PROPOSED 96.5 sqm.

BUNGALOW HOUSE
SUMMARY FOR CIVIL WORKS
CONCRETING REINFORCEMENT
TOTAL VOLUME CEMENT SAND GRAVEL 10 mm 12 mm 16 mm 20 mm TIE WIRE # 16
BEAM 4.2 38 2.1 4.2 80 64 11.2
COLUMN 4.75 43 2.4 4.8 76 109 16.9
SLAB ON GRADE 13.78 104 6.9 13.8 70 15
WALL FOOTING 1.5 14 0.8 1.5 26 3.8
FOOTING 1.82 17 1 1.9 48 9.2

MASONRY (CHB) 3131 138 7.7 151 12

TOTAL 26.05 354 20.9 26.2 307 96 221 0 68.1


WEIGHT 1135.662 kgs 511.3809 kgs 2092.8737 kgs 0 68.1

PRICES 220 1400 1500 140 160 360 65


COSTS 77880 29260 39300 42980 15360 79560 0 4426.5
TOTAL MATERIAL COSTS Php= 288766.5