Professional Documents
Culture Documents
Proposed Supply Warehouse
Proposed Supply Warehouse
Proposed Supply Warehouse
BILL OF QUANTITIES
Submitted by:
In Words Err:509
BILL OF QUANTITIES
AMOUNT
60,049.50
59,519.25
133,147.56
27,243.38
Err:509
Err:509
Err:509
55,900.95
41,265.00
37,401.00
Err:509
Err:509
Err:509
PROPOSED SUPPLY WAREHOUSE
Location: QSU Diffun Campus, Diffun, Quirino
APPROVED:
208.33 218.75
1,000.00 1,050.00
5,199.09 5,459.05
973.97 1,022.67
426.96 448.31
25,946.08 27,243.38
53,239.00 55,900.95
451.21 41,265.00
205.82 37,401.00
Page 1 of 1
RECOMMENDING APPROVAL:
RICHARD P. PABLO
OIC - Director, Physical Plant & Site Development
Republic of the Philippines
QUIRINO STATE UNIVERSITY
Diffun, Quirino
A. Building 100.00%
B. Miscellaneous 0.00%
100.00%
D E S C R I P T I O N QTY
A. Building
B. Miscellaneous
BREAKDOWN OF EXPENDITURE :
APPROVED:
COST
of PCCP
ication :
g Date : Upon Approval
roject Duration : 70 cal. Days
EQUIPMENT
DESCRIPTION REQUIRED
OJECT
AMOUNT TOTAL
P 428,701.64
P -
Total P 428,701.64
MENDING APPROVAL:
RICHARD P. PABLO
OIC-Director, Physical Plant and Site Dev't.
APPROVED BUDGET FOR THE CONTRACT
APPROVED:
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Foreman 1 2.00 P 500.00 P 1,000.00
Carpenter 1 2.00 450.00 900.00
Laborer 1 2.00 300.00 600.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
C. SUB-TOTAL, MATERIAL P -
SUMMARY:
A Equipment P -
B Labor 2,500.00
C Materials -
D TOTAL DIRECT COST 2,500.00
DIRECT UNIT COST 208.33
E OCM of D -
F Profit of D -
G VAT 5% of (D+E+F) 125.00
H Total Cost (D+E+F+G) 2,625.00
I Unit Cost H/Quantity P 218.75
DETAILED UNIT PRICE ANALYSIS
PROPOSED SUPPLY WAREHOUSE
Location: QSU Diffun Campus, Diffun, Quirino
Item No. : II Quantity = 11.00
Description : Backfilling and Gravel Fill Unit = cu.m.
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
A. SUB-TOTAL , EQUIPMENT P
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials:
Gravel fill 11.00 cu.m. 600.00 6,600.00
-
SUMMARY:
A Equipment P -
B Labor 4,400.00
C Materials 6,600.00
D TOTAL DIRECT COST 11,000.00
DIRECT UNIT COST 1,000.00
E OCM of D -
F Profit of D -
G VAT 5% of (D+E+F) 550.00
H Total Cost (D+E+F+G) 11,550.00
I Unit Cost H/Quantity P 1,050.00
DETAILED UNIT PRICE ANALYSIS
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day
Equipment
A. SUB-TOTAL , EQUIPMENT P
B Designation of Personnel No. of Men No. of Days Unit Rate/Day
Labor
Construction Foreman 1.00 8.00 500.00
Mason 2.00 8.00 450.00
Laborer 4.00 8.00 300.00
B. SUB-TOTAL, LABOR P
C. SUB-TOTAL, MATERIAL P
SUMMARY:
A Equipment P
B Labor
C Materials
D TOTAL DIRECT COST
DIRECT UNIT COST
E OCM of D
F Profit of D
G VAT 5% of (D+E+F)
H Total Cost (D+E+F+G)
I Unit Cost H/Quantity P
11.00
cu.m.
-
Total Cost (Pesos)
4,000.00
7,200.00
9,600.00
-
20,800.00
25,740.00
3,300.00
6,600.00
750.00
-
-
-
-
-
-
-
-
36,390.00
-
20,800.00
36,390.00
57,190.00
5,199.09
-
-
2,859.50
60,049.50
5,459.05
DETAILED UNIT PRICE ANALYSIS
PROPOSED SUPPLY WAREHOUSE
Location: QSU Diffun Campus, Diffun, Quirino
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
-
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Labor
Construction Foreman 1.00 10.00 500.00 5,000.00
Mason 2.00 10.00 450.00 9,000.00
Laborer 3.00 10.00 300.00 9,000.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
-
4" CHB 730.00 pcs. 10.50 7,665.00
Portland cement 30.00 bags 260.00 7,800.00
fine aggregates 3.00 cu.m. 600.00 1,800.00
10mm x 6.0 def bars 40.00 pcs. 180.00 7,200.00
# 16 tie wire 10.00 kls 75.00 750.00
hacksaw blade 30.00 pcs. 75.00 2,250.00
Cement - Plastering @ .020 thicknes (2 faces) 17.00 bags 260.00 4,420.00
fine aggregates 3.00 cu.m. 600.00 1,800.00
SUMMARY:
A Equipment P -
B Labor 23,000.00
C Materials 33,685.00
D TOTAL DIRECT COST 56,685.00
DIRECT UNIT COST 973.97
E OCM of D -
F Profit of D -
G VAT 5% of (D+E+F) 2,834.25
H Total Cost (D+E+F+G) 59,519.25
I Unit Cost H/Quantity P 1,022.67
DETAILED UNIT PRICE ANALYSIS
PROPOSED SUPPLY WAREHOUSE
Location: QSU Diffun Campus, Diffun, Quirino
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
welding machine 1.00 15.00 800.00 12,000.00
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
labor
Construction Foreman 1 16.00 P 435.45 6,967.20
welder/Steelman 1 16.00 380.00 6,080.00
Laborer 2 16.00 300.00 9,600.00
B. SUB-TOTAL, LABOR P 22,647.20
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
50mm x 75mm x 2.5mm thick - Steel C- Purlins 12.00 pcs. 425.00 5,100.00
5mm x 50mm x 50mm angle bar 42.00 pcs. 650.00 27,300.00
2" x 1/4" thick Flat bar 48.00 pcs. 420.00 20,160.00
1-1/2" tekscrew 800.00 pcs. 2.50 2,000.00
welding rod @ 20kg / box 3.00 box/es 1,700.00 5,100.00
Gray primer 3.00 gals 600.00 1,800.00
Paint thinner 1.00 gal 275.00 275.00
Paint brush, 2" & 4" 5.00 pcs. 85.00 425.00
Roll-up including installation 1.00 set 30,000.00 30,000.00
-
-
-
-
-
-
-
-
C. SUB-TOTAL, MATERIAL P 92,160.00
SUMMARY:
A Equipment P 12,000.00
B Labor 22,647.20
C Materials 92,160.00
D TOTAL DIRECT COST 126,807.20
DIRECT UNIT COST 426.96
E OCM of D -
F Profit of D -
G VAT 5% of (D+E+F) 6,340.36
H Total Cost (D+E+F+G) 133,147.56
I Unit Cost H/Quantity P 448.31
DETAILED UNIT PRICE ANALYSIS
PROPOSED SUPPLY WAREHOUSE
Location: QSU Diffun Campus, Diffun, Quirino
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
A. SUB-TOTAL , EQUIPMENT P
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
labor
Construction Foreman 1.00 6.00 500.00
Carpenter 2.00 6.00 450.00
Laborer 2.00 6.00 300.00
B. SUB-TOTAL, LABOR P
C. Name and Description Quantity Unit Unit Cost Total Cost (Pesos)
Materials
Marine Plywood 31.00 pcs. 450.00
Blind Rivets (1/8 x 3/8) 1,500.00 pcs. 8.50
Concrete Nail 5.00 kls 120.00
###
C. SUB-TOTAL, MATERIAL P
SUMMARY:
A Equipment P
B Labor
C Materials
D TOTAL DIRECT COST
DIRECT UNIT COST
E OCM of D
F Profit of D
G VAT 5% of (D+E+F)
H Total Cost (D+E+F+G)
I Unit Cost H/Quantity P
87.10
sq.m.
3,000.00
5,400.00
3,600.00
12,000.00
Total Cost (Pesos)
13,950.00
12,750.00
600.00
-
-
-
-
-
-
-
27,300.00
-
12,000.00
27,300.00
39,300.00
451.21
-
-
1,965.00
41,265.00
473.77
DETAILED UNIT PRICE ANALYSIS
PROPOSED SUPPLY WAREHOUSE
Location: QSU Diffun Campus, Diffun, Quirino
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day
Equipment
A. SUB-TOTAL , EQUIPMENT P
B Designation of Personnel No. of Men No. of Days Unit Rate/Day
B. SUB-TOTAL, LABOR P
C. SUB-TOTAL, MATERIAL P
SUMMARY:
A Equipment P
B Labor
C Materials
D TOTAL DIRECT COST
DIRECT UNIT COST
E OCM
F Profit
G VAT 5% of D
H Total Cost of D
I Unit Cost of (D+E+F) P
84.88
sq.m.
-
-
-
Total Cost (Pesos)
3,483.60
3,050.48
2,400.00
8,934.08
6,500.00
6,500.00
1,512.00
300.00
2,200.00
-
-
-
-
-
17,012.00
-
8,934.08
17,012.00
25,946.08
25,946.08
-
1,297.30
27,243.38
320.96
DETAILED UNIT PRICE ANALYSIS
PROPOSED SUPPLY WAREHOUSE
Location: QSU Diffun Campus, Diffun, Quirino
Item No. : VIII Quantity = 181.72
Description : Painting works Unit = sq.m.
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Labor
Construction Foreman 1.00 7.00 500.00 3,500.00
Painter 1.00 7.00 450.00 3,150.00
Laborer 2.00 7.00 300.00 4,200.00
B. SUB-TOTAL, LABOR P 10,850.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
Semi-Gloss Latex (Boysen) 5 pails 2,400.00 12,000.00
Flat Latex (Boysen) 2 gal/s 600.00 1,200.00
Raw Siena 2 lit 150.00 300.00
Skim coat 5 bag/s 450.00 2,250.00
Easy tite 2 gal/s 580.00 1,160.00
Royal blue QDE 7 gal/s 600.00 4,200.00
Sophie Shirt Gray 1 gal/s 600.00 600.00
0136_Charcoal 1 gal/s 600.00 600.00
Vulcaseal 2 gal/s 440.00 880.00
# 80 Sand Paper 25 pcs 25.00 625.00
Paleta 3 pair/s 35.00 105.00
Paint Roller with pan 5 pcs 95.00 475.00
Paint Brush 2'' 5 pcs 75.00 375.00
-
-
-
SUMMARY:
A Equipment P -
B Labor 10,850.00
C Materials 24,770.00
D TOTAL DIRECT COST 35,620.00
DIRECT UNIT COST 35,620.00
E OCM of D -
F Profit of D -
G VAT 5% of (D+E+F) 1,781.00
H Total Cost (D+E+F+G) 37,401.00
I Unit Cost H/Quantity P 205.82
DETAILED UNIT PRICE ANALYSIS
PROPOSED SUPPLY WAREHOUSE
Location: QSU Diffun Campus, Diffun, Quirino
Item No. : IX Quantity =
Description : Electrical Works Unit =
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
A. SUB-TOTAL , EQUIPMENT P
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Labor
Construction Foreman 1.00 10.00 500.00
Electrician 1.00 10.00 450.00
Laborer 1.00 10.00 300.00
B. SUB-TOTAL, LABOR P
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
Led Tubular Ligths 18 watts with Frame & firefly
Holder 9 set/s 1,500.00
Single Pole 3 gang Switch-wide series Panasonic 2 set/s 170.00
Single Pole 1 gang Switch wide series Panasonic 2 set/s 150.00
Duplex universal Outlet with ground Panasonic 5 set/s 250.00
ACU Outlet Tandem type Panasonic 1 set/s 250.00
Electrical Tape Armak 10 pc/s. 30.00
Utility Box, metal deep type, .8mm thickness 10 pc/s. 30.00
PVC Junction Box 4x4 with Cover Poly 12 pc/s. 27.00
2.0mm.sq. THHN Copper Wire Columbia/Sycwin 1 box/es 3,500.00
3.5mm.sq. THHN Copper Wire Columbia/Sycwin 1 box/es 3,500.00
8.0mm.sq. THHN Copper Wire Columbia/Sycwin 20 mtrs 45.00
LED bulb 18 watts firefly 2 pc/s 180.00
Receptacle 4 inch firefly 2 pc/s. 150.00
Flexible Hose 1/2 " dia. poly flex 100 mtrs 45.00
Electrical conduit pipe 1" dia. polytech 1 pc/s. 65.00
25mmØ service entrance cap heavy duty 1 pc/s. 150.00
60AT Breaker Bolt-on 1 set/s 650.00
type
Universal covvinient outlet w/ ground wide Koten
series 1 set/s 250.00
C. SUB-TOTAL, MATERIAL P
SUMMARY:
A Equipment P
B Labor
C Materials
D TOTAL DIRECT COST
DIRECT UNIT COST
E OCM of D
F Profit of D
G VAT 5% of (D+E+F)
H Total Cost (D+E+F+G)
I Unit Cost H/Quantity P
1.00
l.s.
Total Cost (Pesos)
-
Total Cost (Pesos)
5,000.00
4,500.00
3,000.00
-
12,500.00
13,500.00
340.00
300.00
1,250.00
250.00
300.00
300.00
324.00
3,500.00
3,500.00
900.00
360.00
300.00
4,500.00
65.00
150.00
650.00
250.00
10,000.00
40,739.00
-
12,500.00
40,739.00
53,239.00
53,239.00
-
-
2,661.95
55,900.95
55,900.95