Professional Documents
Culture Documents
Boq
Boq
OTHER WORKS -
3 Handrail fabrication & fixing - Substation kg 450 143.51 450.00 64,580
FRP Louveres Sqm 215 2021 215 434,515
Terrace Ladder Works kg 1500 143.51 1,500.00 215,265
compount wall railing kg 1700 123 1,700.00 209,100 -
TOTAL FOR OTHER WORKS 923,460 499,095
FIRE FIGHTING
Fire Hydrant System ,External/Internal 500,000 500,000
Fire Sprinkler at Stilt floor 200,000 200,000
Fire pump panel
Fire pump room piping 100,000 100,000
-
Total Fire Fighting works 800,000 800,000
Substation -
Parapet wall @ 13.55EL & Other works -
1 Blockwork cum 4 7480 4.00 29,920
2 IPS Flooring (Transformer Panel Room) sqm 163 733.67 403.00 295,669
3 Earth Filling cum 100 273.75 25.00 6,844
4 Anti Termite Treatement Sqm 325.3 110.45 325.3 35,929
5 HDPE Sheet laying Sqm 325.3 133 325.3 43,265
6 Raft Slab Steel Kg 5600 82.07 3,953
7 Raft Slab RCC cum 56 7973.7 38.75
8 Rolling Shutter Fixing sqm 46.8 2936.18 46.8 137,413
9 Ball Bearing Hinges for Rolling Shutter NO: 14 601.67 14 8,423
10 Extra for Providing Grilled Rolling Shutters sqm 14.04 429.86 14.04 6,035
11 Excavation m3 10 187.5 3.00 563
12 External Plastering sqm 50 236.86 50.00 11,843
13 Internal primer sqm 45 49.14 45.00 2,211
14 internal Emulsion 1st coat - sqm 45 36.4 80.00 2,912
15 internal Emulsion 2nd coat - sqm 45 38.95 80.00 3,116
16 External Painting sqm 140 200.74 50.00 10,037
Total 594,181 594,181
STP -
1 Shuttering works M2 30 484.04 30.00 14,521
2 Reinforcement work kg 160 82.07 160.00 13,131
3 RCC works , parapet belt M3 2 7973.7 2.00 15,947
FINISHING WORKS - -
1 AAC Blockwork (AGT/STP Mumty Floor) M3 9 9327 9.00 83,943
14 External Plastering sqm 160 236.86 160.00 37,898
14 internal Emulsion 1st coat - sqm 120 36.4 120.00 4,368
15 internal Emulsion 2nd coat - sqm 120 38.95 120.00 4,674
16 External Painting sqm 160 200.74 160.00 32,118
Total 206,601 206,601
Drain work
1 RCC M 25 M3 57.181 7973 38.15 304,146
2 Excavation,rain water pipe M3 94.518 187.5 94.52 17,722
3 PCC drain, sw line M3 25 7042 25.00 176,050
4 Shuttering works M2 320.2136 484 213.62 103,394
5 Reinforcement works Kg 5146.29 82.07 3433.23 281,765
Total 883,077 441,538.49
Road work
1 Backfilling M3 474 273.75 474.00 129,758 129,758
2 GSB Filling M3 673 2905 673.00 1,955,065 977,532.50
3 Kerb Stone M3 10.44 7259.1 10.44 75,785 75,785
4 Paver Block Laying 100 mm M2 3472 1276 3,472.00 4,430,272 1,107,568.00
5 Paver Block Laying 60 mm M2 1024 825.44 1,024.00 845,251 845,251
Total 7,436,130 3,135,894
Stilt Floor
2 Toilet Floor sqm 12.2 1076.55 36.60 39,402
3 Toilet Walls sqm 90 1146.78 90.00 103,210
3 GSB Filling M3 10 2905 10.00 29,050
4 Paver Block Laying 60 mm Sqm 150 825.44 150.00 123,816
8 Granite Works Sqm 138 5355.88 138.00 739,111
Total 1,034,589 295,478
OTHER WORKS -
3 Handrail fabrication & fixing - Substation kg 450 143.51 450.00 64,580
FRP Louveres Sqm 215 2021 215 434,515
Terrace Ladder Works kg 1500 143.51 1,500.00 215,265
compount wall railing kg 1700 123 1,700.00 209,100 -
TOTAL FOR OTHER WORKS 923,460 499,095
FIRE FIGHTING
Fire Hydrant System ,External/Internal 500,000 500,000
Fire Sprinkler at Stilt floor 200,000 200,000
Fire pump panel
Fire pump room piping 100,000 100,000
-
Total Fire Fighting works 800,000 800,000
TARGETED
SL NO DESCRIPTION UNIT RATE PLAN FOR AUGUST PRODUCTION UP TO 05.08.2019
QUANTITY
Plan up to 15/08/2019
Target AMOUNT Target AMOUNT %
Amounts
AGT
1 Shuttering works kerb/ parapet belt shuttering/Lintel&shade M2 20 484.04 20.00 9,681 20.00 9,681
2 , parapet belt concrete/Lintel&shade m3 3 7973.7 3.00 23,921 4.50 35,882
4 External plastering M2 140 236.86 140.00 33,160 115.00 27,239
5 Internal primer sqm 80 49.14 80.00 3,931 -
6 internal Emulsion 1st coat - sqm 80 36.4 80.00 2,912 -
7 internal Emulsion 2nd coat - sqm 80 38.95 80.00 3,116 -
8 External painting sqm 250 200.74 250.00 50,185 -
Total 126,907 72,801 126,907
Substation - -
Parapet wall @ 13.55EL & Other works - -
1 Blockwork cum 4 7480 4.00 29,920 -
2 IPS Flooring (Transformer Panel Room) sqm 163 733.67 403.00 295,669 -
3 Earth Filling cum 100 273.75 25.00 6,844 -
4 Anti Termite Treatement Sqm 325.3 110.45 325.3 35,929 -
5 HDPE Sheet laying Sqm 325.3 133 325.3 43,265 -
6 Raft Slab Steel Kg 5600 82.07 3,953
7 Raft Slab RCC cum 56 7973.7 38.75
8 Rolling Shutter Fixing sqm 46.8 2936.18 46.8 137,413 -
9 Ball Bearing Hinges for Rolling Shutter NO: 14 601.67 14 8,423 -
10 Extra for Providing Grilled Rolling Shutters sqm 14.04 429.86 14.04 6,035 -
11 Excavation m3 10 187.5 3.00 563 -
12 External Plastering sqm 50 236.86 50.00 11,843 24.00 5,685
13 Internal primer sqm 45 49.14 45.00 2,211 -
14 internal Emulsion 1st coat - sqm 45 36.4 80.00 2,912 -
15 internal Emulsion 2nd coat - sqm 45 38.95 80.00 3,116 -
16 External Painting sqm 140 200.74 50.00 10,037 -
Total 594,181 5,685 594,181
STP - -
1 Shuttering works M2 30 484.04 30.00 14,521 15.00 7,261
2 Reinforcement work kg 160 82.07 160.00 13,131 150.00 12,311
3 RCC works , parapet belt M3 2 7973.7 2.00 15,947 2.00 15,947
FINISHING WORKS - - -
1 AAC Blockwork (AGT/STP Mumty Floor) M3 9 9327 9.00 83,943 8.00 74,616
14 External Plastering sqm 160 236.86 160.00 37,898 50.00 11,843
14 internal Emulsion 1st coat - sqm 120 36.4 120.00 4,368 -
15 internal Emulsion 2nd coat - sqm 120 38.95 120.00 4,674 -
16 External Painting sqm 160 200.74 160.00 32,118 -
Total 206,601 121,978 206,601
Drain work
1 RCC M 25 M3 57.181 7973 38.15 304,146 5.75 45,845
2 Excavation,rain water pipe M3 94.518 187.5 94.52 17,722 -
3 PCC drain, sw line, kerbstone M3 25 7042 25.00 176,050 2.65 18,661
4 Shuttering works M2 320.2136 484 213.62 103,394 32.20 15,585
5 Reinforcement works Kg 5146.29 82.07 3433.23 281,765 517.50 42,471
Total 883,077 122,562 441,538.49
Road work
1 Backfilling M3 474 273.75 474.00 129,758 36.00 9,855 129,758
2 GSB Filling M3 673 2905 673.00 1,955,065 41.00 119,105 977,532.50
3 Kerb Stone M3 10.44 7259.1 10.44 75,785 0.68 4,900 75,785
4 Paver Block Laying 100 mm M2 3472 1276 3,472.00 4,430,272 - 1,107,568.00
5 Paver Block Laying 60 mm M2 1024 825.44 1,024.00 845,251 - 845,251
Total 7,436,130 133,860 3,135,894
Guard Room - -
2 Grade Slab RCC Cum 0.441 7192.12 0.44 3,172 -
4 Beam RCC Cum 0.756 7973.7 0.76 6,028 -
5 Slab RCC Cum 0.6615 7973.7 0.66 5,275 -
6 Lintel & Shade RCC Cum 0.22 7973.7 0.22 1,754 -
7 Beam Shuttering Sqm 14.175 400.28 14.18 5,674 -
8 Column Shuttering Sqm 10.4 546.35 10.40 5,682 -
9 Slab Shuttering Sqm 4.41 484.04 4.41 2,135 -
10 Plinth Beam,Column,Beam & Slab Steelwork Kg 204.25 82.07 204.25 16,763 -
11 AAC Blockwok Cum 1.194 9327 1.19 11,136 -
12 Ceiling Plastering Sqm 4.41 184.64 4.41 814 -
13 Internal Plastering Sqm 23.75 204.85 23.75 4,865 -
14 External Plastering Sqm 23.75 236.86 23.75 5,625 -
68,923 - 68,923
Stilt Floor
2 Toilet Floor sqm 12.2 1076.55 36.60 39,402 -
3 Toilet Walls sqm 90 1146.78 90.00 103,210 -
3 GSB Filling M3 10 2905 10.00 29,050 -
4 Paver Block Laying 60 mm Sqm 150 825.44 150.00 123,816 -
8 Granite Works Sqm 138 5355.88 138.00 739,111 -
Total 1,034,589 - 295,478
OTHER WORKS - -
3 Handrail fabrication & fixing - Substation kg 450 143.51 450.00 64,580 -
FRP Louveres Sqm 215 2021 215 434,515 -
Terrace Ladder Works kg 1500 143.51 1,500.00 215,265 -
compount wall railing kg 1700 123 1,700.00 209,100 - -
TOTAL FOR OTHER WORKS 923,460 - 499,095
FIRE FIGHTING
Fire Hydrant System ,External/Internal 500,000 500,000
Fire Sprinkler at Stilt floor 200,000 200,000
Fire pump panel
Fire pump room piping 100,000 100,000
-
Total Fire Fighting works 800,000 - 800,000
SL NO DESCRIPTION UNIT
AGT
Slab @ 7.6EL - 200mm thick
RCC M 30 M3
Staircase (STP & AGT)
1 RCC M 30 M3
staircase slab concreting
staircasec1 column 4 nos
staircasec beam rcc
2 Reinforcement works kg
stair column steel
3 Shuttering works M2
shuttering works stair
column 4 nos
Slab @ 2.6EL - 200mm thick
RCC M 30 M3
Reinforcement works kg
Shuttering works M2
Wall
RCC M 30 M3
Reinforcement works kg
Shuttering works M2
terrace kerb shuttering
pcc
PCC M3
Mumty slab at 11.5EL
Column RCC Works M3
Shuttering works M2
Reinforcement work kg
RCC works SLAB M3
Total
Substation
Parapet wall @ 13.55EL & Other works
1 Blockwork cum
6 IPS Flooring (Transformer Panel Room) sqm
7 AAC Blockwork cum
8 Earth Filling cum
stp back filling
AGT back filling
9 Anti Termite Treatement Sqm
10 HDPE Sheet laying Sqm
11 Raft Slab Steel Kg
12 Raft Slab RCC cum
shade rcc
13 Rolling Shutter Fixing sqm
14 Ball Bearing Hinges for Rolling Shutter NO:
15 Extra for Providing Grilled Rolling Shutters sqm
16 shuttering m2
parapet kerb
17 Excavation m3
20 External Plastering sqm
Total
STP
Wall lift upto 3.2EL
Wall lift -1- 3.4 EL to 5.8 EL
1 RCC M 30 M3
wall
stp column concreting
Wall lift -2- 5.8 EL to 7.4 EL
1 RCC M 30 M3
wall
2 Reinforcement works kg
3 Shuttering works M2
Slab @ 7.4EL - 200mm thick
1 RCC M 30 M3
2 Reinforcement works kg
3 Shuttering works M2
Mumty slab at 11.5EL
Column RCC Works M3
Shuttering works M2
Reinforcement work kg
RCC works M3
FINISHING WORKS
AAC Blockwork (AGT/STP Mumty Floor) M3
Total
Drain work
1 RCC M 25 M3
External drain -wall
2 Excavation M3
Man hole
3 PCC M3
kerb stone pcc
Man hole
4 Shuttering works M2
External drain
5 Reinforcement works Kg
Total
Road work
1 Backfilling M3
2 GSB Filling M3
3 Kerb Stone M3
Stilt Floor
Anti Termite Treatement Sqm
HDPE SHEET LAYING Sqm
GSB Filling M3
Paver Block Laying 60 mm Sqm
Lobby Grade Slab PCC Cum
Lobby Grade Slab RCC Cum
duct slab rcc
Grade slab Steelwork Kg
Granite Works Sqm
Internal Plastering Sqm
Total
Painting
Tower 1
1 External Cement primer sqm
2 External Texture coat 1 sqm
Total
OTHER WORKS
3 Handrail fabrication & fixing - Substation kg
MEP
Electrical works
1 Testing & Commissioning of Lifts Ls
2 Testing & Commissioning of 56 Flats Ls
3 Street Light fixing - Supply & Fixing Ls
FIRE FIGHTING
Fire Hydrant System ,External/Internal
Fire Sprinkler at Stilt floor
TARGETED TARGETED
RATE ACHIEVED TILL NOW 24.06.2019
QUANTITY AMOUNT
QTY AMOUNT %
5 7042 35,210
6 7480 44,880 -
403 733.67 295,669
5 9327 46,635 5 46,635.00
100 273.75 27,375 90 24,637.50
65
25
356.3 110.45 39,353
356.3 133 47,388
5600 82.07 459,592
56 7973.7 446,527 2.3 18,339.51
2.3
46.8 2936.18 137,413
14 601.67 8,423
14.04 429.86 6,035
15 400.28 6,004 4.5 1,801.26
4.5
10 187.5 1,875
200 236.86 47,372 120 28,423.20
120
1,614,544 119,836
4,169,497 2,172,087
12,556,771 1,810,384
6,952,589 1,087,876
10,510,095 51,700
4,000,000 3,600,000
2,000,000
600,000
1,600,000
400,000 250,000
1,500,000
2,000,000 2,000,000
900,000 900,000
400,000
200,000 #REF!
500,000 #REF!
85,000
14,100,000 #REF!
3,000,000
1,600,000 #REF!
1,700,000
660,000 #REF!
6,960,000 #REF!
1,500,000 #REF!
200,000 #REF!
1,700,000 #REF!
8,660,000 #REF!
22,760,000 #REF!
65,704,786 #REF!
KMRL STAFF QUARTERS
TARGET/ BUDGET FOR THE MONTH OF SEPTEMBER 2019
SL NO DESCRIPTION UNIT RATE PLAN FOR SEPTEMBER PRODUCTION UP TO 30.08.2019
Plan up to 15/08/2019
Target AMOUNT Target AMOUNT % Amounts
AGT
5 Internal primer sqm 49.14 80.00 3,931 -
6 internal Emulsion 1st coat - sqm 36.4 80.00 2,912 -
7 internal Emulsion 2nd coat - sqm 38.95 80.00 3,116 -
8 External painting sqm 200.74 250.00 50,185 -
Total 60,144 - 60,144
Substation - -
Parapet wall @ 13.55EL & Other works - -
1 Blockwork cum 7480 4.00 29,920 - #REF!
2 IPS Flooring (Transformer Panel Room) sqm 733.67 403.00 295,669 -
3 Earth Filling cum 273.75 25.00 6,844 -
4 Anti Termite Treatement Sqm 110.45 325.3 35,929 -
5 HDPE Sheet laying Sqm 133 325.3 43,265 - #REF!
13 Internal primer sqm 49.14 403.00 19,803 -
14 internal Emulsion 1st coat - sqm 36.4 400.00 14,560 -
15 internal Emulsion 2nd coat - sqm 38.95 400.00 15,580 -
16 External Painting sqm 200.74 800.00 160,592 -
primer only sqm 80.296 -
Total 622,162 - 622,162 #REF!
STP - -
FINISHING WORKS - - - pcc sw line 4 m3
14 internal Emulsion 1st coat - sqm 36.4 120.00 4,368 -
15 internal Emulsion 2nd coat - sqm 38.95 120.00 4,674 -
16 External Painting sqm 200.74 180.00 36,133 -
Total 45,175 - 45,175 #REF!
#REF!
#REF!
Drain work
1 RCC M 25 M3 7973 31.00 247,163 #REF!
2 Excavation,fire line M3 187.5 25.00 4,688
3 PCC drain, sw line, kerbstone, plumb line M3 7042 4.00 28,168
4 Shuttering works M2 484 50.00 24,200
5 Reinforcement works Kg 82.07 1000 82,070 - -
Total 386,289 - 193,144.25
Road work
1 Backfilling M3 273.75 438.00 119,903 - 119,903 #REF!
2 GSB Filling M3 2905 617.00 1,792,385 - 896,192.50
3 Kerb Stone M3 7259.1 9.49 68,889 - 68,889
4 Paver Block Laying 100 mm M2 1276 2,500.00 3,190,000 - 797,500.00
5 Paver Block Laying 60 mm M2 825.44 800.00 660,352 - 660,352 198
Total 5,831,528 - 2,542,836 144
108
450
Piling/Raft foundation/ Column work for compound wall - - #REF!
RCC WORKS - - 0.027
2 Earthwork Excavation cum 187.52 10 1,875 -
3 Pile Cap & Pile Cap Beam PCC cum 7042.44 1.927 13,571 -
4 Pile Cap & Pile Cap Beam Concrete cum 7973.7 10.96 87,392
5 Tie Beam RCC, beam near gate cum 7973.7 5 39,869 31.5
6 Retaining Wall/Column RCC cum 7973.7 8 63,790 16
7 Raft foundation shuttering sqm 236 134.91 31,839 15
8 Column for compound wall concrete cum 7685 2 15,370 15
9 Column for compound wall shuttering , pile cap sqm 484 22.22 10,754 31.5
10 AAC Blockwork cum 9327 12.56 117,147 16
11 Steel reinforcement works kg 82.07 3327 273,047 125
12 Plastering works sqm 204 140 28,560
13 Grill works kg 123.5 1200 148,200
14 Compound Wall Primer Sqm 28.4 331.2 9,406
15 north side Gate Kg 123.5 750.00 92,625
Total 933,444 - 700,083.12 #REF!
Guard Room - -
2 Grade Slab RCC Cum 7192.12 0.50 3,596 -
4 Beam RCC Cum 7973.7 0.76 6,028 -
5 Slab RCC Cum 7973.7 0.66 5,275 -
6 Lintel & Shade RCC Cum 7973.7 0.22 1,754 -
7 Beam Shuttering Sqm 400.28 8.00 3,202 -
9 Slab Shuttering Sqm 484.04 4.41 2,135 -
10 Plinth Beam,Column,Beam & Slab Steelwork Kg 82.07 300.00 24,621 -
11 AAC Blockwok Cum 9327 1.60 14,923
12 Ceiling Plastering Sqm 184.64 4.41 814 -
13 Internal Plastering Sqm 204.85 23.75 4,865 -
14 External Plastering Sqm 236.86 23.75 5,625 -
72,839 - 72,839
Stilt Floor
3 GSB Filling M3 2905 10.00 29,050 - #REF! #REF!
4 Paver Block Laying 60 mm Sqm 825.44 150.00 123,816 -
Total 152,866 - #REF!
FIRE FIGHTING
-
Testing and commissioning balance 25% claim 1,000,000 1,000,000
-
Total Fire Fighting works 1,000,000 - 1,000,000
. -
pump room drain cover 200 kg
150kg -
240.64 240.64
4.5
9
9
9
KMRL STAFF QUARTERS
TARGET/ BUDGET FOR THE MONTH OF AUGUST 2019
TARGETED
SL NO DESCRIPTION UNIT QUANTITY for RATE
completion
Plan up to 15/08/2019
AMOUNT Amounts
AGT
Stilt Floor
2 Toilet Floor sqm 1076.55 -
3 Toilet Walls sqm 1146.78 -
3 GSB Filling M3 2905 - #REF! #REF!
4 Paver Block Laying 60 mm Sqm 825.44 -
8 Granite Works Sqm 5355.88 -
FINISHING WORKS - 81
Flooring - 72
Tower 1 - #REF! 153
1 Common Wash Dado (10 to 14th floor) sqm 1146.78 - #REF!
2 Staircase flooring (Main stair) sqm 1927.12 -
2 Staircase flooring (Fire Stair -Gf to 4th Floor) sqm 1927.12 -
3 Staircase Skirting (Fire Stair - Gf to 4th floor) sqm 1940.09 -
6 Lift wall cladding (Granite ) 1 st floor to 14th floor sqm 4908 - 1.1
1 to 13th floor -
Stilt floor -
6 Lift wall cladding (Vitrified Tile )1st floor to 14th floor sqm 1146.78 - 1.1
1 to 13th floor -
Stilt floor -
Tower 2 - 6
1 Common Wash Dado -2nd floor(ABCD) sqm 1146.78 - 3.3428
2 Toilet Floor ( 2 Flats) 8a, 12 a sqm 1076.55 - 4.4428
3 Toilet Walls ( 2 Floors) 8A, 12 A sqm 1146.78 -
4 Staircase flooring (Mainstair) sqm 1927.12 - 2.7735
4 Staircase flooring ( Fire Stair - GF TO 7 th Floors) sqm 1927.12 - 2.7735
5 Staircase Skirting ( Fire Stair - GF TO 7 th Floors) sqm 1940.09 - 4.2
6 Lift wall cladding (Granite ) 1 st floor to 14th floor sqm 4908 -
1 to 13th floor -
Stilt floor -
7 Lift wall cladding (Vitrified Tile )1st floor to 14th floor sqm 1146.78 -
1 to 13th floor -
Stilt floor -
- - #REF!
Painting -
Tower 1 -
3 Internal painting(Putty - 1st coat) sqm 53.2 - #REF!
main stair area -
Fire stair area -
4 Internal painting(Putty - 2nd coat) flat 2C,D sqm 98.9 - #REF!
2 External Texture coat 1 sqm 75.8 -
5 Internal primer apartment area ( 2 FLAT 2,CD) sqm 49.14 -
6 Emulsion 1st coat - apartment (2 flat 2CD) sqm 36.4 -
7 Emulsion 2nd coat - apartment (55Flats Ceiling) sqm 38.95 -
8 Internal painting(Putty - 2nd coat)- Lobby - 2nd floor sqm 98.9 -
main stair area -
9 Internal primer lobby area - 14 floors 2nd floor (1, 3-14 90%completed) sqm 49.14 -
10 Enamel painting sqm 34.6 -
Door frame 13 floors 80% -
Tower 2 -
2 External Texture coat 1 sqm 75.8 -
4 Internal painting(Putty - 1st coat) sqm 53.2 - #REF!
main stair area -
4 Internal painting(Putty - 1st coat) main stair sqm 98.9 - #REF!
4 Internal painting(Putty - 2nd coat) 2,14 sqm 98.9 -
5 External primer 1st coat sqm 49.14 -
5 Internal primer apartment area ( 2,&14th floor) sqm 49.14 -
14th floor B,D completed, A 50%, C 60% -
6 Emulsion 1st coat - apartment ( 2,&14th floor) sqm 36.4 -
7 Emulsion 2nd coat - apartment (55Flats Ceiling) sqm 39.0 -
8 Internal painting(Putty - 2nd coat)- Lobby - 2nd, 6-10th , & 14th 60% sqm 98.9 -
main stair area -
9 Internal primer lobby area - 2nd to 10th ,13-14 sqm 49.1 -
10 Enamel painting sqm 34.6 -
Door frame 3 to 7 floors 80% -
- - #REF!
Other Finishing works -
Tower 1 & 2 -
1 Aluminium works - Balance kg 517 - -
stair side -
2 Aluminium Works - Door Shutters - Balance kg 597 - -
3 Aluminium louver works - Balance sqm 1967 - - #REF!
4 Aluminum hardware fixing 20 flat LS - -
5 S/F glass for Al Windows sqm 1095 - -
6 Mosquito net fixing m2 737.85 - -
7 Grill works Kg 160 - -
8 Shaft Door m2 4213 - 1800000
Tower 2 - -
1 Aluminium works - Balance kg 517 - -
stair side -
2 Aluminium Works - Door Shutters - Balance kg 597 - -
3 Aluminium louver works - Balance sqm 1967 - -
4 Aluminum hardware fixing 20 flat LS - -
5 S/F glass for Al Windows sqm 1095 - -
6 Grill works Kg 160 - -
7 Mosquito net fixing m2 737.85 - - 6188915
8 Shaft Door m2 4213 - 1800000
- 50.4 4388915
- 29.7
- 20.7
Total - -
-
OTHER WORKS -
3 Handrail fabrication & fixing - Substation kg 143.51 -
4 Handrail fabrication & fixing - T1 fire stair kg 143.51 -
5 Water proofing Works Tower 1 sqm 1102.5 -
6 Water proofing Works Tower 2 sqm 1102.5 -
7 Fire Door & shaft door - Tower 1 -
8 Fire Door & shaft door - Tower 2 -
9 FRP Louveres Sqm 2021 -
10 Terrace Ladder Works kg 143.51 - -
11 compount wall railing kg 123 - - -
TOTAL FOR OTHER WORKS - -
#REF!
TOTAL FOR FINISHING WORKS - 101
MEP
Electrical works
1 Testing & Commissioning of Lifts Ls
2 Testing & Commissioning of 56 Flats Ls
3 Street Light fixing - Supply & Fixing/Gate Light Ls
4 Testing & Commissioning of Panel Boards/LT/HT Ls 29316460
5 External Earthing works Ls 23176682
7 Common Area Lighting+Balance Fans Ls 4130748
8 LT & HT Cables,& termination Ls #REF! 56623890
DG - Supply Ls
Testing & Commissioning of Transformer Ls 32476682
Cable Tray - Substation Ls 9300000
Fire Alarm Works Ls 23176682
DB - at 1st floor T!&T2 Ls
DB Fixing at Substation Ls 250000
Light Fixtures at Substation Ls 187500
Laying of GI Strip 25*6 mm/Copper strip Ls
Laying of 95 mm cable Ls
Laying of 300 mm cable Ls
Laying of 240 mm cable Ls
Laying of 10 sq mm cable Ls 90
4Cx 10 sq.mm cable Ls 90
angle Ls
Circuting wiring Ls
Earth pit Ls
2 Testing & Commissioning of DG with exhaust valve and fuel tank Ls
UPS Instalation
D AT SUBSTATION AND AGT
FIRE FIGHTING
Fire Hydrant System ,External/Internal -
Fire Sprinkler at Stilt floor -
Fire fighting pump & equipments
Fire pump room piping -
150 MM GI pipe - Substation and main gate area
-
Total Fire Fighting works - -
.
pump room drain cover 200 kg
150kg #REF!
240.64 240.64
KMRL STAFF QUARTERS
TARGET/ BUDGET FOR THE MONTH OF AUGUST 2019
TARGETED
SL NO DESCRIPTION UNIT QUANTITY RATE PLAN FOR AUGUST PRODUCTION UP TO 30.08.2019
Plan up to 15/08/2019
Target AMOUNT Target AMOUNT % Amounts
AGT
1 Shuttering works kerb/ parapet belt shuttering/Lintel&shade M2 20 484.04 20.00 9,681 20.00 9,681
2 , parapet belt concrete/Lintel&shade m3 3 7973.7 3.00 23,921 4.95 39,470
4 External plastering M2 140 236.86 140.00 33,160 350.00 82,901 #REF!
5 Internal primer sqm 80 49.14 80.00 3,931 -
6 internal Emulsion 1st coat - sqm 80 36.4 80.00 2,912 -
7 internal Emulsion 2nd coat - sqm 80 38.95 80.00 3,116 -
8 External painting sqm 250 200.74 250.00 50,185 -
Total 126,907 132,052 126,907
Substation - -
Parapet wall @ 13.55EL & Other works - -
1 Blockwork cum 4 7480 4.00 29,920 - #REF!
2 IPS Flooring (Transformer Panel Room) sqm 163 733.67 403.00 295,669 -
3 Earth Filling cum 100 273.75 25.00 6,844 -
4 Anti Termite Treatement Sqm 325.3 110.45 325.3 35,929 -
5 HDPE Sheet laying Sqm 325.3 133 325.3 43,265 - 5,302,422
6 Raft Slab Steel Kg 5600 82.07 3,953
7 Raft Slab RCC cum 56 7973.7 38.75
8 Rolling Shutter Fixing sqm 46.8 2936.18 46.8 137,413 28.80 84,562
9 Ball Bearing Hinges for Rolling Shutter NO: 14 601.67 14 8,423 8.000 4,813
10 Extra for Providing Grilled Rolling Shutters sqm 14.04 429.86 14.04 6,035 14.04 6,035
11 Excavation m3 10 187.5 3.00 563 -
12 External Plastering sqm 50 236.86 50.00 11,843 118.00 27,949
13 Internal primer sqm 45 49.14 45.00 2,211 -
14 internal Emulsion 1st coat - sqm 45 36.4 80.00 2,912 -
15 internal Emulsion 2nd coat - sqm 45 38.95 80.00 3,116 -
16 External Painting sqm 140 200.74 50.00 10,037 -
primer only sqm 80.296 - 350.00 28,104 40% of 200.4
Total 594,181 151,464 594,181 #REF!
STP - -
1 Shuttering works M2 30 484.04 30.00 14,521 30.00 14,521
2 Reinforcement work kg 160 82.07 160.00 13,131 160.00 13,131
3 RCC works , parapet belt M3 2 7973.7 2.00 15,947 2.90 23,124
FINISHING WORKS - - - pcc sw line 4 m3
1 AAC Blockwork (AGT/STP Mumty Floor) M3 9 9327 9.00 83,943 8.80 82,078
14 External Plastering sqm 160 236.86 160.00 37,898 395.00 93,560
14 internal Emulsion 1st coat - sqm 120 36.4 120.00 4,368 -
15 internal Emulsion 2nd coat - sqm 120 38.95 120.00 4,674 -
16 External Painting sqm 160 200.74 160.00 32,118 -
Total 206,601 226,413 206,601 #REF!
#REF!
Total for AGT/STP/SS 927,688 509,929 6,230,110 33
307791
Drain work
1 RCC M 25 M3 57.181 7973 38.15 304,146 26.65 212,480 #REF!
2 Excavation,fire line M3 94.518 187.5 94.52 17,722 52.00 9,750
3 PCC drain, sw line, kerbstone, plumb line M3 25 7042 25.00 176,050 8.85 62,322
4 Shuttering works M2 320.2136 484 213.62 103,394 197.23 95,459
5 Reinforcement works Kg 5146.29 82.07 3433.23 281,765 2,398.50 196,845
Gratings -pump room Kg 110 350.00 38,500
Total 883,077 615,356 441,538.49
Road work
1 Backfilling M3 474 273.75 474.00 129,758 36.00 9,855 129,758 #REF!
2 GSB Filling M3 673 2905 673.00 1,955,065 56.00 162,680 977,532.50
3 Kerb Stone M3 10.44 7259.1 10.44 75,785 0.95 6,860 75,785
4 Paver Block Laying 100 mm M2 3472 1276 3,472.00 4,430,272 670.00 854,920 1,107,568.00
5 Paver Block Laying 60 mm M2 1024 825.44 1,024.00 845,251 310.00 255,886 845,251 198
Total 7,436,130 1,290,201 3,135,894 144
108
450
Piling/Raft foundation/ Column work for compound wall - - #REF!
RCC WORKS - - 0.027
2 Earthwork Excavation cum 10 187.52 10 1,875 -
3 Pile Cap & Pile Cap Beam PCC cum 1.927 7042.44 1.927 13,571 -
4 Pile Cap & Pile Cap Beam Concrete cum 10.96 7973.7 10.96 87,392 -
5 Tie Beam RCC, beam near gate cum 13.02 7973.7 13.02 103,818 0.8 6,379 31.5
6 Retaining Wall/Column RCC cum 8.02 7973.7 13.02 103,818 0.8 - 16
7 Raft foundation shuttering sqm 85.41 236 134.91 31,839 - 15
8 Column for compound wall concrete cum 2 7685 2 15,370 1.2 9,222 15
9 Column for compound wall shuttering , pile cap sqm 22.22 484 22.22 10,754 16 7,744 31.5
10 AAC Blockwork cum 12.56 9327 12.56 117,147 - 16
11 Steel reinforcement works kg 3327.68 82.07 3327 273,047 175 14,362 125
12 Plastering works sqm 140 204 140 28,560 142 28,968
13 Grill works kg 1200 123.5 1200 148,200 -
14 Compound Wall Primer Sqm 331.2 28.4 331.2 9,406 -
15 Compound Wall Gate Kg 1500 123.5 1,500.00 185,250 1,500.00 185,250
Total 1,130,046 251,925 847,534.66 #REF!
Guard Room - -
2 Grade Slab RCC Cum 0.441 7192.12 0.44 3,172 -
3 Column RCC Cum 0.72 7973.7 - 0.90 7,176 (4,222)
4 Beam RCC Cum 0.756 7973.7 0.76 6,028 0.76 6,060
5 Slab RCC Cum 0.6615 7973.7 0.66 5,275 0.66 5,263
6 Lintel & Shade RCC Cum 0.22 7973.7 0.22 1,754 0.22 1,754
7 Beam Shuttering Sqm 14.175 400.28 14.18 5,674 14.18 5,676
8 Column Shuttering Sqm 10.4 546.35 10.40 5,682 10.40 5,682
9 Slab Shuttering Sqm 4.41 484.04 4.41 2,135 4.41 2,135
10 Plinth Beam,Column,Beam & Slab Steelwork Kg 204.25 82.07 204.25 16,763 204.25 16,763
11 AAC Blockwok Cum 1.194 9327 1.19 11,136 1.80 16,789
12 Ceiling Plastering Sqm 4.41 184.64 4.41 814 -
13 Internal Plastering Sqm 23.75 204.85 23.75 4,865 -
14 External Plastering Sqm 23.75 236.86 23.75 5,625 -
68,923 67,297 68,923
Stilt Floor
2 Toilet Floor sqm 12.2 1076.55 36.60 39,402 -
3 Toilet Walls sqm 90 1146.78 90.00 103,210 30.00 34,403
3 GSB Filling M3 10 2905 10.00 29,050 - 3,881,842 #REF!
4 Paver Block Laying 60 mm Sqm 150 825.44 150.00 123,816 -
8 Granite Works Sqm 138 5355.88 138.00 739,111 64.45 345,186
Total 1,034,589 379,590 295,478
OTHER WORKS - -
3 Handrail fabrication & fixing - Substation kg 450 143.51 450.00 64,580 -
4 Handrail fabrication & fixing - T1 fire stair kg 143.51 - -
5 Water proofing Works Tower 1 sqm 1102.5 - -
6 Water proofing Works Tower 2 sqm 1102.5 - -
7 Fire Door & shaft door - Tower 1 - -
8 Fire Door & shaft door - Tower 2 - -
9 FRP Louveres Sqm 215 2021 215 434,515 -
10 Terrace Ladder Works kg 1500 143.51 1,500.00 215,265 - 12,821,837
11 compount wall railing kg 1700 123 1,700.00 209,100 - - -
TOTAL FOR OTHER WORKS 923,460 - 499,095
#REF!
TOTAL FOR FINISHING WORKS 12,821,837 3,282,525 9,063,596
MEP
Electrical works
1 Testing & Commissioning of Lifts Ls 3,600,000 3,600,000
2 Testing & Commissioning of 56 Flats Ls
3 Street Light fixing - Supply & Fixing/Gate Light Ls 706,500
4 Testing & Commissioning of Panel Boards/LT/HT Ls 1,784,264 29316460
5 External Earthing works Ls 23176682
7 Common Area Lighting+Balance Fans Ls 4130748
8 LT & HT Cables,& termination Ls #REF! 56623890
DG - Supply Ls
Testing & Commissioning of Transformer Ls 371,372 32476682
Cable Tray - Substation Ls 9300000
Fire Alarm Works Ls 466,000 23176682
DB - at 1st floor T!&T2 Ls
DB Fixing at Substation Ls 250000
Light Fixtures at Substation Ls 187500
Laying of GI Strip 25*6 mm/Copper strip Ls 500,000
Laying of 95 mm cable Ls
Laying of 300 mm cable Ls
Laying of 240 mm cable Ls
Laying of 10 sq mm cable Ls 2,300,000
90
4Cx 10 sq.mm cable Ls 90
angle Ls
Circuting wiring Ls
Earth pit Ls
2 Testing & Commissioning of DG with exhaust valve and fuel tank Ls 549,550
UPS Instalation
D AT SUBSTATION AND AGT
31
Total Plumbing works 6,100,000 2,200,000 900,000
FIRE FIGHTING
Fire Hydrant System ,External/Internal 500,000 536,000 500,000
Fire Sprinkler at Stilt floor 200,000 74,000 200,000
Fire fighting pump & equipments 400,000
Fire pump room piping 100,000 100,000
150 MM GI pipe - Substation and main gate area
-
Total Fire Fighting works 800,000 1,010,000 800,000
3,746,677 7,164,367
pump room drain cover 200 kg
150kg 7,164,367
20.08.2018 282,100
4.5
9
9
9
KMRL STAFF QUARTERS
TARGET/ BUDGET FOR THE MONTH OF AUGUST 2019
TARGETED
SL NO DESCRIPTION UNIT QUANTITY RATE PLAN FOR AUGUST PRODUCTION UP TO 30.08.2019
Plan up to 15/08/2019
Target AMOUNT Target AMOUNT % Amounts
AGT
1 Shuttering works kerb/ parapet belt shuttering/Lintel&shade M2 20 484.04 20.00 9,681 20.00 9,681
2 , parapet belt concrete/Lintel&shade m3 3 7973.7 3.00 23,921 4.95 39,470
4 External plastering M2 140 236.86 140.00 33,160 280.00 66,321 #REF!
5 Internal primer sqm 80 49.14 80.00 3,931 -
6 internal Emulsion 1st coat - sqm 80 36.4 80.00 2,912 -
7 internal Emulsion 2nd coat - sqm 80 38.95 80.00 3,116 -
8 External painting sqm 250 200.74 250.00 50,185 -
Total 126,907 115,471 126,907
Substation - -
Parapet wall @ 13.55EL & Other works - -
1 Blockwork cum 4 7480 4.00 29,920 - #REF!
2 IPS Flooring (Transformer Panel Room) sqm 163 733.67 403.00 295,669 -
3 Earth Filling cum 100 273.75 25.00 6,844 -
4 Anti Termite Treatement Sqm 325.3 110.45 325.3 35,929 -
5 HDPE Sheet laying Sqm 325.3 133 325.3 43,265 - 5,095,514
6 Raft Slab Steel Kg 5600 82.07 3,953
7 Raft Slab RCC cum 56 7973.7 38.75
8 Rolling Shutter Fixing sqm 46.8 2936.18 46.8 137,413 28.80 84,562
9 Ball Bearing Hinges for Rolling Shutter NO: 14 601.67 14 8,423 8.000 4,813
10 Extra for Providing Grilled Rolling Shutters sqm 14.04 429.86 14.04 6,035 14.04 6,035
11 Excavation m3 10 187.5 3.00 563 -
12 External Plastering sqm 50 236.86 50.00 11,843 118.00 27,949
13 Internal primer sqm 45 49.14 45.00 2,211 -
14 internal Emulsion 1st coat - sqm 45 36.4 80.00 2,912 -
15 internal Emulsion 2nd coat - sqm 45 38.95 80.00 3,116 -
16 External Painting sqm 140 200.74 50.00 10,037 -
primer only sqm 80.296 - 350.00 28,104 40% of 200.4
Total 594,181 151,464 594,181 #REF!
STP - -
1 Shuttering works M2 30 484.04 30.00 14,521 30.00 14,521
2 Reinforcement work kg 160 82.07 160.00 13,131 160.00 13,131
3 RCC works , parapet belt M3 2 7973.7 2.00 15,947 2.90 23,124
FINISHING WORKS - - - pcc sw line 4 m3
1 AAC Blockwork (AGT/STP Mumty Floor) M3 9 9327 9.00 83,943 8.80 82,078
14 External Plastering sqm 160 236.86 160.00 37,898 315.00 74,611
14 internal Emulsion 1st coat - sqm 120 36.4 120.00 4,368 -
15 internal Emulsion 2nd coat - sqm 120 38.95 120.00 4,674 -
16 External Painting sqm 160 200.74 160.00 32,118 -
Total 206,601 207,465 206,601 #REF!
#REF!
Total for AGT/STP/SS 927,688 474,400 6,023,202 33
307791
Drain work
1 RCC M 25 M3 57.181 7973 38.15 304,146 26.65 212,480 #REF!
2 Excavation,fire line M3 94.518 187.5 94.52 17,722 52.00 9,750
3 PCC drain, sw line, kerbstone, plumb line M3 25 7042 25.00 176,050 8.85 62,322
4 Shuttering works M2 320.2136 484 213.62 103,394 197.23 95,459
5 Reinforcement works Kg 5146.29 82.07 3433.23 281,765 2,398.50 196,845
Gratings -pump room Kg 110 350.00 38,500
Total 883,077 615,356 441,538.49
Road work
1 Backfilling M3 474 273.75 474.00 129,758 36.00 9,855 129,758 #REF!
2 GSB Filling M3 673 2905 673.00 1,955,065 56.00 162,680 977,532.50
3 Kerb Stone M3 10.44 7259.1 10.44 75,785 0.95 6,860 75,785
4 Paver Block Laying 100 mm M2 3472 1276 3,472.00 4,430,272 670.00 854,920 1,107,568.00
5 Paver Block Laying 60 mm M2 1024 825.44 1,024.00 845,251 310.00 255,886 845,251 198
Total 7,436,130 1,290,201 3,135,894 144
108
450
Piling/Raft foundation/ Column work for compound wall - - #REF!
RCC WORKS - - 0.027
2 Earthwork Excavation cum 10 187.52 10 1,875 -
3 Pile Cap & Pile Cap Beam PCC cum 1.927 7042.44 1.927 13,571 -
4 Pile Cap & Pile Cap Beam Concrete cum 10.96 7973.7 10.96 87,392 -
5 Tie Beam RCC, beam near gate cum 13.02 7973.7 13.02 103,818 0.8 6,379 31.5
6 Retaining Wall/Column RCC cum 8.02 7973.7 13.02 103,818 0.8 - 16
7 Raft foundation shuttering sqm 85.41 236 134.91 31,839 - 15
8 Column for compound wall concrete cum 2 7685 2 15,370 1.2 9,222 15
9 Column for compound wall shuttering , pile cap sqm 22.22 484 22.22 10,754 16 7,744 31.5
10 AAC Blockwork cum 12.56 9327 12.56 117,147 - 16
11 Steel reinforcement works kg 3327.68 82.07 3327 273,047 175 14,362 125
12 Plastering works sqm 140 204 140 28,560 142 28,968
13 Grill works kg 1200 123.5 1200 148,200 -
14 Compound Wall Primer Sqm 331.2 28.4 331.2 9,406 -
15 Compound Wall Gate Kg 1500 123.5 1,500.00 185,250 1,500.00 185,250
Total 1,130,046 251,925 847,534.66 #REF!
Guard Room - -
2 Grade Slab RCC Cum 0.441 7192.12 0.44 3,172 -
3 Column RCC Cum 0.72 7973.7 - 0.90 7,176 107,279
4 Beam RCC Cum 0.756 7973.7 0.76 6,028 -
5 Slab RCC Cum 0.6615 7973.7 0.66 5,275 -
6 Lintel & Shade RCC Cum 0.22 7973.7 0.22 1,754 -
7 Beam Shuttering Sqm 14.175 400.28 14.18 5,674 -
8 Column Shuttering Sqm 10.4 546.35 10.40 5,682 -
9 Slab Shuttering Sqm 4.41 484.04 4.41 2,135 -
10 Plinth Beam,Column,Beam & Slab Steelwork Kg 204.25 82.07 204.25 16,763 -
11 AAC Blockwok Cum 1.194 9327 1.19 11,136 1.80 16,789
12 Ceiling Plastering Sqm 4.41 184.64 4.41 814 -
13 Internal Plastering Sqm 23.75 204.85 23.75 4,865 -
14 External Plastering Sqm 23.75 236.86 23.75 5,625 -
68,923 23,965 68,923
Stilt Floor
2 Toilet Floor sqm 12.2 1076.55 36.60 39,402 -
3 Toilet Walls sqm 90 1146.78 90.00 103,210 30.00 34,403
3 GSB Filling M3 10 2905 10.00 29,050 - 3,544,784 #REF!
4 Paver Block Laying 60 mm Sqm 150 825.44 150.00 123,816 -
8 Granite Works Sqm 138 5355.88 138.00 739,111 64.45 345,186
Total 1,034,589 379,590 295,478
OTHER WORKS - -
3 Handrail fabrication & fixing - Substation kg 450 143.51 450.00 64,580 -
4 Handrail fabrication & fixing - T1 fire stair kg 143.51 - -
5 Water proofing Works Tower 1 sqm 1102.5 - -
6 Water proofing Works Tower 2 sqm 1102.5 - -
7 Fire Door & shaft door - Tower 1 - -
8 Fire Door & shaft door - Tower 2 - -
9 FRP Louveres Sqm 215 2021 215 434,515 -
10 Terrace Ladder Works kg 1500 143.51 1,500.00 215,265 - 12,821,837
11 compount wall railing kg 1700 123 1,700.00 209,100 - - -
TOTAL FOR OTHER WORKS 923,460 - 499,095
#REF!
TOTAL FOR FINISHING WORKS 12,821,837 1,971,875 9,063,596
MEP
Electrical works
1 Testing & Commissioning of Lifts Ls 3,600,000 3,600,000
2 Testing & Commissioning of 56 Flats Ls
3 Street Light fixing - Supply & Fixing/Gate Light Ls 706,500
4 Testing & Commissioning of Panel Boards/LT/HT Ls 1,784,264 29316460
5 External Earthing works Ls 23176682
7 Common Area Lighting+Balance Fans Ls 4130748
8 LT & HT Cables,& termination Ls #REF! 56623890
DG - Supply Ls
Testing & Commissioning of Transformer Ls 371,372 32476682
Cable Tray - Substation Ls 9300000
Fire Alarm Works Ls 466,000 300,000 23176682
DB - at 1st floor T!&T2 Ls
DB Fixing at Substation Ls 250000
Light Fixtures at Substation Ls 187500
Laying of GI Strip 25*6 mm/Copper strip Ls 500,000 299,813
Laying of 95 mm cable Ls
Laying of 300 mm cable Ls
Laying of 240 mm cable Ls
Laying of 10 sq mm cable Ls 90
4Cx 10 sq.mm cable Ls 200,000 90
angle Ls
Circuting wiring Ls
Earth pit Ls
2 Testing & Commissioning of DG with exhaust valve and fuel tank Ls 549,550 400,000.00
UPS Instalation 191,000
D AT SUBSTATION AND AGT 200,000
FIRE FIGHTING
Fire Hydrant System ,External/Internal 500,000 536,000 500,000
Fire Sprinkler at Stilt floor 200,000 74,000 200,000
Fire fighting pump & equipments 400,000
Fire pump room piping 100,000 100,000
150 MM GI pipe - Substation and main gate area
-
Total Fire Fighting works 800,000 1,010,000 800,000
. 5,516,659
pump room drain cover 200 kg
150kg 5,516,659
20.08.2018 282,100
4.5
9
9
9