Project: North West Transmission Grid Connection Project 400kV transmission line Morupule B -
Letlhakane and 220kV transmission line Letlhakane – Orapa 2
Project No. : 9078/13/01-02
Client : Botswana Power Corporation (BPC)
TECHNICAL SCHDULE FOR 400kV
REQUIRED OFFERED
ITEM DESCRIPTION UNIT
SCHEDULE A SCHEDULE B
A Phase Conductors