences between TCAS and ETCS Level-2.
(ii) Examination of differences.
(iii) Development of Offsite test lab almost nearing to Zero onsite test
lab.
(iv) Minimization of differences.
(v) Improvements in TCAS System.
(vi) Field trials.
(vii) Adoption with TCAS.
3. ETCS Level manufacturers develop interoperable interface with
TCAS. (Possible only after deployment of ETCS Level2 in Indian
Railways for which four reach tender in NCR, CR, ECoR and SCR
are invited by M/s Railtel).
(vi) Selection of Academic Proposed Academic Partners: IISc Bengaluru
and Industry Partners Proposed Industry Partners: TCAS developing firms, Electronic interlocking
firms, CTC firms, UNISIG firms.
(vii) Project Deliverables  Centralized feeding of Caution orders (TSR)
 Interface with EI
 Interface with CTC
 Interoperability with ETCS Level-2
(viii) Expected Timelines GCM Approval- Sept 2019, work sanction- Feb 2020, Floating of tender-
Apr-2020, Approval of the firms- Feb 2023.
(ix) Estimated Project Will be evaluated at later stage.
Cost
(x) Proliferation Road To be evolved in future.
Map

Prepared by Approved by
(G.Pawan Kumar)
Director/Sig-V (Directorate Head)

Project identified in 48th CBRR


Directorate: Signal (Point 13 of Para 5 of DG’s letter No. R1/5/CBRR (48th) dt. 18.07.19):-

SN. Project Name Remarks


i) Project Name Solution for Surge and lightening protection
for signal equipment installed at way-side.
ii) Proposed by RDSO or AM/Rly. AM/Signal/Railway Board, New Delhi
Board
iii) Need/IR requirements Indian Railway requirements.
iv) Expected Benefits (both tangible, Reliability improvement of electronic
non-tangible) equipments like electronic interlocking, axle
counter and UFSBI.
v) Execution Road Map  Study of existing products.
 Performance feedback and suggestion
from Railways.
 Study of problem, consultation with
OEM’s/Vendors, keeping in view the
international standards.
vi) Selection of Academic and IIT, Kharagpur (Eastern region is more
Industry Partners lightning prone).
vii) Project Deliverables Reliability improvement of electronic
equipments.
viii) Expected Timelines  6 months in house.
 Inviting EOI for comprehensive solution.
ix) Estimated Project Cost -
x) Proliferation Roadmap After initial trials adoption in Indian Railways.

Prepared by

(H.O.Kushwaha) Approved by
Director/Sig-VI

(Directorate Head)
Project identified in 48th CBRR

Directorate: Signal (Point 15 of Para 5 of DG’s letter No. R1/5/CBRR (48th) dt. 18.07.19)

S.No. Project details Remarks


6. Project name Development of Condition Monitoring
and Predictive Maintenance of Signalling
Gears
7. Proposed by : RDSO or AM/Rly. Board AM/Signal
8. Need/IR requirements Predictive maintenance of critical gears
e.g. Point Machine, All types of track
circuits, Power Supply, relays etc. for safe
operation of trains.
9. Expected benefits (both tangible, non- Reliability improvement and improved
tangible) train operation.
10. Execution Roadmap (a) Study of signalling gears to identify
critical parameters for monitoring.
(b) Development of interface & software
modules compatible with Data Logger
with association of vendors of Data
Logger and academic partner.
11. Selection of Academic and Industry IIT/Madras & Vendors of Data Logger
Partners
12. Project Deliverables Predictive maintenance of critical
signalling gears.
13. Expected Timelines Development of modules in phased
manner.
Time to be worked out in consultation
with academic and industry partner.
14. Estimated Project Cost To be worked out
15. Proliferation Roadmap Field trial & adoption on Indian Railways.

Prepared by

(A.K.Singh) Approved by
Director/Sig-VIII

(Directorate Head)