HARGA PERKIRAAN SENDIRI

(HPS)

Kegiatan : Jasa Konsultansi Perencanaan


Paket : Penyusunan DED Instalasi Pengolahan Lumpur Tinja (IPLT) Kota LubukLinggau
Lokasi : Kota Lubuklinggau
Waktu : 90 (Sembilan Puluh) Hari Kalender
Sumber Dana : APBD Kota Lubuklinggau
Tahun Anggaran : 2019

I. Biaya Langsung Personil


Volume Satuan Biaya Total Biaya
No Uraian
Kegiatan ( Rp.) ( Rp.)
A. Tenaga Ahli
1 Team Leader (1 Org x 3 Bln) 3.00 OB 17,000,000.00 51,000,000.00
2 Ahli Hidrologika (1 Org x 3 Bln) 3.00 OB 14,000,000.00 42,000,000.00
3 Ahli Planologi (1 Org x 3 Bln) 3.00 OB 14,000,000.00 42,000,000.00
4 Ahli Pengukuran (1 Org x 3 Bln) 3.00 OB 14,000,000.00 42,000,000.00
5 Ahli Sosial Ekonomi (1 Org x 3 Bln) 3.00 OB 14,000,000.00 42,000,000.00

B. Tenaga Penunjang
1 Surveyor (1 Org x 3 Bln) 3.00 OB 5,000,000.00 15,000,000.00
2 Draftman (1 Org x 3 Bln) 3.00 OB 4,000,000.00 12,000,000.00
3 Administrasi (1 Org x 3 Bln) 3.00 OB 3,000,000.00 9,000,000.00
4 Operator Komputer (1 Org x 3 Bln) 3.00 OB 3,000,000.00 9,000,000.00
Jumlah Biaya Langsung Personil 264,000,000.00
HARGA PERKIRAAN SENDIRI
(HPS)

Kegiatan : Jasa Konsultansi Perencanaan


Paket : Penyusunan DED Instalasi Pengolahan Lumpur Tinja (IPLT) Kota LubukLinggau
Lokasi : Kota Lubuklinggau
Waktu : 90 (Sembilan Puluh) Hari Kalender
Sumber Dana : APBD Kota Lubuklinggau
Tahun Anggaran : 2019

II. Biaya Langsung Non Personil


Volume Satuan Biaya Total Biaya
No Uraian
Kegiatan Rp. Rp.
A. BIAYA KANTOR DAN PERLENGKAPAN
1 Bahan Operasional Kantor 1.00 Ls 5,000,000.00 5,000,000.00
2 Peralatan Kantor
- Komputer 2 Unit x 3 Bln 6.00 Bln 500,000.00 3,000,000.00
- Laptop 2 Unit x 3 Bln 6.00 Bln 750,000.00 4,500,000.00
- Printer Ukuran A4 1 Unit x 3 Bln 3.00 Bln 500,000.00 1,500,000.00
- Printer Ukuran A3 1 Unit x 3 Bln 3.00 Bln 700,000.00 2,100,000.00
- Kamera Digital 1 Unit x 3 Bln 3.00 Bln 500,000.00 1,500,000.00
3 Biaya Presentasi 3.00 Kali 2,000,000.00 6,000,000.00
Sub. Total 23,600,000.00
B. BIAYA TRANSPORTASI
1 Kendaraan Roda Empat (Sewa) (1 Unit x 3 Bln) 3.00 Bulan 3,000,000.00 9,000,000.00
2 Kendaraan Roda Dua (Sewa) (1 Unit x 3 Bln) 3.00 Bulan 1,500,000.00 4,500,000.00
Sub. Total 13,500,000.00
C. BIAYA SURVEY LAPANGAN
1 Survey Pendahuluan
- Bahan Dan Peralatan Survey 1.00 Ls 1,000,000.00 1,000,000.00
2 Survey Topografi
- Sewa Peralatan Theodolith (1 Unit x 1 Bln) 1.00 Unit - Bulan 1,500,000.00 1,500,000.00
- Sewa Waterpass (1 Unit x 1 Bln) 1.00 Unit - Bulan 1,000,000.00 1,000,000.00
- Sewa GPS (1 Unit x 1 Bln) 1.00 Unit - Bulan 500,000.00 500,000.00
3 Survey Tanah, Pavement & Quarry
- Pekerjaan Sondir 2.00 Titik 2,000,000.00 4,000,000.00
4 Biaya Laboratorium 1.00 Ls 1,500,000.00 1,500,000.00
Sub. Total 9,500,000.00
D BIAYA PELAPORAN
1 Laporan Pendahuluan 5.00 Set 150,000.00 750,000.00
2 Laporan Antara 5.00 Set 200,000.00 1,000,000.00
3 Laporan Akhir 5.00 Set 300,000.00 1,500,000.00
4 Gambar Perencanaan A3 5.00 Set 300,000.00 1,500,000.00
5 Rencana Anggaran Biaya (RAB) 5.00 Set 300,000.00 1,500,000.00
6 Album Foto Dokumentasi 1.00 Set 250,000.00 250,000.00
7 Hard Disk Eksternal 1 TB 1.00 Buah 1,000,000.00 1,000,000.00
Sub. Total 7,500,000.00
Jumlah Biaya Langsung Non Personil 54,100,000.00
REKAPITULASI
HARGA PERKIRAAN SENDIRI
(HPS)

Kegiatan : Jasa Konsultansi Perencanaan

Paket : Penyusunan DED Instalasi Pengolahan Lumpur Tinja (IPLT) Kota LubukLinggau
Lokasi : Kota Lubuklinggau
Waktu : 90 (Sembilan Puluh) Hari Kalender
Sumber Dana : APBD Kota Lubuklinggau
Tahun Anggaran : 2019

No. URAIAN KEGIATAN JUMLAH

I BIAYA LANGSUNG PERSONIL Rp. 264,000,000.00

II. BIAYA LANGSUNG NON PERSONIL Rp. 54,100,000.00

JUMLAH Rp. 318,100,000.00

PPN 10% Rp. 31,810,000.00

TOTAL Rp. 349,910,000.00

PEMBULATAN Rp. 349,910,000.00

TERBILANG : TIGA RATUS SEMBILAN PULUH SEMBILAN JUTA SEMBILAN RATUS ENAM PULUH RIBU RUPIAH

........................, ........................................ 2019

Disusun Oleh,
......................................................................
......................................................................
......................................................................
Selaku
......................................................................

......................................................
NIP. .....................................................