Camp Inspection Report

Inspected by: V.Gopala Krishna Reddy, (Safety Officer) Date: 25/08/2019

S.NO Observation Control Measure Timescale


1. Too many Bed bugs found on every Arrange pest control treatment for 1 week
room all rooms periodically

2. Two rooms of labors accommodation Need to make new paint for


ceiling paint damaged & its falling to damaged ceiling paint area 1 week
ground
2. Mattress & Beds on Damage Condition Need to replace damaged mattress 1 month
& beds
Air-conditions are dirty & no covers and Need to make service all air-
3. not cooling properly condition if it’s in working condition 1 month
and replace damaged air-
conditions
Need to remove luggage from
overhead beds
4. Labors kept their luggage on Overhead make arrangements for shelves or 1 month
beds. cupboards for kept their matter on
safer way

Gas cylinders kept inside the kitchen & Remove gas cylinders from kitchen
5. housekeeping not in good condition in Training labors for keep kitchen 1 Day
cooking area area tidy & clean

6. Labor toilets very dirty & Smelly and Arrange some disinfector liquids for 1 week
walls with fungus cleaning toilets & remove fungus
from walls

Photos:
Damaged Ceeling paint
Camp Inspection Report
Inspected by: V.Gopala Krishna Reddy, (Safety Officer) Date: 25/08/2019
Luggage on Overhead Beds
Camp Inspection Report
Inspected by: V.Gopala Krishna Reddy, (Safety Officer) Date: 25/08/2019
A/C Condition

Kitchen
Camp Inspection Report
Inspected by: V.Gopala Krishna Reddy, (Safety Officer) Date: 25/08/2019
Toilets