Coal Fired Power Plant Project Proposal
Coal Fired Power Plant Project Proposal
Coal Fired Power Plant Project Proposal
1. Bidders are invited to submit a complete tender for the installation of new coal
fired power plant project include auxiliaries, other facilities and services as
stipulated in the Bidder scope of work and supply at PT “X” Mill located at
(unknown), Indonesia. The bidders are expected to offer the project to PT “X” in
the scheme of “Turnkey Project” according to the condition, to be set up in the
agreement.
2. The new plant consist of Raw water intake (sea/river/ground water),
Demineralized plant, Boiler Plant, Steam turbine and other facilities)
3. Demineralized Plant specification & performance requirements.
6. The project requirements of this tender should basically covering the following
aspects :
Other facilities.
Hydrant system (min. 12 pcs) & fire prevention system
included with booster pump.
Lighting & lighting protection
Sewer and drainage
Telephone & intercome system
Laboratory equipment (Coal analyzer)
Mechanical, electrical & instrument tool kits
Air conditioning system.
Wind speed & direction monitoring.
Lightening protection.
6.2. Since the mill be operated whole year around, back up for spare
parts has to be considered accurately to secure the availability and
operational reliability.
6.3 Term of Payment
- 10% (ten percent) of total contract price as a down payment
will be paid after contract signing
- 85% (eighty five) percent of total contract price will be paid
after bidder receive Final Acceptance Certificate issued by PT
“X”
- 5% (five) percent of total contract price will be paid after end
of warranty period
PT “X” will cover amount of 90% (ninety percent) of total contract
price with Guarantee Bank or Local L/C at the contract signing