Practitioner Exam Questions

® 8
PRINCE2 Practitioner Resource Book

Syllabus Area Question Number Part 2 Marks


Change Theme 9 C 4

The project is now in Stage 4. The MD has decided that the seats should be painted the same
colour as the ride steelwork (green). Work has already started painting the seats red and
whilst this can be achieved within the timeframes specified there will be an additional cost of
£25,000. There is £300,000 left in the Change Budget. The Change Authority specified in the
Configuration Management Strategy is the Project Board. This issue will be handled formally.

Column 1 contains a number of statements that should be included within the Issue Report. Select
from Column 2 the appropriate heading for each statement. Each option in column 2 may be used
once, more than once or not at all.
Column 1 Column 2
1 The Project Board have approved the request and A Issue description
transferred the funds into the project budget.
B Impact analysis
2 Changing the colour of the seats will require the work
already started to be scrapped. C Recommendation
3 As work has started the Project Manager believes that the
D Severity
best option will be to continue with the original colour
scheme. E Decision
4 The cost of this change is outside the authority level of the
Project Manager and must be escalated.

Question Part

9 C A B C D E

1
2
3
4

© 2009 ILX Group plc 127