Standard Deviation of Concrete Cubes

A Min Max Standard Deviation (N/mm2)


For the month of : Sep -2015 Strength
34.49
33.61 35.37 0.48
28 Days B
Sl.No Location Grade D.O.C D.O.T compr.strength Average A-B (A-B)2
compr.
sample-1 sample-2 sample-3 strength
1 A TOWER M30 30-Jul-15 27-Aug-15 34.57 33.57 33.73 33.96 0.53 0.28
2 UG SUMP M30 30-Jul-15 27-Aug-15 33.73 34.84 34.48 34.35 0.14 0.02
3 UG SUMP M30 30-Jul-15 27-Aug-15 34.04 34.31 33.24 33.86 0.63 0.39
4 A TOWER M30 31-Jul-15 28-Aug-15 34.84 34.40 34.17 34.47 0.02 0.00
5 F TOWER M30 1-Aug-15 29-Aug-15 34.17 33.51 33.28 33.65 0.84 0.70
6 D TOWER M30 1-Aug-15 29-Aug-15 33.86 34.40 33.73 34.00 0.49 0.24
7 D TOWER M30 1-Aug-15 29-Aug-15 33.95 33.73 33.24 33.64 0.85 0.72
8 D TOWER M30 1-Aug-15 29-Aug-15 34.62 34.08 33.42 34.04 0.45 0.20
9 D TOWER M30 1-Aug-15 29-Aug-15 33.55 34.17 33.68 33.80 0.69 0.48
10 A TOWER M30 2-Aug-15 30-Aug-15 35.37 34.66 34.13 34.72 -0.23 0.05
11 A TOWER M30 2-Aug-15 30-Aug-15 35.28 35.02 35.33 35.21 -0.72 0.52
12 A TOWER M30 2-Aug-15 30-Aug-15 34.17 34.84 35.02 34.68 -0.19 0.03
13 A TOWER M30 2-Aug-15 30-Aug-15 35.15 35.51 34.00 34.89 -0.40 0.16
14 E TOWER M30 3-Aug-15 31-Aug-15 34.57 34.88 35.06 34.84 -0.35 0.12
15 UG SUMP M30 4-Aug-15 1-Sep-15 35.15 34.84 34.57 34.85 -0.36 0.13
16 C TOWER M30 5-Aug-15 2-Sep-15 34.84 34.13 35.33 34.77 -0.28 0.08
17 C TOWER M30 5-Aug-15 2-Sep-15 35.28 34.53 34.84 34.88 -0.39 0.15
18 C TOWER M30 5-Aug-15 2-Sep-15 33.68 34.97 35.06 34.57 -0.08 0.01
19 C TOWER M30 5-Aug-15 2-Sep-15 35.15 34.75 34.57 34.82 -0.33 0.11
20 B TOWER M30 5-Aug-15 2-Sep-15 34.71 34.00 35.46 34.72 -0.23 0.05
21 B TOWER M30 5-Aug-15 2-Sep-15 35.06 35.33 35.73 35.37 -0.88 0.78
22 B TOWER M30 5-Aug-15 2-Sep-15 34.13 34.93 34.26 34.44 0.05 0.00
23 B TOWER M30 8-Aug-15 5-Sep-15 34.84 33.91 33.24 34.00 0.49 0.24
24 B TOWER M30 8-Aug-15 5-Sep-15 34.62 34.13 33.60 34.12 0.37 0.14
25 B TOWER M30 8-Aug-15 5-Sep-15 34.75 34.44 33.91 34.37 0.12 0.02
26 B TOWER M30 8-Aug-15 5-Sep-15 33.95 33.68 33.28 33.64 0.85 0.73

CHECKED BY VERIFIED BY
NCCCL SYNERGY
27 D TOWER M30 8-Aug-15 5-Sep-15 34.93 34.57 33.86 34.45 0.04 0.00
28 D TOWER M30 8-Aug-15 5-Sep-15 34.17 33.51 33.28 33.65 0.84 0.70
29 D TOWER M30 9-Aug-15 6-Sep-15 34.35 34.13 33.55 34.01 0.48 0.23
30 CP-I M30 9-Aug-15 6-Sep-15 34.71 34.00 33.60 34.10 0.39 0.15
31 CP-I M30 9-Aug-15 6-Sep-15 33.91 33.68 33.24 33.61 0.88 0.77
32 UG/FERN M30 6-Aug-15 3-Sep-15 34.71 34.17 33.42 34.10 0.39 0.15
33 A TOWER M30 11-Aug-15 8-Sep-15 35.11 34.53 34.88 34.84 -0.35 0.12
34 E TOWER M30 11-Aug-15 8-Sep-15 34.84 35.15 34.66 34.88 -0.39 0.15
35 A TOWER M30 11-Aug-15 8-Sep-15 33.95 34.71 34.53 34.40 0.09 0.01
36 FERN M30 12-Aug-15 9-Sep-15 35.15 34.88 34.08 34.70 -0.21 0.05
37 A TOWER M30 12-Aug-15 9-Sep-15 35.42 35.73 34.71 35.29 -0.80 0.63
38 A TOWER M30 12-Aug-15 9-Sep-15 35.15 33.91 34.62 34.56 -0.07 0.00
39 A TOWER M30 12-Aug-15 9-Sep-15 34.71 33.77 35.33 34.60 -0.11 0.01
40 A TOWER M30 12-Aug-15 9-Sep-15 35.28 34.84 33.82 34.65 -0.16 0.02
41 CP-II M30 13-Aug-15 10-Sep-15 34.84 33.82 34.17 34.28 0.21 0.05
42 CP-I M30 13-Aug-15 10-Sep-15 35.51 35.86 34.88 35.42 -0.93 0.86
43 FERN M30 17-Aug-15 14-Sep-15 34.66 34.08 35.88 34.87 -0.38 0.15
44 FERN M30 18-Aug-15 15-Sep-15 35.33 34.84 34.08 34.75 -0.26 0.07
45 C TOWER M30 18-Aug-15 15-Sep-15 34.88 33.95 35.15 34.66 -0.17 0.03
46 C TOWER M30 18-Aug-15 15-Sep-15 34.57 35.06 34.84 34.82 -0.33 0.11
47 C TOWER M30 18-Aug-15 15-Sep-15 35.28 34.17 35.15 34.87 -0.38 0.14
48 C TOWER M30 18-Aug-15 15-Sep-15 34.84 35.20 34.88 34.97 -0.48 0.23
49 UG SUMP M30 21-Aug-15 18-Sep-15 35.11 34.84 35.42 35.12 -0.63 0.40
50 A TOWER M30 21-Aug-15 18-Sep-15 34.66 35.42 34.88 34.99 -0.50 0.25
51 A TOWER M30 22-Aug-15 19-Sep-15 35.15 34.84 35.42 35.14 -0.65 0.42
52 E TOWER M30 22-Aug-15 19-Sep-15 34.44 34.84 34.08 34.45 0.04 0.00
53 E TOWER M30 22-Aug-15 19-Sep-15 34.71 33.95 34.17 34.28 0.21 0.05
54 E TOWER M30 22-Aug-15 19-Sep-15 34.00 35.06 34.48 34.51 -0.02 0.00
55 E TOWER M30 22-Aug-15 19-Sep-15 35.15 34.88 33.82 34.62 -0.13 0.02
56 A TOWER M30 25-Aug-15 22-Sep-15 34.17 33.91 35.02 34.37 0.12 0.02
57 B TOWER M30 25-Aug-15 22-Sep-15 35.11 35.51 35.95 35.52 -1.03 1.07
58 B TOWER M30 25-Aug-15 22-Sep-15 34.66 33.11 34.13 33.97 0.52 0.27
59 B TOWER M30 25-Aug-15 22-Sep-15 34.13 34.57 33.82 34.17 0.32 0.10
60 B TOWER M30 25-Aug-15 22-Sep-15 34.88 35.15 33.60 34.54 -0.05 0.00

CHECKED BY VERIFIED BY
NCCCL SYNERGY
61 E TOWER M30 26-Aug-15 23-Sep-15 33.95 33.20 33.95 33.70 0.79 0.62
62 D TOWER M30 26-Aug-15 23-Sep-15 34.80 32.17 34.57 33.85 0.64 0.41
63 D TOWER M30 26-Aug-15 23-Sep-15 34.93 34.17 35.15 34.75 -0.26 0.07
64 D TOWER M30 26-Aug-15 23-Sep-15 34.75 33.28 35.15 34.39 0.10 0.01
65 D TOWER M30 26-Aug-15 23-Sep-15 35.20 33.95 34.71 34.62 -0.13 0.02
Average of All Samples 34.49 14.74

M30
Standard Deviation = sqrt(sum of (A-B)2/n-1)
n = number of samples = 65.00
n-1 = 64.00
Hence S.D = 0.48 (N/mm2)

CHECKED BY VERIFIED BY
NCCCL SYNERGY
Standard Deviation of Concrete Cubes
A Min Max Standard Deviation (N/mm2)
For the month of : sep -2015 Strength
23.20
0.00 40.25 27.54
28 Days B
Sl.No Location Grade D.O.C D.O.T compr.strength Average A-B (A-B)2
compr.
sample-1 sample-2 sample-3 strength
1 FERN M35 6-Oct-14 3-Nov-14 38.62 37.68 38.17 38.16 4.53 20.55
2 E & F TOW M35 6-Oct-14 3-Nov-14 38.08 38.48 38.84 38.47 4.22 17.84
3 A TOWER M35 6-Oct-14 3-Nov-14 38.40 37.64 38.93 38.32 4.37 19.07
4 C TOWER M35 7-Oct-14 4-Nov-14 38.40 38.17 39.20 38.59 4.10 16.81
5 FERN M35 7-Oct-14 4-Nov-14 37.95 37.64 38.08 37.89 4.80 23.04
6 E TOWER M35 7-Oct-14 4-Nov-14 38.26 37.77 39.15 38.39 4.30 18.46
7 D TOWER M35 8-Oct-14 5-Nov-14 37.55 38.97 38.40 38.31 4.38 19.21
8 B TOWER M35 12-Oct-14 9-Nov-14 38.13 38.93 38.48 38.51 4.18 17.44
9 A TOWER M35 13-Oct-14 10-Nov-14 38.62 38.00 37.68 38.10 4.59 21.07
10 A TOWER M35 14-Oct-14 11-Nov-14 38.40 37.28 37.95 37.88 4.81 23.17
11 G & E TOW M35 14-Oct-14 11-Nov-14 38.66 38.13 37.19 37.99 4.70 22.06
12 FERN M35 16-Oct-14 13-Nov-14 38.62 39.11 39.24 38.99 3.70 13.69
13 A TOWER M35 17-Oct-14 14-Nov-14 38.40 38.97 39.37 38.91 3.78 14.26
14 FERN M35 21-Oct-14 18-Nov-14 39.42 39.06 39.46 39.31 3.38 11.40
15 B TOWER M35 23-Oct-14 20-Nov-14 39.11 38.80 39.70 39.20 3.49 12.16
16 FERN M35 23-Oct-14 20-Nov-14 35.02 35.42 34.17 34.87 7.82 61.15
17 B TOWER M35 24-Oct-14 21-Nov-14 39.77 40.53 39.42 39.91 2.78 7.75
18 C TOWER M35 25-Oct-14 22-Nov-14 39.55 40.80 40.40 40.25 2.44 5.95
19 A TOWER M35 25-Oct-14 22-Nov-14 39.77 38.84 38.62 39.08 3.61 13.06
20 B TOWER M35 26-Oct-14 23-Nov-14 40.40 38.66 38.04 39.03 3.66 13.37
21 E TOWER M35 27-Oct-14 24-Nov-14 39.10 39.86 38.80 39.25 3.44 11.81
22 B TOWER M35 27-Oct-14 24-Nov-14 39.86 40.13 38.84 39.61 3.08 9.49
23 B TOWER M35 28-Oct-14 25-Nov-14 38.40 39.90 39.15 39.15 3.54 12.53
24 C & D TOW M35 28-Oct-14 25-Nov-14 40.66 39.86 39.00 39.84 2.85 8.12
1 M35 27-Jan-00 0.00 42.69 1822.44
2 M35 27-Jan-00 0.00 42.69 1822.44

CHECKED BY VERIFIED BY
NCCCL SYNERGY
3 M35 27-Jan-00 0.00 42.69 1822.44
4 M35 27-Jan-00 0.00 42.69 1822.44
5 M35 27-Jan-00 0.00 42.69 1822.44
6 M35 27-Jan-00 0.00 42.69 1822.44
7 M35 27-Jan-00 0.00 42.69 1822.44
8 M35 27-Jan-00 0.00 42.69 1822.44
9 M35 27-Jan-00 0.00 42.69 1822.44
10 M35 27-Jan-00 0.00 42.69 1822.44
11 M35 27-Jan-00 0.00 42.69 1822.44
12 M35 27-Jan-00 0.00 42.69 1822.44
13 M35 27-Jan-00 0.00 42.69 1822.44
14 M35 27-Jan-00 0.00 42.69 1822.44
15 M35 27-Jan-00 0.00 42.69 1822.44
16 M35 27-Jan-00 0.00 42.69 1822.44
Average of All Samples 23.20 29,572.44

M35
Standard Deviation = sqrt(sum of (A-B)2/n-1)
n = number of samples = 40.00
n-1 = 39.00
Hence S.D = 27.54 (N/mm2)

CHECKED BY VERIFIED BY
NCCCL SYNERGY
Standard Deviation of Concrete Cubes
A Min Max Standard Deviation (N/mm2)
For the month of :AUGUST -2014 Strength
1.99 0.00 43.89 45.56
28 Days B
Sl.No Location Grade D.O.C D.O.T compr.strength Average A-B (A-B)2
compr.
sample-1 sample-2 sample-3 strength
1 FERN M40 4-Oct-14 1-Nov-14 43.06 44.00 44.44 43.83 2.27 5.14
2 C TOWER M40 6-Oct-14 3-Nov-14 43.46 44.08 44.13 43.89 2.21 4.88
3 M40 27-Jan-00 0.00 46.10 2,125.21
4 M40 27-Jan-00 0.00 46.10 2,125.21
5 M40 27-Jan-00 0.00 46.10 2,125.21
6 M40 27-Jan-00 0.00 46.10 2,125.21
7 M40 27-Jan-00 0.00 46.10 2,125.21
8 M40 27-Jan-00 0.00 46.10 2,125.21
9 M40 27-Jan-00 0.00 46.10 2,125.21
10 M40 27-Jan-00 0.00 46.10 2,125.21
11 M40 27-Jan-00 0.00 46.10 2,125.21
12 M40 27-Jan-00 0.00 46.10 2,125.21
13 M40 27-Jan-00 0.00 46.10 2,125.21
14 M40 27-Jan-00 0.00 46.10 2,125.21
15 M40 27-Jan-00 0.00 46.10 2,125.21
16 M40 27-Jan-00 0.00 46.10 2,125.21
17 M40 27-Jan-00 0.00 46.10 2,125.21
18 M40 27-Jan-00 0.00 46.10 2,125.21
19 M40 27-Jan-00 0.00 46.10 2,125.21
20 M40 27-Jan-00 0.00 46.10 2,125.21
21 M40 27-Jan-00 0.00 46.10 2,125.21
22 M40 27-Jan-00 0.00 46.10 2,125.21
23 M40 27-Jan-00 0.00 46.10 2,125.21
24 M40 17-Oct-14 0.00 46.10 2,125.21
25 M40 27-Jan-00 0.00 46.10 2,125.21
26 M40 27-Jan-00 0.00 46.10 2,125.21
27 M40 27-Jan-00 0.00 46.10 2,125.21

CHECKED BY VERIFIED BY
NCCCL SYNERGY
28 M40 27-Jan-00 0.00 46.10 2,125.21

CHECKED BY VERIFIED BY
NCCCL SYNERGY
29 M40 27-Jan-00 0.00 46.10 2,125.21
30 M40 27-Jan-00 0.00 46.10 2,125.21
31 M40 27-Jan-00 0.00 46.10 2,125.21
32 M40 27-Jan-00 0.00 46.10 2,125.21
33 M40 27-Jan-00 0.00 46.10 2,125.21
34 M40 27-Jan-00 0.00 46.10 2,125.21
35 M40 27-Jan-00 0.00 46.10 2,125.21
36 M40 27-Jan-00 0.00 46.10 2,125.21
37 M40 27-Jan-00 0.00 46.10 2,125.21
38 M40 27-Jan-00 0.00 46.10 2,125.21
39 M40 27-Jan-00 0.00 46.10 2,125.21
40 M40 27-Jan-00 0.00 46.10 2,125.21
41 M40 27-Jan-00 0.00 46.10 2,125.21
42 M40 27-Jan-00 0.00 46.10 2,125.21
43 M40 27-Jan-00 0.00 46.10 2,125.21
44 M40 27-Jan-00 0.00 46.10 2,125.21
Average of All Samples 1.99 89,268.84

M40
Standard Deviation = sqrt(sum of (A-B)2/n-1)
n = number of samples = 44.00
n-1 = 43.00
Hence S.D = 45.56 (N/mm2)