ID Task Name Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
0 PIPING ERECTOR

1 1 AWARD

2 2 MOB & DEMOBILIZATION

5 3 OFFICE AND INFRASTRUCTURE

10 4 PIPING WORK

23 5 SCAFFOLDING

24 6 PRECOMMISIONING WORK

32 7 PIPE INTERNAL CLEANING

33 8 DEMOBILISATION

Start External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: PIPING ERECTOR Milestone Inactive Milestone Start‐only


Date: Thu 10/10/19 Summary Inactive Summary Finish‐only
Project Summary Manual Task Deadline
External Tasks Duration‐only Progress