Professional Documents
Culture Documents
Economics PPT Submisson
Economics PPT Submisson
Efficiency
Some of these standards differ from each other, and also with respect to the
application of the terms to different building types. The important tasks for
designers are to make sure that the project will be equal or better than the
average expected efficiency level for the building type in question and to select
the most efficient from a set of alternative schemes. The first task must use
standard definitions; for the second, the consistent application of one definition
to all comparable , schemes
is the critical issue. 1 Total Floor Area, Gross Floor Area, Architectural Area The
terms Total FIDOI Area (TFA), gross floor area, and architectural area refer to a
measure of the building size in terms of flour area, as measured from
(permanent) outside finished surface to outside finished surface of the building It
includes all areas occupied by walls, columns, stairs, ducts, and shafts, whether
they can be physically occupied by people or not. AIA document Dl01 specifies
how different parts of buildings should he wanted tn the TFA or architectural area
for . ' the purpose of estimating overall size and, from that, ' : 3 expected cost. It
distinguishes regular floor space from aim of the building that are tactfully
enclosed, or are ' not complete floors.
Typical floors, mechanical spaces , basements, subbasements, balconies in inside
spaces, bulkheads and penthouse areas, enclosed entrances ,, duct spaces,
interstitial areas higher than 6 feet count in full.
h regard to the project budget The design-build approach remedies this by 05mg
8 commanding dimmer team (design-build team) that gives the client a final
contract at the outset The team then proceeds with the planning and
construction work as in the fast-track approach. Both approaches require that the
contractor be brought in early in the planning process, both work best with
standardized construction methods or building systems, and both leave the client
with some uncertainty as to the final product at the time when the crucial
decision to proceed with the communion must be made. They require that the
owner have a higher degree of trust and confidence in the architect and the
contractor than would be necessary if all the work were carefully specified and
documented in working drawings prior to signing of the contract. In times of high
interest and high inflation rates, the initial cost savings due to the reduction in
delivery time may be well worth the potential drawbacks.
SUMMARY OBSERVATIONS
The building delivery process, as described by its sequence of steps, activities, and
the made by the various participants, can influence not only the economies of the
building but also the economic objectives of the parties involved and thus the
analysis techniques that should be used to investigate the appropriateness of
design solutions. in each particular mutation, then, the probable process and
understood. A few main observations can be made. t program filling economic
Viability should be cm again; feasibility analysis should accompany the entire pro.
at each m- . 352; time that the WW "“131 {even to a previous the: because its
assumptions have prayed to inadequate. or because assumption
it is also likely to cost the Irresponsible party credibility and reputation. . Care
should be taken, therefore. to arrange the process in as straightforward a manner
as possible, en. surfing that the analysis at each step will result in reliable
assumptions to serve as the basis for the next steps, avoiding the need to go back
to a previous stage. in other words, the delivery process must be considered as
part of the design problem ;tt must itself be carefully planned.
time and money. it is also likely to cost the Irresponsible party credibility and
reputation. . Care should be taken, therefore. to arrange the process in as
straightforward a manner as possible, surfing that the analysis at each step will
result in reliable assumptions to serve as the basis for the next steps, avoiding the
need to go back to a previous stage. in other words, the delivery process_ must
be considered as part of the design problem ; must itself be carefully planned
this. Both have complex. 193:8th review end 1mm! processes with severe
budget ones :,
We: Whit for 31?; maze; CM»? mm urban iv» gay. $1.4, 7mm92:3: .5 :55: 33mg:
aw; MW 7. , t performed in:
particular conditions. For example l @MGQQQ,W8DIS fort the remain»? m0f 33%
governs only, 90 that construction can begin ’ initial cost (perhaps through
legislative action), with the while other, parts still are being designed and smith. . ’
, Operation and maintenance of the buildings . This results in an overall reduction
of the delivery time ' coming an entirely different budget. This arrange-. The
drawback is that no final ' trade-offs between the initial ,7 Cost figure be
established when construction starts, long-term
90 that construction can begin ’ initial cost (perhaps through legislative action),
with the while other, parts still are being designed and smith. . ’,first Operation
and maintainance of the buildings . This results in an overall reduction of the
delivery time ' 'coming an entirely different budget. This arranged the incentive
for planners to planning and construction activity. The drawback is that no final '
trade-offs between the initial ,7 Cost figure can be established when construction
starts, long-term
INTRODUCTION
lower NGR will have the lower TF the lower initial cost. A “(1&me Building
elliciency as measured by the Net Ratio or m inverse .the Groom-Net Ratio.
refers to the amount of space that must be built in the building as a whole (TFA)
in order to provide the amount of space (net usable area or net usable area) for
which the owner will receive rental income, or which actually produces the use
value of the building, The difference between the TFA and the NLA is the “non
rentable” area or service area. The cost of the building, and the relationship
between cost and rental income, will be ' favorable if the NGR is high (close to 1);
it will be the more unfavorable the more the NGR drops below 1. Because this
relationship is almost always quite direct and close, the NGR can be used as a
reliable perform ance indicator during the design process. The designer will not
have to calculate the initial cost for each new design concept; it is sufficient to
check the NGR to see if it is better or worse than preceding solutions. If the NGR
does not improve, it is not worthwhile to further pursue the scheme. Standard
expectation levels of the NGR are further used at the feasibility analysis and worn:
stage to estimate the TFA, given the s
There are a few (almost obvious) design rules of thumb that can be applied to
building efficiency and design decisions One such rule is that because circulation
W (hallways. corridors) are responsible for a significant fraction of non rentable
space in building, spammed by corridor should be as deep
Some of these standards differ from each other, and also with respect to the
application of the terms to different building types. The important tasks for
designers are to make sure that the project will be equal or better than the
average expected efficiency level for the building type in question and to select
the most efficient from a set of alternative schemes. The first task must use
standard definitions; for the second, the consistent application of one definition
to all comparable schemes is the critical issue
less net area per floor, Clearly does not makes , solution more efficient. " A
fallacy sometimes encountered in connection with the effort to make a design
scheme more as. based on the correct, observation that efficiency is related to
the ratio of the depth of served spaces Mm; a hotel room—to the width of the
corridor serving than. For example, in the process of modifying solution A in figure
A l-3, an alternative proposal may be solution B. Checking the NGR, it might look
as though B is 1hr: better scheme because its NGR is higher. However, rite higher
NGR has been achieved