Professional Documents
Culture Documents
Concrete Piling
Concrete Piling
~ 22 PCI Journal
the requirement that the leads
not be hung from lines, but that the
bottom of the leads should be sup-
ported on a firm foundation. Addi-
tional requirements of the standard
specifications required the use of
steam, air, or diesel type pile driv-
ing equipment for concrete piling
and a driving capacity depending
upon the mass to be driven. These
specification requirements contribut-
ed to early success in the use of
prestressed concrete piling because
they also formed the basic criteria
essential to success in driving these
piles. These specifications required
contractors throughout the state to
convert to equipment large enough
and, which actually had a capability
of driving concrete piling. Since very
little steam and air pile driving
equipment was being used in the
state at that time, most contractors
purchased compact operating diesel
pile driving units. This also ap-
peared to be a major factor in early
successful use of prestressed con- Fig. 1. Driving 90 ft. long 14 in. octagonal pre-
stressed pile with, a M·K diesel hammer.
crete piling because the diesel driv-
ers had the ability to drive the mas- other states who have begun the
sive piling through difficult driving use of prestressed piling. A reduc-
strata without any apparent dam- tion in the initial prestress force
age to the pile. would have increased the handling
problems although, on piling driven
DESIGN to rock, more load carrying capacity
In order that a satisfactory han- would be available.
dling and driving pile would result, Figures 2 and 3 indicate an ac-
certain basic preliminary design as- ceptable prestressed concrete pile
sumptions were necessary. No pre- standard plan on which twelve-inch
vious criteria were available, but square to sixteen-inch square, solid
after numerous preliminary calcula- and hollow piling are shown, plus
tions, the basic criteria was adopted octagonal types. The square solid
to use a design concrete prestress types have been used successfully
force of 600 to 700 pounds per in plastic and point bearing stratas.
square inch in the piling. This in- The octagonal tapered piling are
sured sufficient force to properly used in sand, sandy silts, and sand-
handle and drive the piling. The gravel formations. The hollow square
accuracy of this decision is borne piling have been used with limited
out by the successful handling and success. Due to the critical place-
driving of hundreds of piling, and ment requirements of the void dur-
the acceptance of this criteria by ing the manufacture of hollow piling,
September, 1961 23
" _____"________"---""----""-" "---1
I
I
ELEVATIONS
nl'f: :!ILl
• H
- 17,
~IZ
•
-"LD5tll"
•• "'"'""
a>
_.,
INI"t
TWO "', 'k.ll _.,
u
.."'
.I
.
"-
~ 'IZI
r:tiT~ ..-:,..., ---NOTES._..
lml!il! Load Otuac/7 ~il Slraml e.pw/s 10, !50 povnds"
t
t: .707 L
L
I 293L~ (m!ial Load on ew-17 M/fl Slr.ifld ~v.-ls I<I_ (lO(l povn<ls.
Slr~f(qlli of Concrd<! hfor~ rd~ii.N of Preslre.ss mvslt>J!40()(}psi
SlrMJIIi of ~ncrele before hand/tog Ptle mvsl bt' 4ilOOps/.
ONE POINT ~ UP All w;rt' spiral mvsl bl? cold-drilwn skd /or Concrl'le reinf-
Ijo7?,l "fiB~ ' L l"?onj orcing and salisfy !he It's/ of ASTM ,t/-3Z.
Tl?t' m;n;mvm v!ltmille sfr,ss of Preslresst;?p s!..,; sltal//Je
?501 ooo psi,
TWO POt NT PICK UP The mimm11m yK>Io' slreog/17 a! tJ. 2% o/(sel of !hepr.-slresst.Jy
skd shalf bl' t!'i!-6 of i!wmimmvm vllimal<' slrMg/1;.
All rein/orctng sf,..-; SNII "-' deformed bars.
minor flotation has been encoun- quired in the pile driving, it ap-
tered. This produces an eccen- peared reasonable, that prestressed
tric pile which causes eccentricity in concrete piling should also be per-
driving and minor tension cracks mitted an approved splice. For this
can occur transverse to the axis of reason sleeve pile splices were de-
the piling. veloped and tested in flexure by
Since competitive piling were per- testing a 10 ft. long simply support-
mitted the use of pile splices to re- ed section. Deflections were meas-
duce the length of driver leads re- ured at three points along the span.
24 PCI Journal
•~
. .. .
dQE,lfi5} - . ._,_ .
.· .· . ·
.. .
~,..
~a ~
. ... . iilf"·. . -
·- : ·.. . . o·ilf"
. . . . ... a =~ .:.·.·.:,:
. ..-..
,.~
..., a\..
~ . . ·..
. ·.··.. -'"a.
TYPE I TYPE n
,.,. ,.,. • • I •• .,
·! [i~~
,.~
:~t"'CO!d-drow~
O •.
wn
.:._• 01 ~TRAHDW/rf:SfJIWI..J: 01 ~TRAHO .J:t~ ~TRAND Wire Spiro/ ...l."t~ ~TRANI)
II I II I
SECTION A-A
Prt:sfressed sfronds as
"ndlcafed tvr pile fype.
..
'/4"~Cold·drown wire spiro
-
,_ .... ,.
...,__....,.
ilrflli«Muu ...'JIM
- ---tlfP.I'::~U
September, 1961 25
rBl-~
r - - - - - - - - - - - 1 2 ' 4 _ _ _ _ _ _ _ ___, H-T
-~1-0"~
TEST NO. I
7"
ii ~~~~~~~~~--·----,
WELD
l_
...
- - - 12'-0.. ~-
TEST NO. 2
r CAlL[ TENSIONED
TO 15,000 POUNDS -
1---- 3Co" --t----- &Co" ---------j WELD
r~ 6'
--=4=-~ ~
r~o"
i ~il-" PLATE, BENT WELD
AND WELDED
I
f - - - - - - - - - 1 2 ·0· - - - - - -
1
A.S SHOWN-·
TEST NO. 3
NOTE· FOft fURTHEft DETAILS OF PILING
SEE STANDARD PLAN NO. 1720·C·RI, TYPE I
Fig. 4. Test specimens used for flexure tests of prestressed concrete piling.
12'·0"
L 6'·0"
IIEAD Of TESTING MACHINE~ j
A
T'v rT
WPOINT A VPOINT 8
H POINT C~
h I 1--.
~ 1:::31' ).,
0
i 0
-- 2'·7" l 2'·7"
3'-ol"--+---3~o:f • -
s'-o" l s'-o"
I
Fig. 5. Details of testing apparatus for flexure tests of prestressed piling.
L .
Tests were made of two-6 ft. pile by diesel hammers to a pile is vari-
sections joined by a 6 ft. sleeve, able and frequently slightly in
which was fabricated from ~ in. doubt.
thick steel plates for one test and In order to gain some information
%6 in. thick steel plates for a second to the solution of this problem, the
test. Figure No. 4 shows the type of Nebraska Department of Roads con-
sleeve splice which was tested and ducted numerous pile load tests to
indicates the use of 2%6 in. cables. obtain some insight into the energy
These cables were tensioned to 15,- being delivered to the pile under
000 pounds each, which simulated different conditions of driving. Fig-
an end bearing of 15 tons per pile. ure No. 7 shows typical Load-Settle-
This appeared to be the minimum ment curves developed to arrive at
which might ever be specified in usable pile driving formulas and to
future bridge projects. Figure No. 5 establish reasonable energy figures
indicates the test setup and position- for diesel hammers.
ing of the deflection gages and Fig- The pile load test shown in Fig-
ure No. 6 is a graph of Load plotted ure No. 7 indicates that the calcu-
against Midspan Deflection for the lated bearing by formula should be,
two splice sleeves being tested and 4.6E ( W )
for the test of a 12-inch square pile p = S+0.1 X -(W+M)
without a splice. These tests indi- E=KWH
cated a desirability to specify a ~ K = 1.8 (H-1)
in. thick steel plate sleeve or per- (Hm)
haps one fabricated from even heav- H = stroke in feet
ier plates, if an unspliced condition H.n = 8.0 feet
is to be assimulated. P = safe load in tons
W = weight of hammer
PILE LOAD TESTS
M = weight of pile plus weight
The simultaneous introduction of ,of cap in tons
prestressed concrete piling and die- E =energy per blow in foot-tons,
sel pile drivers caused a number of and S = average penetration in
problems relative to driving corre- inches per blow for last
lation. The actual energy delivered 10 blows.
~ r-----~-----.----~-----,.-----.------.~~~----
120000
TABULATION NO. 1
Calculated
Bearing Calculated Design
Penetration Yield<•J (tons) Shear<"J Bearing<')
No. Kind of Pile below ground (tons) by Formula (tons) (tons)
1. Step Taper, Concrete
---
Filled, 143/s" Butt,
85fs" Tip 45'-4" 90 52<•) 112.3 35
2. Step Taper, Concrete
Filled, 163/s" Butt,
103/s" Tip 43'-1" 105 60<") 124.2 35
3. Monotube, Concrete
Filled, 12" Butt,
30' Tapered Section 79'-4" 220 80<'J 205.8<"J 70
4. 14" Octagonal Pre-
stressed Concrete
20' Tapered to 10" Tip 43'-0" 195 48<') 128.1 70
5. 12" Diameter Straight
Sided Shell, Concrete
Filled 43'-0" 85 35<'J 113.7 35
6. Monotube, Concrete
Filled, 12" Butt,
30' Tapered Section 43'-1%" 90 43<'J 97.8 35
28 PCI Journal
7. 10" x 42 lb. Steel "H" 43'-0" 55 35(') ll4.4 (g)
NOTES:
a. Yield is based on maximum load supported by pile with net settlement of one-
forth inch or less.
b. Average undisturbed shear strength ( s) is equal to one-half the unconfined com-
pressive strength.
Point resistance = 9 sA (silts)
= 18 sA (sands)
c. Design bearings used in the actual footing pad designs detailed on the construc-
tion plans.
d. s = 0.80 T./sq. ft. From 0-77 feet
s = 1.90 T./sq. ft. From 77-80 feet
P- 4.5 E W
e. - S+0.1 x W+M
P = safe load in tons,
W = weight of hammer or ram in tons,
M = weight of pile plus weight of cap in tons,
E = energy per blow in foot-tons,
and S =average penetration in inches per blow for last 10 blows.
f. p = __:3_!__ X~
S+0.1 W+M
(Notations as above)
g. This pile was not incorporated in the design.