Table A: Cost Summary: Signed: For On Behalf Of: Date
Table A: Cost Summary: Signed: For On Behalf Of: Date
Signed :
For on behalf of :
Date :
* Note for Korean Supplier only: Since the Supplier is entitled to claim for duty drawback in
accordance with the Legislation of the Republic of Korea for the customs duty of the raw
materials or goods imported (or to be imported) for the supply of Contract
Equipment/Material, the Supplier shall not include any amount, which is to be deducted or
refunded on the Supplier, into the total price of their quotation. This note is applicable for
the overseas project only. (Not applicable for Korean local project of which job site is
located in Korea)
TABLE A : COST SUMMARY
BOQ : BOQ - GAP_01 (HDEC Scope), BOQ - GAP_02 (HEC+DODSAL Scope) Currency : IDR
SUBCONTRACTOR NAME
Direct Cost
2 Platform&Ladder BY OTHERS - - - - - - - -
TOTAL - - - - - - - - -
Signed :
For on behalf of :
Date :
COMMERCIAL BID EVALUATION TABLE (LEVEL-2)
Project : LINE Project
SUBCONTRACTOR NAME
Direct Cost
No. Work Activity Unit Q'ty
Construction Tools &
Material Cost Labor Cost Equipment Consumable
Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price
직접비 대비 간접비 비율
COMMERCIAL BID EVALUATION TABLE (LEVEL-2)
Project : LINE Project
SUBCONTRACTOR NAME
직접비 대비 간접비 비율 -
COMMERCIAL BID EVALUATION TABLE (LEVEL-2)
Project : LINE Project
직접비 대비 간접비 비율
Platform
85-TK-0001 1
86-TK-0001A/B/C 3
86-TK-0002A/B 2
86-TK-2004 1
86-TK-2010A/B 2
86-TK-2012 1
86-TK-2013 1
86-TK-2014A/B 2
86-TK-2015A/B 2
86-TK-2016A/B 2
86-TK-2017 1
Total
Description
PFO TANK
NAPHTHA TANK
TBA TANK
RPG TANK
C6 INTERMEDIATE TANK
NON-AROMATIC TANK
BENZENE TANK
TOLUENE TANK
C9+ TANK
Dimension
Design Type Unit
(Φ ID x L or W x L x H)
Erection(Ton)
Each Total
305 305
1,736 5,208
284 567
224 224
347 695
117 117
219 219
307 614
183 366
183 366
310 310
Currency : IDR
Remark
Item No. Q'TY Description Old Data Sheet New Data Sheet
86-TK-2014A/B 2 BENZENE TANK Dengan Epoxy phenolic Tanpa Epoxy phenolic lining
86-TK-2016A/B 2 MIXED XYLENE (C8+) TANK Dengan Epoxy phenolic Tanpa Epoxy phenolic lining
86-TK-2017 1 C9+ TANK Dengan Epoxy phenolic Tanpa Epoxy phenolic lining
TABLE C : BREAKDOWN OF INDIRECT COST
Expenses that are directly related to performing each discipline work items shown on Table B.
1 Table B. Direct Cost
The direct cost of each discipline work items consists of the following components:
This item represents costs for those materials to be used for the permanent purpose and to be
incorporated into the permanent facilities of the plant, which are to be provided by the Subcontractor
1-1 Material Cost pursuant to the provisions of the Subcontract.
Costs of transportation, procurement service, customs duties, taxes, and levies for such materials are
included in this price component.
This item represents costs for the labor directly engaged in the construction of the permanent facilities of
the plant.
The direct labor consists of general foreman, foreman and those workers who work under the control of a
1-2 Labor Cost foreman, such as craftsman (carpenter, re-bar worker, welder, electrician, scaffolding worker, etc.), helpers
and common laborers.
The direct labor cost include wages, overtime premiums, insurance, taxes, social burdens, recruitment,
mob./demob., hand tools, meals, etc.
This item represents costs for the Construction Equipment such as welding/cutting equipment, generator,
cranes, truck and forklifts, etc.
1-3 Equipment Cost
Costs of operator, fuel, lubricant, grease, spare parts and temporary materials and mob./demob. as well as
rental charges for all construction equipment including all maintenance and service.
Tools and Consumables This item represents costs for the construction tools and consumables such as wooden forms for the
1-4
Cost forming work, welding rods, spare parts and temporary materials.
2 Table C. Indirect Cost Costs that are not directly associated with each discipline work items specified in the Table B.
Management & Supervisory Staff (i.e. manager, field supervision, project control staff, accountant,
engineers, etc.)
Management & Supervisory
2-1 Subcontractor shall include all costs for Management & Supervisory Staff in his own cost.
Staff
This cost will cover wages, overtime premiums, insurance, taxes, social burdens, recruitment,
mob./demob., meals, etc.
This item represents cost of those workers who are not directly engaged in the permanent work, but
engaged in the supporting services to the permanent work. Namely, lndirect Labor includes logistics,
maintenance, driver, secretarial work, warehousing, machine shop workers, material unloading worker,
2-2 Indirect Labor etc.)
Subcontractor shall include the all costs for Indirect Labor in his own cost.
This cost will cover wages, overtime premiums, insurance, taxes, social burdens, recruitment,
mob./demob., meals, etc.
This item represents provision, installation, dismantling, maintenance and operation costs of temporary
facilities required to complete his Work such as but not limited to;
Temporary Facilities &
2-3 1) Site Facilities
Utilities
2) Camp Facilities
3) Utilities & Network System
This item covers all subcontractor's field expenses for HSE management such as but not limited to;
1) Safety Management (Including PPE for manpower)
2-4 HSE Cost 2) Health and hygiene Management
3) Environmental Management
4) Security Management
This item represents cost of necessary legal proceedings, applications to central and local governments,
License, Certificates and/or tax declarations, etc., required in connection with the execution of the Subcontract Works. This item also
2-5
Registration covers all subcontractor's expenses to establish and operate a local corporation, a local branch office or a
Permanent Establishment required to the execution of the Subcontract Works.
This item represents all Insurance and Bond costs for construction work shall be included in the submitted
quotation.
Such as Worker's Compensation lnsurance, Liability Insurance, Business Mobile Liability Insurance,
2-6 Insurance & Bond Construction Equipment Liability Insurance, All risk marine cargo Insurance for the material supplied by
bidder,
Oversea traveler Accident Insurance, Performance Bond, Advance Payment Bond, Retention Bond,
Warranty Bond etc.
This item covers all taxes(except V.A.T.), duties and fees required by local regulation in relation to the
execution of the Subcontract Works such as but not limited to;
1) Corporate Tax
2) Profit Tax
2-7 Taxes, Duties, Fees 3) Withholding Tax
4) Excise Tax
5) Property Tax
6) Custom Duty
7) Any Other Taxes, Duties & Fees relating to the work, if required.
This item covers all subcontractor's field expenses such as but not limited to;
2-8 General Expenses 1) Local travel expenses, transportation and commutation
2) Other, if required.
2-9 Other Overhead & Profit Other overhead cost, if any, and profits.