PRE COMM/COMM PLAN FOR OIL GATHERING STATION

STEP I : INDIVIDUAL PREE COMM/COM


No Activity Result
Pree Comm/Commissioning MCC/Switch Gear
1 Relay Test and setting Report
2 Megger/Hipot for cable and Panel Report
3 Continuity Report
4 Function test Report
5 Final Installation Check List (statement ready to energize by vendor) Report
Vibration Panel.
1 Continuity Report
2 Megger test for panel and kabel Report
3 Setting alarm and trip base on spec. requirement Report
4 Function test Report
5 Final Installation Check List (statement ready to energize by vendor) Report
WIP Package
1 Alignment check Report
2 Bolt tightening check Report
3 Solo run/no load test for motor Report
4 Coupling alignment check Report
5 Function test for instrumentation Report
6 Final Installation Check List (statement ready to energize by vendor) Report
Compressor Package
1 Bolt tightening check Report
2 Contuinity for cable Report
3 Megger for cable Report
4 Function test for instrumentation and control Report
5 Final Installation Check List (statement ready to energize by vendor) Report
Support Instrument (control valve, transmitter, Pressure switch and etc)
1 Megger for cable Report
2 Contuinity Report
3 Loop Check Report
4 Function test Report
5 Final Installation Check List (statement ready to energize by vendor)
Pipeline and hook up
1 Cross check piping report already completed Check list

2
Function test and Setting for instrumentation in hook up area (Check valve, Chock
valve, turbine flow meter and etc) Report

3
Final Installation Check List for each of instrumentation (statement ready to
energize by vendor) Report
4 Liquid introduce by contractor Report
Lighting indoor and out door
1 Continuity for cable Report
2 Megger for cable Report
3 Function test Report
4 Illumination test Report
5 Final inspection check list (statement by contractor) Report

STEP II : START UP PREPARATION


No Activity Result
Check all of individual equipment already ready to start up and all of final check
1 list already completed Check list
System ready to energize and looking for best setting for all of instrumentation
2 and control Report
TATION

Concern Remarks

control fuction
Insulation
cable disconnect
proper equipment
vendor statement

cable disconnect
Insulation
control fuction
control fuction
vendor statement

Leveling
Bolt tight
Motor condition
Leveling
control fuction
vendor statement

Bolt tight
cable disconnect
Insulation
control fuction
vendor statement

Insulation
cable disconnect
control fuction
vendor statement

safety concern

equipmet funtion

vendor statement
leakage

cable disconnect
Insulation
Fuction
Ilumination
contractor statement

Concern Remarks

safety concern

Final setting