Download as pdf or txt
Download as pdf or txt
You are on page 1of 72

PLANNING ANALYSIS AND DESIGN OF

OVERHEAD CIRCULAR WATER TANK

A PROJECT REPORT
Submitted by
MUTHUKRISHNAN S (720314103025)
RAMAIAH R M (720314103037)
RAMCHAND M T (720314103038)
SUBASH T (720314103051)
in partial fulfillment for the award of the degree
Of
BACHELOR OF ENGINEERING
IN
CIVIL ENGINEERING
AKSHAYA COLLEGE OF ENGINEERING AND TECHNOLOGY

ANNA UNIVERSITY :: CHENNAI 600 025


OCTOBER-2017

1
PLANNING ANALYSIS AND DESIGN OF
OVERHEAD CIRCULAR WATER TANK

A PROJECT REPORT
Submitted by
MUTHUKRISHNAN S (720314103025)
RAMAIAH R M (720314103037)
RAMCHAND M T (720314103038)
SUBASH T (720314103051)
in partial fulfillment for the award of the degree
Of
BACHELOR OF ENGINEERING
IN
CIVIL ENGINEERING
AKSHAYA COLLEGE OF ENGINEERING AND TECHNOLOGY

ANNA UNIVERSITY :: CHENNAI 600 025


OCTOBER-2017

2
BONAFIDE
ANNA UNIVERSITY: CHENNAI 600 025
BONAFIDE CERTIFICATE

Certified that this project report “PLANNING ANALYSIS AND DESIGN OF


OVERHEAD CIRCULAR WATER TANK” is the bonafide work done by
……………………………………………………………………………………
Reg No…………………………………………… of final year Civil Engineering
(2017-2018) who carried out the project work under my supervision.

SIGNATURE SIGNATURE
Mr.K.THIRUNAVUKKARASU, M.E., Mr.RATHNAVEL.PON, M.E.,
HEAD OF THE DEPARTMENT SUPERVISOR
ASSISTANT PROFESSOR ASSISTANT PROFESSOR
Department of Civil Engineering, Department of Civil Engineering,
Akshaya College of Engineering Akshaya College of Engineering
and Technology, and Technology,
Kinathukadavu. Kinathukadavu.

Submitted for the project viva-voice examination held on …………………….

Internal Examiner External Examiner

3
CERTIFICATE
ANNA UNIVERSITY: CHENNAI 600 025
BONAFIDE CERTIFICATE

Certified that this project report “PLANNING ANALYSIS AND DESIGN OF


OVERHEAD CIRCULAR WATER TANK” is the bonafide work of following
students
MUTHUKRISHNAN S (720314103025)
RAMAIAH R M (720314103037)
RAMCHAND M T (720314103038)
SUBASH T (720314103051)
Who carried out the project work under my supervision.

SIGNATURE SIGNATURE
Mr.K.THIRUNAVUKKARASU, M.E., Mr.RATHNAVEL.PON,M.E.,
HEAD OF THE DEPARTMENT SUPERVISOR
ASSISTANT PROFESSOR ASSISTANT PROFESSOR
Department of Civil Engineering, Department of Civil Engineering,
Akshaya College of Engineering Akshaya College of Engineering
and Technology, and Technology,
Kinathukadavu. Kinathukadavu.

Submitted for the project viva-voice examination held on ……………….

Internal Examiner External Examiner

4
CONTENTS
5
TABLE OF CONTENTS

CHAPTER NO TITLE PAGE


NO.
ACKNOWLEDGEMENT iv
ABSTRACT vi
LIST OF TABLES viii
LIST OF FIGURES x
LIST OF SYMBOLS AND ABBREVATION xii

1 INTRODUCTION
1.1 WATER TANK 2
1.2 PROPOSED SITE 5
1.3 SOURCES OS WATER SUPPLY 6
1.4 POPULATION FORECASTING 8
1.5 GENERAL DESIGN REQUIREMENTS 9
1.6 PROJET SCOPE 10
1.7 PROJECT OBJECTIVE 11
1.8 PROJECT COMPONENTS 11
1.9 PROJECT METHODOLOGY 12

2 PLANNING 13
2.1 PLAN
2.2 ELEVATION

3 ANANLYSIS 14
3.1 OUTLINE OF ANALYSIS 15
3.2 ANALYSIS SUMMARY 17
3.3 SELF WEIGHT 18

6
3.4 LOADS ACTING REGION 19
3.5 COLUMN,BRACE,PLATE PROPERTIES 20
3.6 ANALYSIS RESULTS 21

4 DESIGN
4.1 DESIGN COMPONENTS 23
4.2 POPULATION FORECASTING 24
4.3 CIRCULAR TANK
4.3.1 DESIGN 25
4.3.2 DESIGN OF ROOF SLAB 26
4.3.3 DESIGN OF TANK WALL 29
4.3.4STRUCTURAL DRAWING 35
4.3 BEAM
4.3.1 DESIGN 36
4.3.2 STRUCTURAL DRAWING 42
4 .4 COLUMN
4.4.1 DESIGN 43
4.4.2 STRUCTURAL DRAWING 51
4.5 FOOTING
4.5.1 DESIGN 45
4.5.2 STRUCTURAL DRAWING 51

5 5.1 CONCLUSION 52

REFERENCE 53

7
ACKNOWLEDGEMENT
8
ACKNOWLEDGEMENT
The success of a work depends on the team and its cooperation. We take this
opportunity to express our gratitude and sincere thanks to everyone who helped us
in our project. First and foremost, we would like to thank the Management for the
Excellent Infrastructure, facilities and the constant support provided for the
successful completion of the project work.
We are indebted to the Director,
Dr.K.THANUSHKODI,M.Sc.,(Engg),Ph.D., for his continuous motivation,
inspiring words and guidance throughout this project.
We express our sincere thanks to the Joint Director Dr.N.SUGUNA,
M.E.,Ph.D., for her valuable guidance and support.
We wish to express my heartfelt thanks and deep sense of gratitude to the
Principal,Dr.J.JAYA, M.Tech.,Ph.D., for the continuous encouragement, guidance
and support.
Our special thanks to Mr.S.KAPILAN, M.E.,(Ph.D)., PRO, Civil
Engineering, for his valuable guidance, continuous support and suggestions to
improve the quality of the project work.
We thank our Assistant Professor Mr.K.THIRUNAVUKKARASU, M.E.,
Head of the Department, Department of Civil Engineering, for his valuable
guidance, continuous support and suggestions to improve the quality of the project
work.
We express our special thanks to our guide, Professor,
Mr.RATHNAVEL.PON,M.E for his valuable guidance, insightful comments and
continuous support to carry out the project work.
We express our deep sense of gratitude to all the Faculty members and
supporting staff for their continuous support in completing this project work
successfully.Our sincere thanks to our family members and friends for their support
and motivation to carry out this project successfully.

9
ABSTRACT

10
ABSTRACT
In this project, we have planned, analyzed and designed an overhead circular
reinforced cement concrete tank, to cater to requirements of Seerapalayam village
panchayat. The population of the village panchayat is estimated as 1350 using
conventional population forecasting methods. For this requirement, a circular
overhead water tank is planned using the popular drafting software AutoCAD 2D. It
is further analyzed using the premiere analysis software STAADPRO. Based on the
analysis using STAAD PRO, the salient features of the overhead circular water tank
is manually designed. The design and detailed drawings are presented in this project
work.

11
LIST OF TABLES
12
LIST OF TABLES
TABLE TITLE PAGE NO.
1 Water Demand 7
2 Population Forecasting 26

13
LIST OF FIGURES
14
LIST OF FIGURES
FIGURE TITLE PAGE NO.
1 Project Methodology 12

2 Cirucular Mesh Analysis 19


3 Self Weight 20
4 Load Acting Region 21

5 Column, Brace, Plate properties 22

6 Staad Pro Output Verification 23

15
LIST OF SYMBOLS AND
ABBREVIATIONS
16
LIST OF SYMBOLS

A - Area

Ast - Area of tensile steel reinforcement

Asc - Area of Compression steel

BM - Bending Moment

b - Breadth of the section

D - Overall Depth of beam (or) slab

𝐹𝑦 - Characteristic strength of steel

L - Effective length of slab along shorter span

𝑙𝑥 - Effective length of slab along longer span

MR - Moment of resistance

M - Modular ratio

P - Axial load on a compression member

Sv - Spacing of stirrups

UDL - Uniformly distributed load

V - Shear force

Vs - Design Shear Force

W - Total load

Z - Lever arm

17
αx - Bending moment co-efficient along shorter span

αy - Bending moment co-efficient along longer span

σ cbc - Permissible stress in concrete in bending compression

σst - Permissible stress in steel in tension

τv - Nominal shear stress

τc - Shear stress in concrete (permissible)

τcmax - Shear stress in concrete with shear reinforcement

ǿ - Diameter of bar

Ld - Development length

mm - Millimeter

N - Newton

C/C - Centre to centre distance

F e415 - High Yielding strength deformed bars

M 15, M20 - Grade of concrete

B.V - Basic Value

M.F - Modification Factor

18
19
1.1 WATER TANK
A water tank is an elevated structure supporting a water reservoir
constructed at a height sufficient to pressurize a water supply system for the
distribution of potable water, and to provide emergency storage for fire
protection.Water tanks often operate in conjunction with underground or surface
service reservoirs, which store treated water close to where it will be used. Other
types of water towers may only store raw (non-potable) water for fire protection or
industrial purposes, and may not necessarily be connected to a public water supply.

Water tank are able to supply water even during power outages, because they
rely on hydrostatic pressure produced by elevation of water (due to gravity) to push
the water into domestic and industrial water distribution systems; however, they
cannot supply the water for a long time without power, because a pump is typically
required to refill the tower. A water tower also serves as a reservoir to help with
water needs during peak usage times. The water level in the tower typically falls
during the peak usage hours of the day, and then a pump fills it back up during the
night. This process also keeps the water from freezing in cold weather, since the
tower is constantly being drained and refilled.[citation needed]

Although the use of elevated water storage tanks has existed since ancient
times in various forms, the modern use of water towers for pressurized public water
systems developed during the mid-19th century, as steam-pumping became more
common, and better pipes that could handle higher pressures were developed. In
Great Britain, standpipes, literally consisted of tall, exposed, inverted u-shaped
pipes, used for pressure relief and to provide a fixed elevation for steam-driven
pumping engines which tended to produce a pulsing flow, while the pressurized
water distribution system required constant pressure. Standpipes also provided a

20
convenient fixed location to measure flow rates. Designers typically enclosed the
riser pipes in decorative masonry or wooden structures. By the late 19th-Century,
standpipes grew to include storage tanks to meet the ever-increasing demands of
growing cities.

A variety of materials can be used to construct a typical water tower; steel and
or pre stress concrete are most often used (with wood, or brick also in use),
incorporating an interior coating to protect the water from any effects from the lining
material. The reservoir in the tower may be spherical, cylindrical, or an ellipsoid
with a minimum height of approximately 6 metres and a minimum of 4 m in
diameter A). standard water tower typically has a height of approximately 40 m
Pressurization occurs through the hydrostatic pressure of the elevation of water; or
every 10.20 centimetres of elevation, it produces 1 kilopascal of pressure. 30 m of
elevation produce roughly 300 kPa, which is enough pressure to operate and provide
for most domestic water pressure and distribution system requirements.

The height of the tower provides the pressure for the water supply system, and
it may be supplemented with a pump. The volume of the reservoir and diameter of
the piping provide and sustain flow rate. However, relying on a pump to provide
pressure is expensive; to keep up with varying demand, the pump would have to be
sized to meet peak demands. During periods of low demand, jockey pumps are used
to meet these lower water flow requirements. The water tower reduces the need for
electrical consumption of cycling pumps and thus the need for an expensive pump
control system, as this system would have to be sized sufficiently to give the same
pressure at high flow rates.

Very high volumes and flow rates are needed when fighting fires. With awater
tower present, pumps can be sized for average demand, not peak demand; the water

21
tower can provide water pressure during the day and pumps will refill the water
tower when demands are lower.

1.1.1 TYPES OF OVERHEAD TANKS:

A water tank is used to store water to tide over the daily requirements. It is an
important structure in day today life as it fulfils the daily requirement of water to
public needs.

The water tanks can be classified under three heads:

1) Tanks resting on ground.

2) Elevated tanks supported on staging.

3) Underground tanks.

From the shape point of view, water tanks are classified as ,

1) Circular tanks.

2) Rectangular tanks

3) Spherical tanks

4) Intze tank

5) Circular tank with conical bottoms.

For our design, the most popular water tank in India, the circular overhead tank is
chosen

1.1.2 OVERHEAD CIRCULAR WATER TANK:

When water is filled in circular tank, the hydrostatic water pressure will try to
increase in diameter at any section. However, this increase in the diameter all long

22
the height of the tank will depend on the nature of the joint at the junction of the wall
and bottom slab. If the joint is flexible, it will be free to move outward . the
hydrostatic pressure will be zero and hence there will be no change in diameter and
hydrostatic pressure at the bottom will be maximum, resulting in the maximum
increase in the diameter and maximum movement ,if joint is flexible.

When the joint between the wall and floor is rigid, no horizontal displacement
of the wall at the joint is possible. The deflected shape of the wall will be along
deflected. The upper part will have hoop tension, while the lower part will bend like
cantilever fixed at joint at the bottom. For shallow tanks with large diameter, hoop
stresses are very small and the wall acts more like cantilever. For deep tanks of small
diameter, the cantilever action due to fixed at the base will be small and the hoop
action will be predominant.

1.2 PROPOSED SITE:

The proposed site for our project is located at Seerapalayam Panchayat of


Coimbatore district. The latitude 10.878909 and longitude 76.973734 are the
geocoordinate of the Seerapalayam. Our site situated at the place where all the
natural conditions are suitable for the construction of elevated overhead water tank.
This location is one of the developing area, where there is steady increase in
Population in recent years. The population of the area according to recent survey is
around 1260. Thus this location requires a periodic water supply system atleast twice
a week. This location consist nearly 50% agricultural land. Around 450+ houses are
there and so it requires more than 100m3 capacity water tank. From the three major
types of water tank, we had adopted Elevated Overhead tank because the location
needs pressurized water supply. Other than Elevated Overhead tanks, other types of

23
water tank are not suitable because they do not give pressurized water supply like
Elevated Overhead Tank.

1.3 SOURCES OF WATER SUPPLY :

The various sources of water can be classified into two categories:

Surface sources, such as

1. Ponds and lakes

2. Streams and rivers

3. Storage reservoirs

4. Oceans, generally not used for water supplies, at present.

Sub-surface sources or underground sources, such as

1. Springs

2. Infiltration wells

3. Wells and Tube-wells.

1.3.1 Water Quantity Estimation

The quantity of water required for municipal uses for which the water supply

scheme has to be designed requires following data:

Water consumption rate (Per Capita Demand in litres per day per head)

Population to be served.

Quantity= Per demand x Population


It is very difficult to precisely assess the quantity of water demanded by the

24
public, since there are many variable factors affecting water consumption. The

various types of water demands, which a city may have, may be broken into

following class

Domestic purpose 135 litres/c/d

Industrial use 40 litres/c/d

Public use 25 litres/c/d

Fire demand 15 litres/c/d

Losses, Wastage and thefts 55 litres/c/d

Total 270 litres/c/d

TABLE 1. WATER DEMAND

The factors affecting water demand may be summarized as follows

• Size of the city

• Presence of industries.

• Climatic conditions.

• Habits of economic status.

• Quality of water:

• Pressure in the distribution system.

• Efficiency of water works administration:

• Cost of water.

• Policy of metering and charging method

25
This quantity should be worked out with due provision for the estimated

Requirements of the future. The future period for which a provision is made

in the water supply scheme is known as the design period.

Design period is estimated based on the following:

• Useful life of the component , considering obsolescence, wear, tear, etc.

• Expandability aspect.

• Anticipated rate of growth of population, including industrial, commercial

developments & migration-immigration.

• Available resources.

• Performance of the system during initial period.

1.4 POPULATION FORECASTING METHODS

The various methods adopted for estimating future populations are given

below. The particular method to be adopted for a particular case or for a particular

city depends largely on the factors discussed in the methods, and the selection is

left to the discretion and intelligence of the designer.

1. Incremental Increase Method

2. Decreasing Rate of Growth Method

3. Simple Graphical Method

4. Comparative Graphical Method

5. Ratio Method

26
6. Logistic Curve Method

7. Arithmetic Increase Method

8. Geometric Increase Method

In our design, the population is forecasted using Arithmetic, Geometric,


Incremental and Decreasing Rate methods and the average value is taken as design
population.

1.5 GENERAL DESIGN REQUIREMENTS (IS: 3370)

Plain concrete structures: Plain concrete members of reinforced concrete


liquid structures may be designed against structural failure by allowing tension in
plain concrete as per permissible limits for tension in bending specified in IS:456-
2000.

1.Permissible Stresses in Concrete:

(a) for resistance to cracking : the IS:456-2000 does not specify the
permissible stresses in concrete for its resistance to cracking. The permissible tensile
stresses due to bending apply to face of the member in contact with the liquid. In
members with the thickness less than 225mm and in contact with the liquid on one
side.

(b)For strength calculations: For strength calculations the usual permissible


stresses in accordance with IS:456-2000 are used. Where the calculated shear stress
in concrete above exceeds the permissible value, reinforcement acting in conjunction
with diagonal compression in concrete shall be provided to take whole of the shear.

27
3.Permissible Stresses in Steel in Reinforcement:

When steel and concrete are assumed to act together for checking the tensile
stresses in concrete for avoidance of cracking the tensile stresses in steel will be
limited by the requirement that the permissible tensile stress in concrete is not
exceeded so that tensile stresses in steel shall be equal to product of modular ratio of
steel and concrete.

4.Steel reinforcement:

The minimum reinforcement in walls ,floor, and roofs in each of the two
directions at right angles shall have an area of 0.3% of the concrete section in that
direction for sections up to 100mm thickness. For sections of thickness greater than
100mm and less than 450 mm the minimum reinforcement in each of the two
directions shall be linearly be reduced from 0.3% for 100 mm thick section to 0.2%
for 450mm, the minimum reinforcement in each of the two directions shall be kept
at .2%.

5.Minimum cover to reinforcement:

For liquid faces of parts of members either in contact with the liquid or
enclosing the space above the liquid, the minimum cover to all reinforcement should
be 25mm or the diameter of main bar, whichever is greater.

1.6 PROJECT SCOPE

 To make a study about the analysis and design of water tank.


 To make a study about the guidelines for the design of liquid retaining
structures according to IS Code.
 To know about the design philosophy for the safe and economical
design of water tank.

28
 To conduct case studies on the existing overhead water tank.
 To know about the problems faced by the people in water supply around
the areas of existing water tank.
 To find the possible solution and meet the daily requirements of water.
 To overcome the problem of low water pressure at all distribution ends.
 To choose a location around the area where water losses are minimum
and good efficiency is maintained.
 To increase the design life period and serviceability of the structure.

1.7 PROJECT OBJECTIVE

To plan, analysis and design a water tank (Overhead Water Tank – made of
Reinforced Cement Concrete) for Seerapalayam panchayat.

1.8 PROJECT COMPONENTS

* Functional Planning

- Selection of Site

- Estimation of Tank Capacity

- Design of Tank Dimensions

* Structural Analysis and Design

- Preparation of Tank Plan using AUTOCAD

- Analysis of the Structure using STAAD PRO

- Manual Design based on STAAD PRO Results

29
1.9 PROJECT METHODOLOGY:

SQW
DRAWING
1.SITE LAYOUT
AUTO CAD 2.PLAN AND ELEVATION OF
CIRCULAR WATER TANK.
3.REINFORCEMENT DETAILS.

ANALYSIS

STAAD PRO 1. STRUCTURAL ANALYSIS OF


CIRCULAR WATER TANK..

DESIGN

LIMITE STATE
METHOD 1. DESIGN OF CIRCULAR TANK:
 DESIGN OF TANK WALL.
 DESIGN OF FLOOR SLAB.
 DESIGN OF BASE SLAB.
 DESIGN OF GRIT&BRACE BEAM.
 DESIGN OF COLUMN&FOOTING.

FIG 1. PROJECT METHODOLOGY

30
31
32
33
3.1 OUTLINE OF ANALYSIS:

The analysis of the structure that is determination of the internal forces like
Bending moment, shear force, etc in the component members, for which these
members have to be designed, under the action of given external loads. This process
requires the knowledge of structural mechanics which includes mechanics of rigid
bodies (i.e. mechanics of forces), mechanics of deformable bodies (i.e. mechanics
of deformations) and theory of structures (i.e the science dealing with response of
structural system to external loads). A brief review is taken of structural analysis to
refresh the basic principles.

The framing of a multi storied building consist of columns, girders, and beams
which support roof and floor load. Such type of building frames is something called
beam and column frame. The beam with supports the external wall is known as wall
beam or spaniel beams. A building frame may consider a number of base and may
have several stories. A multi-storeyed, multi panelled frame is a complicated
statically indeterminate structure. It consist of number of beams and columns built
monolithically, framing a network. The doors and walls are supported on beams that
transmit the loads to the columns. A building frame is subjected to both vertical as
well as horizontal loads. The vertical load consists of dead weight of the structure
components such as beams, slabs, columns, etc., and live load. The horizontal load
consists of wind forces and earthquake forces. The ability of a multi-storied building
to resist the wind 7 other lateral forces depends upon the rigidity of the connection
between beam and columns. When connections of beam and columns are fully rigid,
the structure as a whole is capable of resisting lateral force acting on the structure.
The columns for multi-stored buildings can be fabricated for one, two or more storey.
Columns may be continuous through two or three storey and the beam on each
floor is connected to such continuous column on their sides. In order to achieve
34
optimum utilization of column properties, the columns are arranged with flanges
parallel to the long axis of the structure, since the traverse wind condition is the most
severe.
Foundation, required to take the super-imposer loads on the columns, usually
consists of rafts, piles or piers going deeper, harder, strata. Structural behaviour of
multi-storied buildings subjected to lateral forces complex and. highly indeterminate
There are three recognized types of joints between beams and columns, simple, semi
rigid and rigid joints. Frames with flexible joints have no internal resistance against
horizontal loads. In another way it is possible to provide lateral resistance with the
introduction of vertical walls in proper locations. These are referred as diaphragms.
Such diaphragm infill should be made of some structural materials of substantial
stiffness and should be positively attached to the frame. The stiffness of infill
diaphragm will resist any change to the original rectangular shape of the frame.

35
3.2. ANALYSIS SUMMARY

FIG 2. CIRCULAR MESH ANALYSIS

36
3.3 SELF WEIGHT:

FIG 3. SELF WEIGHT

37
3.4 LOAD ACTING REGION:

FIG 4. LOAD ACTING REGION

38
3.5 COLUMN,BRACE,PLATE PROPERTIES:

FIG 5. COLUMN,BRACE,PLATE PROPERTIES

39
3.6 ANALYSIS RESULTS:

FIG 6. STAAD PRO OUTPUT VERIFICATION

40
41
4.1 DESIGN COMPONENTS:

By using IS standards the following components are designed,

1. Estimation of population

2. Design of circular water tank,

a. Design of tank wall.

b. Design of roof slab.

c. Design of base slab.

d. Design of beam.

e. Design of grit beam.

f. Design of column.

3. Design of footing,

42
4.2. POPULATION FORECASTING IN SEERAPALAYAM VILLAGE

YEAR POPULATION INCREASE INCREMENTAL PERCENTAGE DECREASE IN


PER INCREASE INCREASE PERCENTAGE
DECADE INCREASE
1960 536 ---- --- --- ---
1970 652 116 --- 21.6 ---
1980 721 69 -47 10.5 -11.1
1990 829 108 39 13.02 2.52
2000 950 121 13 14.59 1.57
2010 1124 171 50 18 3.41
AVERAGE 117 13.75 15.5 -3.6
TABLE 2. POPULATION FORECASTING

Arithmetical progression method

= 1124+117 = 1241

Geometrical progression method

= 1124 + (15.5/100) (1000) = 1279

Incremental increase method

= 1000 + 117 + 14 = 1255


Changing increase rate method

= 1124 + (18 + 3.6) (1000) / 100 = 1340

Considering highest value , P = 1340

Rounded off to Population of P = 1350

43
4.3. CIRCULAR WATER TANK

4.3.1 DESIGN OF CIRCULAR WATER TANK:

PERMISSIBLE STRESS:

σcbc = 8.5 N/mm2

σcc = 6 N/mm2

σct = 1.3 N/mm2[ for Tank wall ] and 3.2 N/mm2

σst = 150 N/mm2

DIMENSION OF TANK:

Capacity = 182250 litres (m3)

Π x 4 x D2/ 4 = 182.22

∴D =8m

Load Calculation:

Self weight of slab = 0.125 x 25 x 1 = 3.125 N/mm2

Self weight of beam = 0.3 x 25 x 0.65 = 2.65 N/mm2

Live load + floor finish load = 2.5 N/ mm2

Total load = 3.125 + 2.5

= 3.125 + 5.625 + 2.625

∴Total Load = 8.250

THICKNESS OF TANK WALL:

t = Thickness of tank wall , from cracking consideration.


44
(ϒ x H x D /2)/ (1000t + (m-1) Ast) = σct

(10 x 4.2 x 8/2) / [ 1000 x t + 12 x1680] = 1.3

1) t = 109 mm ~ 110 mm

2) t = (30 x H ) + 50

= (30 x 4.2 )+50

t = 176 mm

4.3.2 DESIGN OF ROOF SLAB :

D = 8.176 M

Thickness of slab = 125MM

Self weight = 0.125 x 25 x1 = 3.125k N/m2

Live Load = 1 kN/m2

Total Load = 4.125 kN/m2

CENTER OF SLAB:

(Mx)c = (Mθ)c = 3/16 x wu2

= 3/16 x 4.125 x (8.176/2)2

(Mx)c = 12.91kN/ m2

Circumferential Moment:

(Mθ)c =2/16 x wu2

∴ (Mθ)c = 8.61kN/m2

√12.91 𝑥 106
d =
√1000 𝑥 1.32

45
= 98.9 mm ~ 100mm

Provide total thickness of 176 mm using 12 mm dia bars with clear cover of 15
mm.

D = 176 – 15 – 6

= 155 mm

For 1stLayer ,

155 – 12 = 143mm

Circumferential Reinforcement required @ center, Ast

=12.9x106/143 x0.853 x 155

= 682.24~ 690 mm2

Provide 12 mm dia bars.

Spacing = ast/Ast x 1000

= 113 /690 x 1000

= 163.76 mmc/c

= 176 -15 – 2x12 – 6

= 131 mm

(Ast)θ = 8.61 x 106/ 11.5 x 0.85 x 131

= 672 mm2

Spacing = 169 mm c/c

The Circumferential steel will be provided for a length = 2/3 x 45 x Φ

46
= 2/3 x 45 x 12

=360 mm ~315 mm c/c

Hence provide 12mm dia bars at 200 mm c/c spacing.

Total Rings = 360/200

= 1.8 ~ 2

Pr =½xwxa

= ½ x4.125 x (8.176/2)

= (8.43 x 103) / 1000 x 143

= 0.058 kN/ m2< 2 N/mm2

Hence Safe

47
4.3.3 DESIGN OF TANK WALLS:

The maximum ring tension occurs at depth 3m below the water surface ( table 5.15
Hoop tension)

Pr = 0.608(w x H x d/2) at 0.6 x H from top

Pr = (0.608 x 10 x 4.2 x 8/2)

Pr = 102.14 kN

Acting at 2.52 meters from top

Ast = 102.14 x 103/ 115

= 888mm2

Provide 12mm dia rods

Spacing:

Spacing = (113.09 / 888) x 1000

= 127 mm c/c

Both sides = 254

Provide rings 250 mm spacing as provided.

Tensile Stress in concrete wall

= [102.14 x 103/ 1000 x 210 + 12 x 888 ] < 1.2

= 0.48 N/mm2<1.2 N/mm2

Hence Safe

Bending Moment = 3155.6 N m

48
√3155.6 𝑥 103
d =
√1000 𝑥 1.5

d = 45.86 mm ~50 mm

Provide minimum thickness = (3H + 5)

= (3 x 4 + 5)

= 12 +4 = 16cm

Using 12mm dia bars and clear cover as 25 mm,

Available d = 160 – 31

= 109 mm

Actual BM = 3155.6 x 103 / 115 x 0.853 x 109

= 295.12 mm2 ~ 295 mm2

= Provide 10 mm dia bars

Spacing =ast/ Astx 1000

= 78.53 / 295 x 1000

= 270 mm c/c

∴Provide 10 mm dia bars @ 270 mm c/c spacing.

Development length ,Ld =

= (10 x 115 ) / (4 x 0.8)

= 360 mm = 0.36m

400mm c/c spacing clear cover 25 mm. Distribution reinforcement of 0.3 %

Ast = (0.3 /100) x 160 x 1000

49
= 480 mm2

Area of steel on each face = 240 mm2

No additional reinforcement will be provided at the inner face, since the Vertical

steel for cantilever

Provide 8 mm dia bars

∴ Spacing =ast/ Ast x1000

= 50.25 / 480

= 210 mm

∴ Provide Distribution reinforcement of 8 mm dia bars @ 210 mm c/c spacing.

Development length ,Ld =

= (10 x 115 ) / (4 x 0.8)

= 360 mm

= 0.36m

400mm c/c spacing clear cover 25 mm. Distribution reinforcement of 0.3 %

Ast = (0.3 /100) x 160 x 1000

= 480 mm2

Area of steel on each face = 240 mm2

No additional reinforcement will be provided at the inner face, since the Vertical

steel for cantilever

Provide 8 mm dia bars

50
∴ Spacing =ast/ Ast x1000

= 50.25 / 480 = 210 mm

∴ Provide Distribution reinforcement of 8 mm dia bars @ 210 mm c/c spacing.

BASE SLAB:

Slab thickness = 210 mm

Weight of water = 3 x 1 x 1 x 9.8 = 23.4 kN / m2

Self weight of slab = 0.21 x 1 x 25 = 5.25 kN / m2

Weight of roof slab = 0.125 x 1 x 25 = 3.125 kN / m2

Weight of tank wall = 0.125 x 1 x 25 = 3.125

P = 35 kN / m2

Circumferential Moment = (Mo)c

= (1/16) x P x a2

= (1/16) x 35 x (8.125/2)2

= 36.10 kN m

∴Radial moment = 36.10 kN m

Radial shear = (1/2) x P x a

= ½ x 35.6 x (8.125 / 2)

= 72.31 kN.m

(Mr)c = (2/16) x P x a2

= (2/16) x 35 x (8.125/2)2

51
= 58.72 kN m

Radial Moment is zero at radius given by ,

Mr = 0

= (1/16) x P x (a2 – 3r2)

r = a / 2√3

= 8.125 / 2√3

∴r = 2.34 m

Point of Contra flexure = 1.08m

√68.72 𝑥 106
d =
√1000 𝑥 1.32

d = 227 mm

Using 25mm clear cover

Effective Depth = 227 +25 + 12.5

= 264.5 mm

Say 270 mm

= 270 – 25 – 12.5 = 232.5 mm

Spacing:

Ast = (58.72 x 106) / ( 115 x 0.853 x 232.5)

∴Ast = 2574 mm2

Provide 25 mm dia rods

Spacing =ast / Ast x 1000

52
= 490 / 2574 x 1000 = 190 mm

∴ Provide 25 mm dia radial bars @ 190 mm c/c from edge to the distance 1.08
m.

Provide 2 rings of 25 mm dia wires to support these.

CHECK FOR SHEAR:

Pr = 58.72

𝛕V = Pr/ b x d

= 58.72 x 103/ 1000 x 232.5

= 0.256

=100 Ast / b x d

= 100 x 2574 / 1000 x 232.5

= 1.15

𝛕c = 0.64 -------

𝛕v<𝛕c

Hence it is safe for shear section

53
54
4.3.4 DESIGN OF BEAM:

Square beam

Size = 300x300

Self weight of slab = 3.125KN

Self weight of beam = 2.625KN

Floor finish +live load =2.5KN

W = 8.25KN/M

DESIGN

Effective depth

d =300-50 =250mm

LOAD CALCULATION:

Load on beam =8.25KN/M

Dead load = 25x0.3x0.3 =2.25KN/M

Total load =8.25+2.25 =10.5KN/M

Design load =10.5x1.5 =15.75KN/M

MOMENT CALCULATION:

Mu =WL2/8

= 15.75X32/8

= 17.17KNM

55
Mub =0.138fckbd2

=0.138x20x300x3002

Mu = 74.52x106KN

REINFORCEMENT DETAILS:

Mub =0.87 fyAST d (1-(415AST/fck bd)

74.52x106 =0.87x415Xastx300(1-415AST/20X300X250)

74.52X106 =90.26X103AST-24.97AST2

AST = 1276.14mm2

Assume 25mm dia bar

No of bars =AST/ast

= 1276.14/384.65

=3.32 say 4nos

Provide 4 nos 25mm dia

SHEAR REINFORCEMRNT:

Vu = WL2/2

= 15.75X3/2

=23.55KN

𝛕V = Vu/bd

= 23.55x103/300x250

56
=0.314N/mm2

Pt =100AST/bd

=100x1276.14/300x250

=1.70%

From the table 19, IS 456-2000

𝛕c =0.72N/mm

Hence 𝛕c <𝛕V

The section is safe in shear yet minimum shear reinforcement is provided for beam

S𝑆𝑢 = 0.87 fyAsv/0.4 b

= 0.87x415x2x50.3/0.4x300

= 302mm say 300mm

Provide stirrups 8mm @ 300mm spacing c/c

DESIGN OF GRID BEAM :

Size = 300x650

Self weight of (roof + floor) slab = 5.25 KN

Weight of tank wall = 2.625KN

Floor finish +live load = 2.5 KN

W = 8.25KN/M

DESIGN

Effective depth

57
D = 600mm

LOAD CALCULATION

Load on beam =8.25KN/M

Dead load = 25x0.3x0.65 =2.25KN/M

Total load =8.25+2.25 =10.5KN/M

Design load =10.5x1.5 =15.75KN/M

MOMENT CALCULATION

Mu =WL2/8

= 15.75X32/8

= 17.17 kN m

Mub =0.138fckbd2

=0.138x20x300x6002

MU = 298.08x106kN m

REINFORCEMENT DETAILS:

Mub =0.87 fyAst d (1-(415Ast/fck bd)

74.52x106 =0.87x415x astx300(1-415Ast/20 x300x600)

74.52X106 =90.26X103Ast -24.97Ast2

Ast = 1715.0 mm2

Assume 25mm dia bars

58
Spacing =ast/Ast X1000

490.87 / 1715.0 x1000 =286.22mm

Say 285 mm spacing

No of bars = Ast/ast

= 1715 /285 =6.01 nos

Provide 7nos 25mm dia

SHEAR REINFORCEMRNT:

Vu = WL/2

= (15.75x3) /2

=23.55KN

𝛕V = Vu/bd

= 23.55x103/300x600

=0.13 N/mm2

Pt =100Ast/bd

=100x1715/300x600

= 0.95 %

From the Table 19, IS 456-2000

𝛕c =0.8 N/mm2

Hence 𝛕c < 𝛕V

The section is safe in shear yet minimum shear reinforcement is provided for beam

59
Su = 0.87 fyx Asv/0.4 b

= 0.87x415x2x50.3/0.4x300

= 302mm say 300mm

Provide stirrups 8mm @ 300mm spacing c/c

60
61
4.3.5 COLUMN:

Size = 300 x 300

(since the total load on column is p =96.56 kN ,we design the column for the max.
load of 1000kN for more obtaining more serviceability)

Axial load = 1000 KN

SBC of soil = 200 KN/m2

Material = M20 & Fe415

MAIN COLIUMN REINFORCEMENT:

Factored load on column ,Pu = (1.5 x 1000)

= 1500 KN

P = 0.4fckAc + 0.67fyAsc

= 0.4fck(Ag-Asc) + 0.67fyAsc

Ag = 300 x 300

= 90000 Nm2

1x103 = 0.4 x 20 (9x104- Asc) + 0.67 x AIS x Asc

= 720 x 103-8Asc + 278.05Asc

1 x 103 = 720 x103 + 270.05 Asc

780 x 103 = 270.05Asc

62
Asc = 780 x 103/270.05

= 2888.33 mm2

Ac = Ag – Asc

= 9000 – 2888.33

= 87.11 x 103

Min. reinforcement = 0.8% of gross Area

Asc =720 mm2

Provide 4 bars of 22mm dia. With

Asc = 1520 mm2

Lateral ties:

Greater diameters of,

i. 22\4 = 5.5 mm
ii. 5 mm

Adopt 6mm dia. Ties

Pitch of ties is the least of

i. Least lateral dimensions = 300 mm


ii. 16 times of longitudinal bar = 16 x 22 = 352 mm
iii. 300 mm

Adopt 6mm ties @ 250 mm C/C.

63
64
4.3.6 FOOTING:

(since the load axial load on the footing is 96.56 kN we choose the max. load of
1000 kN for the obtaining more serviceability)

Load on column = 1000x 1.5 = 1500 KN

Self weight of footing (10% ) = 150 KN

Total ultimate, Wu = 1650 KN

Footing area = (1650/1.5 x 200)

= 5.5 m

Hence , (3X x 5X) = 5.5

X = 0.604m

Short side of footing = (3 x 0.604) = 1.814 m

Long side of footing = (5 x 0.604) = 3.02 m

Adopt isolated sloped footing.

Upward soil pressure at service load,

= (1000/2 x 3)

= 167 KN/m3< 200 KN/m3

Hence it is safe.

Factored soil pressure, Pu = (1.5 x 167)

= 250.5 KN/m2

= 0.2505 N/mm2

65
Factored moments:

Cantilever projection from the short side face of the column’

= 0.5 (3- 0.5)

= 1.25m

Cantilever projection from the long side face of the column,

= 0.5 (2-0.5)

= 0.85 m

BM at the short side face of the column is,

= (0.5PuL2)

= (0.5 x 250.5 x 1.252)

BM at the long side face of column is,

= (0.5PuL2)

= (0.5 x 250.5 x 0.852)

= 90.5 KNm

DEPTH OF FOOTING:

From moment consideration,

Mu = 0.138fckba2

𝑀𝑢
D =√
(0.138𝑓𝑐𝑘𝑏)

195.7 𝑥 106
=√
(0.138 𝑥 20 𝑥 103

66
= 266.3 mm

From shear,

The critical section for one way shear is located at a distance from the face of the
column.

Shear force per meter width,

Vu = 0.2505 x 103(1250 – d)

Assuming shear strength of concrete,

Te = 0.36 N/mm2

M20 grade concrete

P1 = 0.25

Tc = (Vu/ bd)

0.36 = {(0.2505 x 103(1250 – d)/103 x d}

D = 513 mm

Hence adopt effective depth, d = 550 mm

Overall depth, D = 600 mm

Footing reinforcement:

(From IS 456-2000 CLAUSE 9.1.1)

Longer direction ,

Mu = 0.87fyAstd[1-Astfy/bdfck]

67
195.7 x 106 = 0.87Ast x 415 x 550 [1-415Ast/103 x 550 x 20]

Ast = 1029 mm2

Use 16mm dia. Bars at 160mm c/c,

Ast = 1257mm2

Shorter direction:

(90.5 x 106) = 0.87Ast x 415 x 550 [1-415 Ast/103 x 550 x 20]

Ast = 468mm2

Ratio of long to short side =B

= (3/2)

= 1.5

Reinforcement in central band width of 2m,

= [2/B+1] Ast

= [2/1.5+1](2 x 468)

= 749mm

Hence provided 12mm dia. Bar at 150mm C/C,

Ast = 754mm2

CHECK FOR SHEAR STRESS:

One way shear:

The critical section for one way shear is located at distance ‘d’ from the face of the
column,

68
Factored shear force per meter width,

Vu = 250.5 x 0.7

= 176 KN

(100ast/bd) = (100 x 1257/1000 x 550)

= 0.228

Permissible shear stress = (Ks Tc)

= (1 x 0.33)

= 0.33 N/mm2

Nominal shear stress ,Tu = (Vu/ba)

= (176 x 103/1000 x 550)

= 0.32 N/mm2

Two way shear:

The critical section for two-way shear is located at a distance of 0.5d from the face
of column,

Shear force on critical section,

Vu = [(3 x 2) – (1.05 x 0.85)]250.5

= 1280 KN

Periphery of the critical section,

Bo = 2(1.05+0.85)

= 3.8m

69
Tu = [Vu/bd]

= (1280 x 1000/3.8 x 1000 x 550)

= 0.612 N/mm2

The Permissible shear stress

= Ks Tc

Ks = (0.5+Pc) but > 1 and Tc = 0.16fck

Pc = (0.3/0.5)

= 0.6

Ks = (0.5 + 0.6)

= 1.1

Limited =1

Tc = 0.6√20

= 0.715 N/mm2

Ks x Tc = (1 x 0.175)

= 0.715 N/mm2

“Ks Tc>Tc”

Hence safe.

70
5.1 CONCLUSION

The objective of the project was to design a circular overhead tank for a village
panchayat and the same was achieved as listed as follows
Seerapalayam Village Panchayat was chosen as the location and population
was estimated for the panchayat. Based on the estimated population and prevailing
water demand, the quantity of water to be supplied and stored in the tank was
computed.
The plan and other drawings for the circular overhead water tank was prepared
using AutoCAD 2D software
The analysis was done using STAAD PRO software and the structure was
analyzed for self-weight, meshes for surface loads, brace properties, etc and the
outputs were verified. The design data were acquired after due analysis.
After analysis, the design data were generated. Based on the design data, the
overhead circular tank was designed manually.
The design would satisfy the safety and economy norms and can be used for
any village panchayat with similar population.

71
REFRENCES
TEXT BOOKS
Dayaratnam P. Design of Reinforced Concrete Structures. New Delhi. Oxford &
IBH publication.2000
Sayal & Goel .Reinforced Concrete Structures. New Delhi. S.Chand
publication.2004.

CODE BOOKS
IS 456-2000 CODE FOR PLAIN AND REINFORCED CONCRETE
IS 3370-1965 CODE FOR CONCRETE STRUCTURES FOR STORAGE OF
LIQUIDS
IS 11682 – 1985 CODE FOR RCC STAGING OF STRUCTURES

72

You might also like