THERMAL DECOMPOSITION PLANT (TDP)

QUESTIONNAIRE

Fields with values not known at the moment to be left empty

Date 16th-Sep-2019

1. Customer General Information


PT Wika Bitumen,
1.1 Customer Name (company, location, contacts) Jakarta, Indonesia
Mr Ari Gunadi
(+62811971677) /
1.2 Customer Project Manager information (contacts) Mr Teguh Pribadi
(+6281325661350)
Plant Capacity
100,000 TPY.
Short description of the site of TDP intended installation.
1.3 Climatic conditions
Climatic conditions, geographical location & other, see
Attached
Refer to Vendor
1.4 Dimensions, area of the required plant model in square meters recommendation,
no limitation.
#) Electric Power:
PLN (local source)
approx. 30MW &
EDG (emergency
Networks at the site: diesel generator)
- electric power approx. 6MW
1.5
- water supply #) Water Supply:
- sewerage Deep Well & Sea
Water.
#) Sewerage: In-
house Water
Treatment Plant.
2. Intended use of Thermal Decomposition Plant
2.1 Check all that
Output/Product
apply
Asphalt PEN 45/55
Describe the product expected from the process: (with Blending
System)
Natural gas NA
Product similar to crude oil Diesel, MFO

Diesel/gasoline mix/electricity*
* subject to provide an additional equipment
Other (specify)

Describe state of the final product once it comes out of the Plant:

Yes

It should be ready to use by a consumer and needs no further refining


No
Product needs further refining by a third party
Check all that
Scope of the order
apply
2.2 Turn-key plant construction EPC & OM
TDP plant + optional equipment: power generator, separation column /mini refinery
plant
3. Feedstock/waste characteristics

Feedstock/waste Value

From Dryer System


Source of feedstock/waste (Waste type: Solid
Waste)

Volume and generation rates of feedstock/waste 128 TPH


3.1

Feedstock/waste content (main fraction), type (solid, liquid, pasty, sludge), size Dusty

Hydrocarbon
Chemical Composition (hydrocarbon, water, solid residues) Content <2%
Generation of feedstock/waste (tons per day, tons per year)

Return back to
What is the method of waste handling at present nature
4. Process design

4.1 Annual operation: days per year, days per month 300 days per year

4.2 Location: building, open air, construction required Inside plant

5. Additional Information
5.1 Laboratory testing data of feedstock/waste: amounts of hydrocarbons, water, solid residue and other
tests.

Signature/ / Print Full Name