1.

Preparation of Anti Termite Solution:

The entire employee shall be provided with complete PPE

The entire employee shall attend special induction training to understand with all associated hazards
with the work

All the workers shall provide the adequate tools and equipment to carry out the job safely

Material / suppliers shall be obtain approved

Emergency Contact numbers shall be displayed at site.

Eye wash facility shall be available in case of accidental splash of chemicals

Standby personnel shall be available to control and monitor the activity

2. Application of Anti termite to the prepared area

Manufactures /instructions and procedures including dilution and shall be strictly followed during
application

Liaisons with other contractors and personnel nearby area

Approved Method of statement with Permit