2019 09 29 List of Critical Issues

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

SL Location/Issues Notes/Challenges

Internal
Related to ASE
3 No work performance at 22URA since Verbally ASE instructed not to
28-July-2019 proceed further execution work at
22URA until further notice

4 No work performance at 22URA since


29-Aug-2019 due to additional
Agreement 2 (AA2) for additional job
pertaining concrete bedding work

5 Working Drawing of Pump Station According to thematic plan Quarter3


20URS and contract agreement, pump
station foundation work will start on
11-Aug-2019. However, still yet to
receive working drawing from ASE
office.
Action Remarks
Internal
elated to ASE
Paharpur-MIL JV team issued a letter ASE is still discussing with BAEC
to resolve this on 31-July-2019 and expect positive resolution in
the nearest future (Ref 007-
76/18911, Dated: 27-Aug-2019)

For issuing additional agreement Waiting for ASE feedback.


4nos letter has been generated from Yet to receive from ASE office,
Paharpur-MIL JV dated 26-Feb-2019,
31-Mar-2019, 04-Apr-2019 and 28-
Apr-2019

Paharpur-MIL JV already sent a letter Letter has issued for 20URS


to ASE office to provide working working documents
drawing. Paharpur-MIL
Paharpur-MIL JV/ASE/L2900/0046, JV/ASE/L2900/0075
Date: 24-Jun-2019 Date: 24-Jul-2019