Professional Documents
Culture Documents
Tolerance Manual: AND Concrete
Tolerance Manual: AND Concrete
PRECAST/PRESTRESSED
CONCRETE INSTITUTE
TOLERANCES
FOR PRECAST AND PRESTRESSED CONCRETE
CONSTRUCTION
MNL-135-00
prepared by
6
Tolerances more restrictive than those discussed determine the most economical approach to han¬
in this document should be brought to the attention dling the project tolerance requirements.
of the architect/engineer to ascertain that they are
compatible and that the proposed restrictions can be Legal
met. For example, a requirement which states that
"no bowing, warping, or movement is permitted" is To avoid encroaching on property lines and estab¬
not practical or possible to achieve. lish a tolerance standard against which the work can
be compared in the event of a dispute.
Visual It is very important to agree on the project toler¬
ances in writing, particularly with special tolerances
The variations in the finished product should be or in situations with critical visual aesthetics. Similarly,
controllable and result in an acceptable appearance. it is equally important to agree in advance how and
Tolerances related to visual effects or aesthetics may when these tolerances will be verified (with due con¬
be significantly more stringent than those required for sideration for measurement methods, measurement
structural or functional reasons. Tolerances which locations, number of points to measure, support con¬
are critical to project aesthetics should be indicated ditions, thermal conditions, and time of measure¬
as such by the Architect/Engineer. ment).
Economics Contractual
To ensure a reliable and efficient rate of production To establish a known acceptability range and as¬
and erection by having a known degree of accuracy sign responsibility for developing, achieving, and
in the dimensions of precast concrete products. The maintaining mutually agreed tolerances for the proj¬
cost of working to tighter than standard product toler¬ ect. The producer's quality control staff should under¬
ances should be evaluated for cumulative cost effects stand what the producer's contractual obligations are
at the project level. That is, one should evaluate both regarding project tolerances. The actual project tol¬
the cost increases and cost savings for member fab¬ erances contractually agreed to may be different from
rication, interfacing with subsystems and erection to the charted values given here.
7
Fig. 12.1.1 Beam Erection Tolerances
Bldg. grid
datum
c c
A/~
Horizontal
primary
~ÿü control
rr surface
(at support)
4
Vertical primary
control surface"
n
Ledge
both sides Precast concrete
(N/A at inverted beam
tee beam) at inverted
ai
tee beam Support element
A- -V
Centerline of
steel support
Precast element to: precast element, cast-in-place concrete, masonry, or structural steel
96
12.1 Beam Erection Tolerances
The primary control surfaces are usually as shown, although this needs to be confirmed on a
job-by-job basis.
e = Joint width:
Architectural exposed joints ±Vi in. [±6 mm]
Hidden joints ±3A in. [±19 mm]
Exposed structural joint not visually critical ±Vz in. [13 mm]
Note: When bearing pads are used at unarmored edges they should be set back a minimum of Vfe
in. [13 mm] from the face of the support or at least the chamfered dimension at chamfered edges.
* For precast elements on a steel frame, this tolerance takes precedence over tolerance on dimen¬
sion "a".
* Or member top elevation where member is part of a frame without bearing ledges.
* This is a setting tolerance and should not be confused with structural performance requirements
set by the architect/engineer. The nominal bearing dimensions and the allowable variations in the
bearing length and width should be specified by the engineer and shown on the erection drawings.
97
Fig. 12.2.1 Floor and Roof Member Erection Tolerances
BIdg. grid
dalum
BIdg. grid -(J)
dalum
(£ o1 steel support
Primary control surlace
lor carpet direct
of steel support
u
Ho owcore Double tee
Support Support
member member —
Primary control surface Primary control surface
To allow for for topped deck w/ To allow for for pretopped tee
-3/«" tolerance exposed underside -3/<" tolerance
[-19 mm]
Bearing pad by design
[-19 mm]
-I V-T 4 Bearing pad by design
[19mm) Holdback as req'd [19mm] Holdback as req'd
-
—| BIdg. elevation datum |
Hollowcore elevation Double tee elevation
Precast element to: precast, cast-in-place concrete, masonry or structural steel support
98
12.2 Floor and Roof Member Erection Tolerances
The primary control surfaces are usually as shown . A majority of the time there is no designated
vertical primary control surface, and in some scenarios there are no primary control surfaces at all.
This needs to be determined on a job-by-job basis.
= Joint width:
0 to 40 ft. member ±1/2 in. [±13 mm]
41 to 60 ft. member ±3A in. [±19 mm]
.........
61 ft. plus member ±1 in. [±25 mm]
e = Differential top elevation as erected {for units of same design and length):
Field topped % in. [19 mm]
Pretopped tees at driving lanes/carpet direct hollow-core 'A in. [6 mm]
Untopped roof1' % in. [19 mm]
Note: When bearing pads are used at unarmored edges they should be set back a minimum of 1/2
in. [ 13 mm] from the face of the support or at least the chamfered dimension at chamfered edges.
* For precast concrete erected on a steel frame building, this tolerance takes precedence over toler¬
ance on dimension "a".
1 1t may be necessary to feather the edges to ±% in. [±6 mm] to properly apply some roof mem¬
branes.
* This is a setting tolerance and should not be confused with structural performance requirements
set by the architect/ engineer. The nominal bearing dimensions and the allowable variations in the
bearing length and width should be specified by the engineer and shown on the erection drawings.
§
Untopped installations will require a larger tolerance.
99
Fig. 12.3.1 Column Erection Tolerances
d d
o Bldg. grid
datum
-4fO
Plan view
Splice
Vertical primary
control surface
Horizontal primary
control surface
(at first corbel)
Bldg. elevation
datum
Bldg. grid
Bldg. elevation
datum
datum
Elevation Elevation
100
12.3 Column Erection Tolerances
The primary control surfaces are usually as shown, although this needs to be confirmed on a
job-by-job basis.
101
Fig. 12.4.1 Structural Wall Panel Erection Tolerances
Vertical primary
control surface
Horizontal
primary
control
surface
g-*" *
fJ ,_ÿl
t
— -h
Precast
concrete
panel
E
"e
CO
Cast-in-place .
2
o
T. foundation or
precast
°
b
BIdg.
b
I
concrete Elevation
— Cast-in-place or support ~~
Datum"
precast concrete
IKJB
n=TT@n=Mi=m-
— Nominal joint width
BIdg. grid
j-«— h
datum
Vertical primary
control surface
Horizontal
primary
conlrol
V
surface
Support member
'10
é=í-
Steel BIdg. grid
structure datum
102
12.4 Structural Wall Panel Erection Tolerances
The primary control surfaces are usually as shown, although this needs to be confirmed on a
job-by-job basis.
a = Plan location from building grid datum ±'/z in. [±13 mm]
* For precast buildings in excess of 100 ft. tall, tolerances "a" and "d" can increase at the rate of Va
in. [3 mm] per story to a maximum of 2 in. [50 mm].
t Refer to Article 8 for description of bowing tolerance.
103
Fig. 12.5.1 Architectural Walls/Spandrel Erection Tolerances
BIdg. grid
datum Horizontal primary
control surface
Vertical primary
control surface
4 of steel BIdg.
elevation
support
_ Support datum
member
BIdg. grid
datum Horizontal primary '10
control surface
Vertical primary
control surface <> <>
BIdg.
i
of steel elevation
support _ Support datum
member Ar- At-
104
12.5 Architectural Walls/Spandrel Erection Tolerances
.................
The primary control surfaces are usually as shown, although this needs to be confirmed on a
job-by-job basis.
a = Plan location from building grid datum* ±1/2 in. [±13 mm]
a-i = Plan location from centerline of steel support ±1/2 in. [±13 mm]
* For precast buildings in excess of 100 ft. tall, tolerances "a" and "d" can increase at the rate of Va
in. [3 mm] per story to a maximum of 2 in. [50 mm],
t For precast elements erected on a steel frame, this tolerance takes precedence over tolerance on
dimension "a".
105
Fig. 12.6.1 Single and Double Stadium Riser Erection Tolerances
Riser unit
Theoretical
(£of support
Bldg. grid or
datum (typ)
s
,_J.
i
h Vertical primary
control surface
To allow for
-1" (-25 mm} Plan view
tolerance
I-
(25 mm) — Holdback as required
Shims per design
Horizontal primary
control surface
Bldg. grid or
datum (typ) Elevation view
Horizontal primary
control surface e
Vertical primary
ITU-T! g°n
control surface
t~T
ZJ
Riser cross section
106
12.6 Stadium Riser Erection Tolerances
The primary control surfaces are usually as shown, although this is something that needs to
be confirmed with the contractor on job-by-job basis.
a = Plan location from building grid line datum ±1 in. [±25 mm]
h = Joint width (Joint width needs to be % in. [6 mm) minimum in either case)
...........................
............
90° angle ±1/2 in. [±13 mm]
Joint width at skewed ends ±5/e in. [±16 mm]
j = Differential camber (at mid-span as erected) between adjacent members of the same de¬
sign ±3/i6 in. [±5 mm] per 10 ft. [3 m] of member length.
k = Differential sweep (at mid-span as erected) between adjacent members of the same de¬
sign ±3/i6 in. [±5 mm] per 10ft. [3 m] of member length.
Note: Local building codes may require more restrictive riser height tolerances which could also
affect product tolerance.
107
Fig. 12.8.1 Stair Unit Erection Tolerance
Plan view
Building grid
or datum (typ)
Intermediate landing
Line of topping
pan (if applicable)
Elevation view
110
12.8 Stair Unit Erection Tolerance
The primary control surface for stair units is the top of landing at floor levels. Tolerances listed
below are the same whether landings are monolithic or separate pieces.
a = Plan location from building grid line datum ±Vi in. [±13mm]
Note: Local building codes may require more restrictive riser height tolerance which could also af¬
fect product tolerance.
* At stair units that have pre-topped precast landings, the maximum jog between stair units as well
as from stair unit to finish floor can not exceed V* in. However, units which have landings that are
topped have more leeway. This needs to be discussed and agreed upon with the general contrac¬
tor.
111