Equipment Pre Mobilization Checklist
Project Pekerjaan Survei Batimetri, Onshore Geoteknik dan Deep Water Well untuk Fasilitas Senoro Fase-2
Contract Period : September 2019 - September 2020
Condition
No Equipment System Type Qty Unit
Good Fair
1 Positioning Primary System
Veripos LD4 DGPS (Trimble)
Secondary System
DGPS - CHC
1x DGPS
1x SBES System
1x MBES System
Towfish Starfish
Recorder dongle
Condition
No Equipment System Type Qty Unit
Good Fair
1 Wave & Current Measurement ADCP RDI current and wave Profiler
Available
No Equipment Quantity Type Quantity
Y/N
Tripod
Shelby tube
ion
Remarks
Bad
ion
Remarks
Bad
Diketahui Oleh
Secondary System
DGPS - CHC
1x DGPS
1x SBES System
1x MBES System
6 Magnetometer
6 Magnetometer Recording Computer Interfaced to QINSY
Recording System
Recording note book PC
Towfish Starfish
Recorder dongle
1 Wave & Current Measurement ADCP RDI current and wave Profiler
Diperiksa Oleh
Tripod
Shelby tube
Condition
Remarks
Good Fair Bad
Condition
Remarks
Good Fair Bad
Diketahui Oleh