Bill of Quantity: Work Description Unit Quantity Unit Cost Cost I. Structural Concrete & Masonry Works
Bill of Quantity: Work Description Unit Quantity Unit Cost Cost I. Structural Concrete & Masonry Works
I. STRUCTURAL CONCRETE
& MASONRY WORKS
A. CONCRETE WORKS
40 KGS Portand Cement BAGS 297 230 68,310.00
Gravel CM 32 600 19,200.00
S-1 Sand CM 18 700 12,600.00
SUB TOTAL Php100,110.00
C. REBAR WORKS
16mm dia. X 6m RSB EA 0 0 0.00
12mm dia. X 6m RSB EA 62 235 14,570.00
10mm dia. X 6m RSB EA 120 167 20,040.00
09mm dia. X 6m RSB EA 165 120 19,800.00
#16 Tie Wire roll 1 2200 2,200.00
SUB TOTAL Php56,610.00
D. FORMWORKS
4 x 8 x 1/4" Thk ord plywd EA 20 310 6,200.00
4 x 8 x 1/2" Thk ord plywd EA 0 0 0.00
2x4 Form Lumber BF 533 25 13,325.00
2x3 Form Lumber BF 240 25 6,000.00
2x2 Form Lumber BF 0 0 0.00
SUB TOTAL Php25,525.00
MAT'LS. Php256,975.00
LABOR Php102,790.00
TOTAL Php359,765.00
Page 1 BOQ
L -2 x 2 x 1/4 Bottom Chord ea 8 640 5,120.00
L -1 x 1 x 4.5 Strut ea 12 410 4,920.00
1.2 x 2 x 3 C Purlin ea 32 730 23,360.00
8 x 16" Ridge Roll ea 4 350 1,400.00
8 x 16" pre painted gutter ea 8 330 2,640.00
8 x 16" Valley Gutter ea 3 800 2,400.00
8 x 16" S/S Gutter ea 0 0 0.00
Ga 16 Pre Painted Long Span Roof sm 105 250 26,250.00
MATLS. 73,770.00
LABOR 29,508.00
V. MILLWORKS
Panelled main door SET 1 4200 4,200.00
Alum Steel Sliding Door SF 0 0 0.00
Panelled door SET 2 2150 4,300.00
PVC Door SET 2 2250 4,500.00
Misc Hardware LS 1 3000 3,000.00
MATLS. Php11,800.00
LABOR Php4,720.00
VI. PENESTRATIONS
VII. TILEWORKS
Page 2 BOQ
EST. MATERIAL COST Php427,849.00
EST. LABOR COST Php171,140
Prepared By:
EDWIN E. BALOTE
REG. CIVIL ENGR.
PRC REG. 0055726 - 09/26/2017
PTR No. 1582989 - 03/24/2014