The document outlines the design of a grid floor slab with dimensions of 8m x 10m and ribs spaced at 2m. It involves 3 steps:
1) Adopting a slab thickness of 100mm and rib depth of 400mm with a width of 200mm and overall depth of 600mm
2) Calculating loads such as weight of slab, beams, finish, and live load totaling to 508.8 kN
3) Determining bending moments Mx of 72 kNm and My of 46 kNm in the x and y directions respectively at the center of the grid for a 2m width.
The document outlines the design of a grid floor slab with dimensions of 8m x 10m and ribs spaced at 2m. It involves 3 steps:
1) Adopting a slab thickness of 100mm and rib depth of 400mm with a width of 200mm and overall depth of 600mm
2) Calculating loads such as weight of slab, beams, finish, and live load totaling to 508.8 kN
3) Determining bending moments Mx of 72 kNm and My of 46 kNm in the x and y directions respectively at the center of the grid for a 2m width.
The document outlines the design of a grid floor slab with dimensions of 8m x 10m and ribs spaced at 2m. It involves 3 steps:
1) Adopting a slab thickness of 100mm and rib depth of 400mm with a width of 200mm and overall depth of 600mm
2) Calculating loads such as weight of slab, beams, finish, and live load totaling to 508.8 kN
3) Determining bending moments Mx of 72 kNm and My of 46 kNm in the x and y directions respectively at the center of the grid for a 2m width.
The document outlines the design of a grid floor slab with dimensions of 8m x 10m and ribs spaced at 2m. It involves 3 steps:
1) Adopting a slab thickness of 100mm and rib depth of 400mm with a width of 200mm and overall depth of 600mm
2) Calculating loads such as weight of slab, beams, finish, and live load totaling to 508.8 kN
3) Determining bending moments Mx of 72 kNm and My of 46 kNm in the x and y directions respectively at the center of the grid for a 2m width.
Spacing of ribs= 2 m c/c M25 grade concrete Fe 415 HYSD bars STEP1: DIMENSIONS OF SLAB AND BEAMS Adopt thickness of slab= 100 mm Depth of ribs= Span/20 = 8000/20 = 400 mm Width of rib= 200 mm Adopt overall depth of ribs= 600 mm STEP2: LOADS Weight of slab= 0.1×24= 2.4 kN/m2 Total weight of slab= 2.4×8×10= 192 kN Weight of the ribs= 0.2×0.5×24= 2.4 kN/m Total weight of beams (x-direction)= 4×2.4×8 = 76.8 kN Total weight of beams (y-direction)= 3×2.4×10 = 72 kN Total weight of floor finish= 0.6×8×10= 48 kN Total live load= 1.5×8×10= 120 kN Total dead and live load= 508.8 kN Load per m2= 508.8/8*10 = 6.36 kN/m2 STEP 3: MOMENTS q1= q ( by4/(ax4+by4)) = 6.36 (104/84+104) = 4.5 kN/m2 q2= q ( ax4/(ax4+by4)) = 6.36 (84/84+104) = 1.84 kN/m2 MOMENTS IN X AND Y DIRECTIONS AT CENTRE OF GRID FOR 2 m WIDTH Mx= q1b1a2/8 = 4.5×2×82/8 = 72 kNm My= q2b2a1/8 = 1.84×2×102/8 = 46 kNm Qx = (4.5×2×8)/2 = 36 kN Qy = (1.84×2×10)/2 = 18.4 kN