Professional Documents
Culture Documents
Subash 180206134539 PDF
Subash 180206134539 PDF
A PROJECT REPORT
Submitted by
MUTHUKRISHNAN S (720314103025)
RAMAIAH R M (720314103037)
RAMCHAND M T (720314103038)
SUBASH T (720314103051)
in partial fulfillment for the award of the degree
Of
BACHELOR OF ENGINEERING
IN
CIVIL ENGINEERING
AKSHAYA COLLEGE OF ENGINEERING AND TECHNOLOGY
1
PLANNING ANALYSIS AND DESIGN OF
OVERHEAD CIRCULAR WATER TANK
A PROJECT REPORT
Submitted by
MUTHUKRISHNAN S (720314103025)
RAMAIAH R M (720314103037)
RAMCHAND M T (720314103038)
SUBASH T (720314103051)
in partial fulfillment for the award of the degree
Of
BACHELOR OF ENGINEERING
IN
CIVIL ENGINEERING
AKSHAYA COLLEGE OF ENGINEERING AND TECHNOLOGY
2
BONAFIDE
ANNA UNIVERSITY: CHENNAI 600 025
BONAFIDE CERTIFICATE
SIGNATURE SIGNATURE
Mr.K.THIRUNAVUKKARASU, M.E., Mr.RATHNAVEL.PON, M.E.,
HEAD OF THE DEPARTMENT SUPERVISOR
ASSISTANT PROFESSOR ASSISTANT PROFESSOR
Department of Civil Engineering, Department of Civil Engineering,
Akshaya College of Engineering Akshaya College of Engineering
and Technology, and Technology,
Kinathukadavu. Kinathukadavu.
3
CERTIFICATE
ANNA UNIVERSITY: CHENNAI 600 025
BONAFIDE CERTIFICATE
SIGNATURE SIGNATURE
Mr.K.THIRUNAVUKKARASU, M.E., Mr.RATHNAVEL.PON,M.E.,
HEAD OF THE DEPARTMENT SUPERVISOR
ASSISTANT PROFESSOR ASSISTANT PROFESSOR
Department of Civil Engineering, Department of Civil Engineering,
Akshaya College of Engineering Akshaya College of Engineering
and Technology, and Technology,
Kinathukadavu. Kinathukadavu.
4
CONTENTS
5
TABLE OF CONTENTS
1 INTRODUCTION
1.1 WATER TANK 2
1.2 PROPOSED SITE 5
1.3 SOURCES OS WATER SUPPLY 6
1.4 POPULATION FORECASTING 8
1.5 GENERAL DESIGN REQUIREMENTS 9
1.6 PROJET SCOPE 10
1.7 PROJECT OBJECTIVE 11
1.8 PROJECT COMPONENTS 11
1.9 PROJECT METHODOLOGY 12
2 PLANNING 13
2.1 PLAN
2.2 ELEVATION
3 ANANLYSIS 14
3.1 OUTLINE OF ANALYSIS 15
3.2 ANALYSIS SUMMARY 17
3.3 SELF WEIGHT 18
6
3.4 LOADS ACTING REGION 19
3.5 COLUMN,BRACE,PLATE PROPERTIES 20
3.6 ANALYSIS RESULTS 21
4 DESIGN
4.1 DESIGN COMPONENTS 23
4.2 POPULATION FORECASTING 24
4.3 CIRCULAR TANK
4.3.1 DESIGN 25
4.3.2 DESIGN OF ROOF SLAB 26
4.3.3 DESIGN OF TANK WALL 29
4.3.4STRUCTURAL DRAWING 35
4.3 BEAM
4.3.1 DESIGN 36
4.3.2 STRUCTURAL DRAWING 42
4 .4 COLUMN
4.4.1 DESIGN 43
4.4.2 STRUCTURAL DRAWING 51
4.5 FOOTING
4.5.1 DESIGN 45
4.5.2 STRUCTURAL DRAWING 51
5 5.1 CONCLUSION 52
REFERENCE 53
7
ACKNOWLEDGEMENT
8
ACKNOWLEDGEMENT
The success of a work depends on the team and its cooperation. We take this
opportunity to express our gratitude and sincere thanks to everyone who helped us
in our project. First and foremost, we would like to thank the Management for the
Excellent Infrastructure, facilities and the constant support provided for the
successful completion of the project work.
We are indebted to the Director,
Dr.K.THANUSHKODI,M.Sc.,(Engg),Ph.D., for his continuous motivation,
inspiring words and guidance throughout this project.
We express our sincere thanks to the Joint Director Dr.N.SUGUNA,
M.E.,Ph.D., for her valuable guidance and support.
We wish to express my heartfelt thanks and deep sense of gratitude to the
Principal,Dr.J.JAYA, M.Tech.,Ph.D., for the continuous encouragement, guidance
and support.
Our special thanks to Mr.S.KAPILAN, M.E.,(Ph.D)., PRO, Civil
Engineering, for his valuable guidance, continuous support and suggestions to
improve the quality of the project work.
We thank our Assistant Professor Mr.K.THIRUNAVUKKARASU, M.E.,
Head of the Department, Department of Civil Engineering, for his valuable
guidance, continuous support and suggestions to improve the quality of the project
work.
We express our special thanks to our guide, Professor,
Mr.RATHNAVEL.PON,M.E for his valuable guidance, insightful comments and
continuous support to carry out the project work.
We express our deep sense of gratitude to all the Faculty members and
supporting staff for their continuous support in completing this project work
successfully.Our sincere thanks to our family members and friends for their support
and motivation to carry out this project successfully.
9
ABSTRACT
10
ABSTRACT
In this project, we have planned, analyzed and designed an overhead circular
reinforced cement concrete tank, to cater to requirements of Seerapalayam village
panchayat. The population of the village panchayat is estimated as 1350 using
conventional population forecasting methods. For this requirement, a circular
overhead water tank is planned using the popular drafting software AutoCAD 2D. It
is further analyzed using the premiere analysis software STAADPRO. Based on the
analysis using STAAD PRO, the salient features of the overhead circular water tank
is manually designed. The design and detailed drawings are presented in this project
work.
11
LIST OF TABLES
12
LIST OF TABLES
TABLE TITLE PAGE NO.
1 Water Demand 7
2 Population Forecasting 26
13
LIST OF FIGURES
14
LIST OF FIGURES
FIGURE TITLE PAGE NO.
1 Project Methodology 12
15
LIST OF SYMBOLS AND
ABBREVIATIONS
16
LIST OF SYMBOLS
A - Area
BM - Bending Moment
MR - Moment of resistance
M - Modular ratio
Sv - Spacing of stirrups
V - Shear force
W - Total load
Z - Lever arm
17
αx - Bending moment co-efficient along shorter span
ǿ - Diameter of bar
Ld - Development length
mm - Millimeter
N - Newton
18
19
1.1 WATER TANK
A water tank is an elevated structure supporting a water reservoir
constructed at a height sufficient to pressurize a water supply system for the
distribution of potable water, and to provide emergency storage for fire
protection.Water tanks often operate in conjunction with underground or surface
service reservoirs, which store treated water close to where it will be used. Other
types of water towers may only store raw (non-potable) water for fire protection or
industrial purposes, and may not necessarily be connected to a public water supply.
Water tank are able to supply water even during power outages, because they
rely on hydrostatic pressure produced by elevation of water (due to gravity) to push
the water into domestic and industrial water distribution systems; however, they
cannot supply the water for a long time without power, because a pump is typically
required to refill the tower. A water tower also serves as a reservoir to help with
water needs during peak usage times. The water level in the tower typically falls
during the peak usage hours of the day, and then a pump fills it back up during the
night. This process also keeps the water from freezing in cold weather, since the
tower is constantly being drained and refilled.[citation needed]
Although the use of elevated water storage tanks has existed since ancient
times in various forms, the modern use of water towers for pressurized public water
systems developed during the mid-19th century, as steam-pumping became more
common, and better pipes that could handle higher pressures were developed. In
Great Britain, standpipes, literally consisted of tall, exposed, inverted u-shaped
pipes, used for pressure relief and to provide a fixed elevation for steam-driven
pumping engines which tended to produce a pulsing flow, while the pressurized
water distribution system required constant pressure. Standpipes also provided a
20
convenient fixed location to measure flow rates. Designers typically enclosed the
riser pipes in decorative masonry or wooden structures. By the late 19th-Century,
standpipes grew to include storage tanks to meet the ever-increasing demands of
growing cities.
A variety of materials can be used to construct a typical water tower; steel and
or pre stress concrete are most often used (with wood, or brick also in use),
incorporating an interior coating to protect the water from any effects from the lining
material. The reservoir in the tower may be spherical, cylindrical, or an ellipsoid
with a minimum height of approximately 6 metres and a minimum of 4 m in
diameter A). standard water tower typically has a height of approximately 40 m
Pressurization occurs through the hydrostatic pressure of the elevation of water; or
every 10.20 centimetres of elevation, it produces 1 kilopascal of pressure. 30 m of
elevation produce roughly 300 kPa, which is enough pressure to operate and provide
for most domestic water pressure and distribution system requirements.
The height of the tower provides the pressure for the water supply system, and
it may be supplemented with a pump. The volume of the reservoir and diameter of
the piping provide and sustain flow rate. However, relying on a pump to provide
pressure is expensive; to keep up with varying demand, the pump would have to be
sized to meet peak demands. During periods of low demand, jockey pumps are used
to meet these lower water flow requirements. The water tower reduces the need for
electrical consumption of cycling pumps and thus the need for an expensive pump
control system, as this system would have to be sized sufficiently to give the same
pressure at high flow rates.
Very high volumes and flow rates are needed when fighting fires. With awater
tower present, pumps can be sized for average demand, not peak demand; the water
21
tower can provide water pressure during the day and pumps will refill the water
tower when demands are lower.
A water tank is used to store water to tide over the daily requirements. It is an
important structure in day today life as it fulfils the daily requirement of water to
public needs.
3) Underground tanks.
1) Circular tanks.
2) Rectangular tanks
3) Spherical tanks
4) Intze tank
For our design, the most popular water tank in India, the circular overhead tank is
chosen
When water is filled in circular tank, the hydrostatic water pressure will try to
increase in diameter at any section. However, this increase in the diameter all long
22
the height of the tank will depend on the nature of the joint at the junction of the wall
and bottom slab. If the joint is flexible, it will be free to move outward . the
hydrostatic pressure will be zero and hence there will be no change in diameter and
hydrostatic pressure at the bottom will be maximum, resulting in the maximum
increase in the diameter and maximum movement ,if joint is flexible.
When the joint between the wall and floor is rigid, no horizontal displacement
of the wall at the joint is possible. The deflected shape of the wall will be along
deflected. The upper part will have hoop tension, while the lower part will bend like
cantilever fixed at joint at the bottom. For shallow tanks with large diameter, hoop
stresses are very small and the wall acts more like cantilever. For deep tanks of small
diameter, the cantilever action due to fixed at the base will be small and the hoop
action will be predominant.
23
water tank are not suitable because they do not give pressurized water supply like
Elevated Overhead Tank.
3. Storage reservoirs
1. Springs
2. Infiltration wells
The quantity of water required for municipal uses for which the water supply
Water consumption rate (Per Capita Demand in litres per day per head)
Population to be served.
24
public, since there are many variable factors affecting water consumption. The
various types of water demands, which a city may have, may be broken into
following class
• Presence of industries.
• Climatic conditions.
• Quality of water:
• Cost of water.
25
This quantity should be worked out with due provision for the estimated
Requirements of the future. The future period for which a provision is made
• Expandability aspect.
• Available resources.
The various methods adopted for estimating future populations are given
below. The particular method to be adopted for a particular case or for a particular
city depends largely on the factors discussed in the methods, and the selection is
5. Ratio Method
26
6. Logistic Curve Method
(a) for resistance to cracking : the IS:456-2000 does not specify the
permissible stresses in concrete for its resistance to cracking. The permissible tensile
stresses due to bending apply to face of the member in contact with the liquid. In
members with the thickness less than 225mm and in contact with the liquid on one
side.
27
3.Permissible Stresses in Steel in Reinforcement:
When steel and concrete are assumed to act together for checking the tensile
stresses in concrete for avoidance of cracking the tensile stresses in steel will be
limited by the requirement that the permissible tensile stress in concrete is not
exceeded so that tensile stresses in steel shall be equal to product of modular ratio of
steel and concrete.
4.Steel reinforcement:
The minimum reinforcement in walls ,floor, and roofs in each of the two
directions at right angles shall have an area of 0.3% of the concrete section in that
direction for sections up to 100mm thickness. For sections of thickness greater than
100mm and less than 450 mm the minimum reinforcement in each of the two
directions shall be linearly be reduced from 0.3% for 100 mm thick section to 0.2%
for 450mm, the minimum reinforcement in each of the two directions shall be kept
at .2%.
For liquid faces of parts of members either in contact with the liquid or
enclosing the space above the liquid, the minimum cover to all reinforcement should
be 25mm or the diameter of main bar, whichever is greater.
28
To conduct case studies on the existing overhead water tank.
To know about the problems faced by the people in water supply around
the areas of existing water tank.
To find the possible solution and meet the daily requirements of water.
To overcome the problem of low water pressure at all distribution ends.
To choose a location around the area where water losses are minimum
and good efficiency is maintained.
To increase the design life period and serviceability of the structure.
To plan, analysis and design a water tank (Overhead Water Tank – made of
Reinforced Cement Concrete) for Seerapalayam panchayat.
* Functional Planning
- Selection of Site
29
1.9 PROJECT METHODOLOGY:
SQW
DRAWING
1.SITE LAYOUT
AUTO CAD 2.PLAN AND ELEVATION OF
CIRCULAR WATER TANK.
3.REINFORCEMENT DETAILS.
ANALYSIS
DESIGN
LIMITE STATE
METHOD 1. DESIGN OF CIRCULAR TANK:
DESIGN OF TANK WALL.
DESIGN OF FLOOR SLAB.
DESIGN OF BASE SLAB.
DESIGN OF GRIT&BRACE BEAM.
DESIGN OF COLUMN&FOOTING.
30
31
32
33
3.1 OUTLINE OF ANALYSIS:
The analysis of the structure that is determination of the internal forces like
Bending moment, shear force, etc in the component members, for which these
members have to be designed, under the action of given external loads. This process
requires the knowledge of structural mechanics which includes mechanics of rigid
bodies (i.e. mechanics of forces), mechanics of deformable bodies (i.e. mechanics
of deformations) and theory of structures (i.e the science dealing with response of
structural system to external loads). A brief review is taken of structural analysis to
refresh the basic principles.
The framing of a multi storied building consist of columns, girders, and beams
which support roof and floor load. Such type of building frames is something called
beam and column frame. The beam with supports the external wall is known as wall
beam or spaniel beams. A building frame may consider a number of base and may
have several stories. A multi-storeyed, multi panelled frame is a complicated
statically indeterminate structure. It consist of number of beams and columns built
monolithically, framing a network. The doors and walls are supported on beams that
transmit the loads to the columns. A building frame is subjected to both vertical as
well as horizontal loads. The vertical load consists of dead weight of the structure
components such as beams, slabs, columns, etc., and live load. The horizontal load
consists of wind forces and earthquake forces. The ability of a multi-storied building
to resist the wind 7 other lateral forces depends upon the rigidity of the connection
between beam and columns. When connections of beam and columns are fully rigid,
the structure as a whole is capable of resisting lateral force acting on the structure.
The columns for multi-stored buildings can be fabricated for one, two or more storey.
Columns may be continuous through two or three storey and the beam on each
floor is connected to such continuous column on their sides. In order to achieve
34
optimum utilization of column properties, the columns are arranged with flanges
parallel to the long axis of the structure, since the traverse wind condition is the most
severe.
Foundation, required to take the super-imposer loads on the columns, usually
consists of rafts, piles or piers going deeper, harder, strata. Structural behaviour of
multi-storied buildings subjected to lateral forces complex and. highly indeterminate
There are three recognized types of joints between beams and columns, simple, semi
rigid and rigid joints. Frames with flexible joints have no internal resistance against
horizontal loads. In another way it is possible to provide lateral resistance with the
introduction of vertical walls in proper locations. These are referred as diaphragms.
Such diaphragm infill should be made of some structural materials of substantial
stiffness and should be positively attached to the frame. The stiffness of infill
diaphragm will resist any change to the original rectangular shape of the frame.
35
3.2. ANALYSIS SUMMARY
36
3.3 SELF WEIGHT:
37
3.4 LOAD ACTING REGION:
38
3.5 COLUMN,BRACE,PLATE PROPERTIES:
39
3.6 ANALYSIS RESULTS:
40
41
4.1 DESIGN COMPONENTS:
1. Estimation of population
d. Design of beam.
f. Design of column.
3. Design of footing,
42
4.2. POPULATION FORECASTING IN SEERAPALAYAM VILLAGE
= 1124+117 = 1241
43
4.3. CIRCULAR WATER TANK
PERMISSIBLE STRESS:
σcc = 6 N/mm2
DIMENSION OF TANK:
Π x 4 x D2/ 4 = 182.22
∴D =8m
Load Calculation:
1) t = 109 mm ~ 110 mm
2) t = (30 x H ) + 50
t = 176 mm
D = 8.176 M
CENTER OF SLAB:
(Mx)c = 12.91kN/ m2
Circumferential Moment:
∴ (Mθ)c = 8.61kN/m2
√12.91 𝑥 106
d =
√1000 𝑥 1.32
45
= 98.9 mm ~ 100mm
Provide total thickness of 176 mm using 12 mm dia bars with clear cover of 15
mm.
D = 176 – 15 – 6
= 155 mm
For 1stLayer ,
155 – 12 = 143mm
= 163.76 mmc/c
= 131 mm
= 672 mm2
46
= 2/3 x 45 x 12
= 1.8 ~ 2
Pr =½xwxa
= ½ x4.125 x (8.176/2)
Hence Safe
47
4.3.3 DESIGN OF TANK WALLS:
The maximum ring tension occurs at depth 3m below the water surface ( table 5.15
Hoop tension)
Pr = 102.14 kN
= 888mm2
Spacing:
= 127 mm c/c
Hence Safe
48
√3155.6 𝑥 103
d =
√1000 𝑥 1.5
d = 45.86 mm ~50 mm
= (3 x 4 + 5)
= 12 +4 = 16cm
Available d = 160 – 31
= 109 mm
= 270 mm c/c
= 360 mm = 0.36m
49
= 480 mm2
No additional reinforcement will be provided at the inner face, since the Vertical
= 50.25 / 480
= 210 mm
= 360 mm
= 0.36m
= 480 mm2
No additional reinforcement will be provided at the inner face, since the Vertical
50
∴ Spacing =ast/ Ast x1000
BASE SLAB:
P = 35 kN / m2
= (1/16) x P x a2
= (1/16) x 35 x (8.125/2)2
= 36.10 kN m
= ½ x 35.6 x (8.125 / 2)
= 72.31 kN.m
(Mr)c = (2/16) x P x a2
= (2/16) x 35 x (8.125/2)2
51
= 58.72 kN m
Mr = 0
r = a / 2√3
= 8.125 / 2√3
∴r = 2.34 m
√68.72 𝑥 106
d =
√1000 𝑥 1.32
d = 227 mm
= 264.5 mm
Say 270 mm
Spacing:
52
= 490 / 2574 x 1000 = 190 mm
∴ Provide 25 mm dia radial bars @ 190 mm c/c from edge to the distance 1.08
m.
Pr = 58.72
𝛕V = Pr/ b x d
= 0.256
=100 Ast / b x d
= 1.15
𝛕c = 0.64 -------
𝛕v<𝛕c
53
54
4.3.4 DESIGN OF BEAM:
Square beam
Size = 300x300
W = 8.25KN/M
DESIGN
Effective depth
d =300-50 =250mm
LOAD CALCULATION:
MOMENT CALCULATION:
Mu =WL2/8
= 15.75X32/8
= 17.17KNM
55
Mub =0.138fckbd2
=0.138x20x300x3002
Mu = 74.52x106KN
REINFORCEMENT DETAILS:
74.52x106 =0.87x415Xastx300(1-415AST/20X300X250)
74.52X106 =90.26X103AST-24.97AST2
AST = 1276.14mm2
No of bars =AST/ast
= 1276.14/384.65
SHEAR REINFORCEMRNT:
Vu = WL2/2
= 15.75X3/2
=23.55KN
𝛕V = Vu/bd
= 23.55x103/300x250
56
=0.314N/mm2
Pt =100AST/bd
=100x1276.14/300x250
=1.70%
𝛕c =0.72N/mm
Hence 𝛕c <𝛕V
The section is safe in shear yet minimum shear reinforcement is provided for beam
= 0.87x415x2x50.3/0.4x300
Size = 300x650
W = 8.25KN/M
DESIGN
Effective depth
57
D = 600mm
LOAD CALCULATION
MOMENT CALCULATION
Mu =WL2/8
= 15.75X32/8
= 17.17 kN m
Mub =0.138fckbd2
=0.138x20x300x6002
MU = 298.08x106kN m
REINFORCEMENT DETAILS:
58
Spacing =ast/Ast X1000
No of bars = Ast/ast
SHEAR REINFORCEMRNT:
Vu = WL/2
= (15.75x3) /2
=23.55KN
𝛕V = Vu/bd
= 23.55x103/300x600
=0.13 N/mm2
Pt =100Ast/bd
=100x1715/300x600
= 0.95 %
𝛕c =0.8 N/mm2
Hence 𝛕c < 𝛕V
The section is safe in shear yet minimum shear reinforcement is provided for beam
59
Su = 0.87 fyx Asv/0.4 b
= 0.87x415x2x50.3/0.4x300
60
61
4.3.5 COLUMN:
(since the total load on column is p =96.56 kN ,we design the column for the max.
load of 1000kN for more obtaining more serviceability)
= 1500 KN
P = 0.4fckAc + 0.67fyAsc
= 0.4fck(Ag-Asc) + 0.67fyAsc
Ag = 300 x 300
= 90000 Nm2
62
Asc = 780 x 103/270.05
= 2888.33 mm2
Ac = Ag – Asc
= 9000 – 2888.33
= 87.11 x 103
Lateral ties:
i. 22\4 = 5.5 mm
ii. 5 mm
63
64
4.3.6 FOOTING:
(since the load axial load on the footing is 96.56 kN we choose the max. load of
1000 kN for the obtaining more serviceability)
= 5.5 m
X = 0.604m
= (1000/2 x 3)
Hence it is safe.
= 250.5 KN/m2
= 0.2505 N/mm2
65
Factored moments:
= 1.25m
= 0.5 (2-0.5)
= 0.85 m
= (0.5PuL2)
= (0.5PuL2)
= 90.5 KNm
DEPTH OF FOOTING:
Mu = 0.138fckba2
𝑀𝑢
D =√
(0.138𝑓𝑐𝑘𝑏)
195.7 𝑥 106
=√
(0.138 𝑥 20 𝑥 103
66
= 266.3 mm
From shear,
The critical section for one way shear is located at a distance from the face of the
column.
Vu = 0.2505 x 103(1250 – d)
Te = 0.36 N/mm2
P1 = 0.25
Tc = (Vu/ bd)
D = 513 mm
Footing reinforcement:
Longer direction ,
Mu = 0.87fyAstd[1-Astfy/bdfck]
67
195.7 x 106 = 0.87Ast x 415 x 550 [1-415Ast/103 x 550 x 20]
Ast = 1257mm2
Shorter direction:
Ast = 468mm2
= (3/2)
= 1.5
= [2/B+1] Ast
= [2/1.5+1](2 x 468)
= 749mm
Ast = 754mm2
The critical section for one way shear is located at distance ‘d’ from the face of the
column,
68
Factored shear force per meter width,
Vu = 250.5 x 0.7
= 176 KN
= 0.228
= (1 x 0.33)
= 0.33 N/mm2
= 0.32 N/mm2
The critical section for two-way shear is located at a distance of 0.5d from the face
of column,
= 1280 KN
Bo = 2(1.05+0.85)
= 3.8m
69
Tu = [Vu/bd]
= 0.612 N/mm2
= Ks Tc
Pc = (0.3/0.5)
= 0.6
Ks = (0.5 + 0.6)
= 1.1
Limited =1
Tc = 0.6√20
= 0.715 N/mm2
Ks x Tc = (1 x 0.175)
= 0.715 N/mm2
“Ks Tc>Tc”
Hence safe.
70
5.1 CONCLUSION
The objective of the project was to design a circular overhead tank for a village
panchayat and the same was achieved as listed as follows
Seerapalayam Village Panchayat was chosen as the location and population
was estimated for the panchayat. Based on the estimated population and prevailing
water demand, the quantity of water to be supplied and stored in the tank was
computed.
The plan and other drawings for the circular overhead water tank was prepared
using AutoCAD 2D software
The analysis was done using STAAD PRO software and the structure was
analyzed for self-weight, meshes for surface loads, brace properties, etc and the
outputs were verified. The design data were acquired after due analysis.
After analysis, the design data were generated. Based on the design data, the
overhead circular tank was designed manually.
The design would satisfy the safety and economy norms and can be used for
any village panchayat with similar population.
71
REFRENCES
TEXT BOOKS
Dayaratnam P. Design of Reinforced Concrete Structures. New Delhi. Oxford &
IBH publication.2000
Sayal & Goel .Reinforced Concrete Structures. New Delhi. S.Chand
publication.2004.
CODE BOOKS
IS 456-2000 CODE FOR PLAIN AND REINFORCED CONCRETE
IS 3370-1965 CODE FOR CONCRETE STRUCTURES FOR STORAGE OF
LIQUIDS
IS 11682 – 1985 CODE FOR RCC STAGING OF STRUCTURES
72