BILL OF QUANTITY

Construction of Single Detached Residential Unit


Pleasantville Subd. Sariaya, Quezon

WORK DESCRIPTION UNIT QUANTITY UNIT COST COST

I. STRUCTURAL CONCRETE
& MASONRY WORKS

A. CONCRETE WORKS
40 KGS Portand Cement BAGS 297 230 68,310.00
Gravel CM 32 600 19,200.00
S-1 Sand CM 18 700 12,600.00
SUB TOTAL Php100,110.00

B. MASONRY & PLASTERING WORKS


150mm Thk CHB EA 1183 12 14,196.00
100mm Thk. CHB EA 663 10 6,630.00
Portland Cement BAGS 220 230 50,600.00
Sand CM 25 700 17,500.00
SUB TOTAL Php74,730.00

C. REBAR WORKS
16mm dia. X 6m RSB EA 0 0 0.00
12mm dia. X 6m RSB EA 62 235 14,570.00
10mm dia. X 6m RSB EA 120 167 20,040.00
09mm dia. X 6m RSB EA 165 120 19,800.00
#16 Tie Wire roll 1 2200 2,200.00
SUB TOTAL Php56,610.00

D. FORMWORKS
4 x 8 x 1/4" Thk ord plywd EA 20 310 6,200.00
4 x 8 x 1/2" Thk ord plywd EA 0 0 0.00
2x4 Form Lumber BF 533 25 13,325.00
2x3 Form Lumber BF 240 25 6,000.00
2x2 Form Lumber BF 0 0 0.00
SUB TOTAL Php25,525.00

MAT'LS. Php256,975.00
LABOR Php102,790.00
TOTAL Php359,765.00

II. LUMBER FRAMEWORKS


A. CEILING,CABINET FRAMES & CLOSET
4 x 8 x 1/4" Thk mar. plywd EA 30 310 9,300.00
4 x 8 x3/4" Thk mar. plywd EA 6 750 4,500.00
2x2 KD Lumber BF 270 45 12,150.00
2x4 KD Lumber BF 18 45 810.00
Asstd. Wood Mouldings LS 1 5000 5,000.00
Prefab Cabinet & Closet cover & hardwares LS 1 7500 7,500.00
MATLS. Php31,760.00
LABOR Php12,704.00
TOTAL Php44,464.00

III. ROOFING WORKS


L -2 x 2 x 1/4 Top Chord ea 12 640 7,680.00

Page 1 BOQ
L -2 x 2 x 1/4 Bottom Chord ea 8 640 5,120.00
L -1 x 1 x 4.5 Strut ea 12 410 4,920.00
1.2 x 2 x 3 C Purlin ea 32 730 23,360.00
8 x 16" Ridge Roll ea 4 350 1,400.00
8 x 16" pre painted gutter ea 8 330 2,640.00
8 x 16" Valley Gutter ea 3 800 2,400.00
8 x 16" S/S Gutter ea 0 0 0.00
Ga 16 Pre Painted Long Span Roof sm 105 250 26,250.00
MATLS. 73,770.00
LABOR 29,508.00

IV. PAINTING WORKS


Acrylic Latex Semi Gloss can 4 3050 12,200.00
Acrylic Latex Gloss can 2 3050 6,100.00
Flat Wall Enamel can 1 3200 3,200.00
Misc. LS 1 1200 1,200.00
MATLS. Php22,700.00
LABOR Php11,350.00

V. MILLWORKS
Panelled main door SET 1 4200 4,200.00
Alum Steel Sliding Door SF 0 0 0.00
Panelled door SET 2 2150 4,300.00
PVC Door SET 2 2250 4,500.00
Misc Hardware LS 1 3000 3,000.00
MATLS. Php11,800.00
LABOR Php4,720.00
VI. PENESTRATIONS

Aluminum sliding & fixed window w/ 6mm thk. temp.


glass SM 15 2850 Php42,750.00

VII. TILEWORKS

60 cm x 60 cm Flr. Tiles ea 32 250 8,000.00


30 cm x 30 cm Flr. Tiles ea 360 32 11,520.00
30 cm x 30 cm Wall Tiles ea 192 32 6,144.00
.60 x 2.40 granite counter top ea 1 5180 5,180.00
MATLS. Php30,844.00
LABOR Php12,337.60
VIII. PLUMBING FIXTURE

SANIWARE WATER CLOSET W/ LAVATORY &


HARDWARE SET 2 4500 9,000.00
SHOWER SET SET 2 2500 5,000.00
KITCHEN SINK SET 1 3750 3,750.00
MISC. HARDWARWE LS 1 2500 2,500.00
MATLS. Php20,250.00
LABOR Php8,100.00

X.ELECTRICAL WORKS LS 1 25000 Php25,000.00

XI. PLUMBING WORKS LS 1 8000 Php8,000.00

Page 2 BOQ
EST. MATERIAL COST Php427,849.00
EST. LABOR COST Php171,140

EST. TOTAL COST Php674,738.60

Prepared By:

EDWIN E. BALOTE
REG. CIVIL ENGR.
PRC REG. 0055726 - 09/26/2017
PTR No. 1582989 - 03/24/2014

Page 3 BOQ