Professional Documents
Culture Documents
Flat Plate
Flat Plate
2 Reinf.
Conforming RC Design Floor Numbers Nof Area (m ) Concrete 35 MPa (m3) Formwork (m2) PT (kg)
fy = 400 MPa (kg)
CarPark Level 6 - 14 9 1,416 365 2,155 50,856 0
Low Office Level 16 - 29 14 1,892 446 2,804 65,395 0
High Office Level 31- 44 14 1,892 450 2,823 65,900 0
Apartment Low Level 48 - 57 10 1,791 452 2,778 67,604 0
Apartment High Level 59 - 73 15 1,791 452 2,778 67,604 0
Total for RC Design 110,491 27,127 167,640 3,985,928 0
Cost IDR IDR 29,839,285,513 IDR 37,718,939,898 IDR 79,718,552,492 IDR 0
Cost USD USD 2,057,882 USD 2,601,306 USD 5,497,831 USD 0
FLAT PLATE
Reinf.
Prelim NEW Floor Numbers Nof Area (m2) Concrete 35 MPa (m3) Formwork (m2) PT (kg)
fy = 400 MPa (kg)
CarPark Level 6 - 14 9 1,415 365 1,492 23,695 8,351
Low Office Level 16 - 29 14 1,891 406 1,936 16,257 9,265
High Office Level 31- 44 14 1,891 406 1,936 16,257 9,265
Apartment Low Level 48 - 57 10 1,791 435 1,851 17,397 8,775
Apartment High Level 59 - 73 15 1,791 435 1,851 17,397 8,775
Total new Design 62 110,454 25,534 113,924 1,103,367 553,962
Cost IDR IDR 28,087,047,638 IDR 25,632,957,521 IDR 22,067,347,709 IDR 32,129,775,341
Cost USD USD 1,937,038 USD 1,767,790 USD 1,521,886 USD 2,215,847
CIPUTRA WORLD 1 Tower D Concrete Formwork Reinf. PT TOTAL (USD) TOTAL (IDR)
Conforming RC Design USD 2,057,881.76 USD 2,601,306.20 USD 5,497,831.21 USD 0.00 USD 10,157,019.17 IDR 147,276,777,903
Prelim NEW USD 1,937,038 USD 1,767,790 USD 1,521,886 USD 2,215,847 USD 7,442,560.57 IDR 107,917,128,209
Option 2 Estimated Potential Cost Saving Due to Utracon’s Alternative PT Design (USD) USD 2,714,458.60 IDR 39,359,649,694.10
Option 2 Estimated Potential Cost Saving Due to Utracon’s Alternative PT Design (%) 27% 27%
Unit Cost
Concrete Formwork Rebar PT 1 USD IDR 14,500