INSPECTION TEST RECORD (ITR) - A

RISER ST05-A
Project No.
Project Title
Facilities
INFORMATION
Area No Ref Drawing
System Inspection Date
Sub System Location

INSPECTION / TEST OK N/A P/L No.


1 Riser is fabricated according to the AFC drawing
2 Flanges used are as per specification.
3 All welded joints and NDT have been completed.
4 Bolts and nuts at riser clamp adequately tightened, correct length and
coating as per specification
5 Riser coatings are as per specification
6 Riser clamp secure and installed at correct elevation as per drawings.
7 Riser dimensions are as per drawings
8 Bend radius are as per drawings.
9 Coating at riser clamps are as per specification.
10 Hydrotest and Flushing completed
11 Draying and internal cleaning completed
12 Gauging Pig have been performed
COMMENT(S) AND ADDITIONAL INFORMATION

COMPLETED BY VERIFIED BY ACCEPTED BY


Designation
Company
Name
Signature