Professional Documents
Culture Documents
Hiway Assignment
Hiway Assignment
UBGMRW-20-M
1
Contents
List of tables, figures and graphs .......................................................................................... 3
Introduction ........................................................................................................................... 4
Project description ................................................................................................................ 5
The most critical one kilo meter section of the road ........................................................... 5
Location ................................................................................................................................ 6
Existing condition of the road ................................................................................................ 6
Solutions recommended for the issues that were identified. ................................................ 10
Design criteria ..................................................................................................................... 12
Capacity design .................................................................................................................. 13
Geometric design ................................................................................................................ 21
1. Horizontal alignment design ..................................................................................... 21
2. Vertical alignment design ......................................................................................... 21
3. Chainage design ...................................................................................................... 24
Pavement design ................................................................................................................ 30
Material selection for new design ........................................................................................ 33
Marshall Test (Hot mix design analysis) .......................................................................... 34
Costing ............................................................................................................................... 39
References ......................................................................................................................... 41
2
List of tables, figures and graphs
3
Introduction
As a developing country the road system of the country can be named as the most crucial
part of the country's transport system as well as the economy. The road system in the
country can be called one of the governing factors that affect the achievement of national
development that is directly deciding the modernization of the country. Roads provide great
services to the mankind that include the mobility and accessibility at the top. The road
system in the country provides access for people to far and wide areas in the country.
Furthermore the road system provides the mobility to people by providing access to the
locations that they should be at regular intervals at a faster phase like offices or workplaces,
homes, educational institutions, medical institutions etc.
For a developing country like Sri Lanka, it is important that the road network is developed
and well maintained at all times. Though in Sri Lanka the road network shows a rapid
development, the maintenance of the road network is at a very poor status. The poor
maintenance practices of the road network reduces the design life of the road network
drastically that intern affects the economy of the country.
In Sri Lanka the road network shows centralization at the capital city Colombo and spreading
out in to the country. This is a positive fact due to Colombo being the commercial capital of
Sri Lanka. And the rapid development of the road system clearly facilitates the spreading out
of the road network.
In different countries the road network is classified in different methods. In Sri Lanka the
road network can be mainly classified in to five main categories as below according to their
given features.
1. Class A roads: (Maximum speed limit is 70 km/h [1]) Acts as main arteries or long
distance roads that serves the purpose of moving traffic between major cities of the
country
2. Class B roads: (Maximum speed limit is 60 km/h [1]) feed the A class roads and acts
as distributers of traffic between residential areas of the country.
3. Class C roads: Serves the purpose of collection and distribution of traffic in any zone
of the area that finally feeds the traffic to A and B class roads.
4. Class D roads: Serves the purpose of providing access to the people up to
settlements and villages
5. Class E roads: (Maximum speed limit is 50 km/h) Considered as expressways
4
The stretch of the highways in a country can be taken as an indication of its development
.According to the national statistics the grand total of the national highways that the Sri
Lankan government owns runs up to a stretch of 12,333 km with the addition of class A,
class B and class E roads. The C and D class roads runs up to a stretch of 16,000 km and
the total of expressways runs up to a stretch 159.78 km in Sri Lanka.
Project description
The one kilo meter span stretching from Northshore College of Business and Technology
main entrance through Mattakkuliya church road to Ferguson’s road up to Vystwyke road
junction is considered the most critical one kilo meter span of the seven kilo meter span that
the PQR company has been awarded.
This considered one kilo meter span is critical due to the traffic that is attracted by the
buildings and structures in the area including higher educational institutes like Northshore
college of business and technology and Institute of higher national diploma in engineering,
several schools like St. John Vianney Seminary, several religious places like St. Mary's
Church, major retail shops like Cargills Food City, many minor retail shops, public
playgrounds like Modera Street playground, workplaces including People's Bank,
Construction sites, Mattakkuliya Police Station and newly brought up apartments.
Apart from these, the newly commenced construction sites in the considered one kilo meter
span and storage yards attract a very high amount of traffic to this road. Especially the
freight vehicles that the storage yards attract and the heavy vehicles that the construction
sites attract have critically affected the traffic in this one kilo meter span at the recent times.
Furthermore, one section of the road stretching from Northshore College of Business and
Technology through Mattakkuliya church road to St. Mary's road junction that is included in
the critical one kilo meter gets congested due to the highly active Mattakkuliya main bus stop
located in front of Northshore College of Business and Technology. This main bus stop is
populated by 178 Mattakkuliya Narahenpita, 155 Mattakkuliya Soysapura and 145
Mattakkuliya Gangarama – Slave Island buses. This bus stop is most of the time populated
5
by four to seven buses of the above mentioned bus types which results in the decrease of
average speed of vehicles passing through to about 20-25Km/h.
Location
From the sections awarded to PQR Company the most critical 1km section to be
rehabilitated spans from the main entrance of Northshore College of Business and
Technology through Mattakkuliya church road to Ferguson’s road up to Vystwyke road
junction. This road is consisting of two lanes throughout the span and can be assumed as a
class 1 road.
The considered road section can be divided as Mattakkuliya church road and the Ferguson’s
road. This is a critical road that facilitates its users in many ways as discussed above.
The existing condition of the 1km stretch that is considered is in a very unsatisfactory state.
This section of the road has two functional lanes that stretch up to a width of approximately
6
6.6m. But the road does not have a shoulder to be observed. The drain system is also
discontinuous. The drain system of width of approximately 0.45m is observed clearly at
some places but at most of the other places the drains are either covered by mud or
discarded material or have been completely neglected at construction. These observations
are evident in the below figure.
Figure 2. Drains located on some parts of the Mattakkuliya church road that are in functional
conditions.
Figure 3. Drains located on some parts of the Mattakkuliya church road that are in non-
functional conditions.
7
Figure 4.The section of road with no drains, no shoulder and no pathway along Mattakkuliya
church road
The demand for road rehabilitation of some of the selected roads was raised With respect to
a mega scale project. The main concentrations that the PQR Company will have regarding
the selected areas of the road to be developed can be discussed through the below existing
conditions.
8
subjected to deterioration and are not properly enclosed. This raises the safety
issues like pedestrians falling in to the drains. And the sharp edges created by
damages to the drains by deterioration further increases the damage if a pedestrian
falls in to them.
Traffic demand status.
The traffic demand of this section of the road is mainly consist of vehicles travelling in
and out of Colombo from outside. Apart from that, traffic demand is affected by the
bus services running through this section of the road that includes 178 Mattakkuliya
Narahenpita, 155 Mattakkuliya Soysapura and 145 Mattakkuliya Gangarama – Slave
Island buses. The traffic demand shows a rapid growth with the growth of the city of
Colombo. But due to the undeveloped status of the considered section of the road
traffic congestion can be observed in the rush hours.
Misuse of the road by the pedestrians, sales men and drivers
The Mattakkuliya bus stop does not have a separated area for the buses to stop.
Therefore the buses are parked by drivers beside the road which increases the traffic
congestion. The area has a tradition of selling goods in pushcarts that are placed
beside the road that further adds up to the congestion. Due to the unavailability of
pathways, pedestrians miss use the road to travel.
Figure 5.Mattakkuliya main bus stop area (Buses parked beside the road)
9
The geometry of the considered section of the road is mainly flat terrain. But a crest
curve can be observed from the sub post office Mattakkuliya junction to Vystwyke
road junction. Though this section of the road is consisting of few junctions no
horizontal curves can be observed.
The solution for the high traffic congestion is widening the road. The above
mentioned road design can be followed in order to do that.
The inconsistent road sections existing at the present should also be corrected
during the rehabilitation process.
Rutting and mud pits that can be observed at present should be repaired following
technical procedures based on the extent of damage.
A road maintenance system should be introduced functioning under a responsible
body.
Drainage system should be given proper attention during construction and
maintenance.
Sales men in the pushcarts should be given a separate land area for them to carry
out their trade without disturbing the traffic flow.
Placing new road signs where required and maintaining the available road signs
properly.
10
Appointing an experienced health and safety officer to this section of the road during
the construction to maintain health and safety of people during the rehabilitation
project. The health and safety officer should continue his service even after the
completion of the project to look after the maintenance procedures.
In order to carry out the designing and other calculations, a traffic survey was carried out to
collect realistic data. The survey was conducted group wise at the St. Mary's road junction
that is marked in the below figure. Traffic data during one hour was collected on the basis of
whether the vehicles are moving towards Mattakkuliya bus stop or moving out of
Mattakkuliya bus stop. The gathered data can be tabulated as below.
11
Out of Mattakkuliya bus stop
Personal Three
Time cars Bus Trucks wheelers Bicycle Motor bikes
15.40pm 0 - 15 12 5 10 52 12 21 112
15 - 30 5 4 2 54 12 13 90
30 - 45 6 4 4 56 11 11 92
45 - 60 5 5 3 46 16 13 88
TOTAL 28 18 19 208 51 58 382
Percent 7.329842932 4.712042 4.973822 54.45026178 13.35079 15.18324607 753
According to the survey, three wheelers clearly hold the highest percentage to travel
Towards Mattakkuliya bus stop and out of Mattakkuliya bus stop and the buses and trucks
hold the lowest percentage.
Design criteria
The calculations are based on the existing capacity of the highway, existing geometry and
the geometry of the widened four lane road designed for 20 years based on chainage
design, pavement design for the widened four lane highway and material to be used for the
widened four lane highway which includes the Marshall design.
The designing process can be broken down in to the following major aspects as below.
1. Capacity design
This designing process will be integrated with the calculation of the speed limits of
the road, traffic volume of the considered segment of road and level of service (LOS)
calculation of the segment of road.
2. Geometric design
This designing process will be integrated with the coordinated horizontal and vertical
alignment calculation. But the considered segment of the road is not consisting of a
horizontal curved section. Therefore the horizontal alignment calculation is not
required. The required readings of exact locations will be acquired by Google earth.
Apart from the alignment details this designing process will be integrated with types
of site distances, gradients of exact locations and traffic generated at the exact
segment of road when the speed is at a limiting state.
3. Pavement design
This designing process will deal with deciding of the number of layers of material
along with the thickness of each layer that would be used for Surface layer, base
layer, sub base layer and sub grade layer.
12
4. Materials for the new design
This designing process will focus on the selection of required material for
construction attempting to maintain high quality and low cost in the product
considering the availability of material.
Capacity design
The Level of service (LOS) is defined as a quality measure which describes operational
conditions within a considered traffic stream, available freedom to manoeuvre for the vehicle
drivers, affecting traffic interruptions and comfort and convenience for drivers and
passengers. (Highway Capacity Manual 2000)
There are six different types of levels of services according to traffic conditions as follows.
Level of Service A – Availability of free flow with high speed and low volumes. Driver can
select his speed of liking and the flow is unaffected by the presence of others.
Level of Service B – Reasonably free flow. Presence of other users of the road is not
affecting but noticeable. Stable flow is maintained and availability of reasonable freedom to
select their desired speed for drivers.
Level of Service C – Flow is Stable. Majority of the drivers are restricted of the freedom to
select their desired speed, change lanes, overtake etc. Driver operations become affected
by the other users. But operating speeds still remains at a reasonable level.
Level of Service D – Approaches unstable flow with nearly all drivers restricted with the
freedom to manoeuvre. The comfort and convenience levels of users are low but may
remain at tolerable level for a short period of time. Instability arising in the conditions cause
substantial drops in speed of vehicles. But this can still be considered as stable flow. This
service volume is related to the tolerable capacity. Therefore this level of service should be
used in order to find out the upper limitation of traffic demand in scenarios which should be
tolerated
Level of Service E – This has an unstable flow that may be suddenly disturbed by
momentary stoppages along the way. Traffic volume has reached capacity or near capacity.
Speed is relatively slow but maintained uniform with all the other users. Freedom to
manoeuvre is at extremely low status that results in the users wanting other users to give
way. A small increase in the flow would result in a break down.
Level of Service F – This status is called forced or breakdown flow operation. The demand
has exceeded capacity. This results in the stop-start operation with large queue formation. In
the extreme state, both speed and volume can fall down to zero.
It is difficult to suggest the class of the highway section considered in this project due to the
fact that the Sri Lankan conditions are not in direct correlation with the standards followed by
the used codes. The selected highway section can be considered both as class 1 and class
13
2. Therefore the class of the considered highway section is selected as class 1 for the
convenience of calculation.
The capacity design of the considered section of the road for the present conditions can be
carried out as below.
𝑽
𝑽𝒑 =
𝑷𝑯𝑭 ∗ 𝑭𝑮 ∗ 𝒇𝑯𝑽
(20-3)[4]
𝐕𝐩 = 𝐩𝐚𝐬𝐬𝐞𝐧𝐠𝐞𝐫 𝐜𝐚𝐫 𝐞𝐪𝐮𝐢𝐯𝐚𝐥𝐞𝐧𝐭 𝐟𝐥𝐨𝐰 𝐟𝐨𝐫 𝟏𝟓 𝐦𝐢𝐧 𝐩𝐞𝐫𝐢𝐨𝐝 𝐩𝐜/𝐡)
𝑽
𝑷𝑯𝑭 =
𝑽𝟏𝟓 ∗ 𝟒
𝟕𝟓𝟑
= 𝟐𝟐𝟗∗𝟒= 0.822
Assuming :600<Vp<1200
Assuming :600<Vp<1200
ET = 1.1
ET = 1.2
ER = 1.0
ER = 1.0
FG = 1(Terrain = level)
FG = 1(Terrain = level)
(Exhibit 20-10)[4]
(Exhibit 20-9)[4]
𝟔𝟖
PT = 𝟕𝟓𝟑 ∗ 𝟏𝟎𝟎%= 9.03% = 0.0903 (considering buses and trucks)
𝒇 𝟏 𝑓 1
𝑯𝑽 = 𝐻𝑉 =
𝟏+𝟎.𝟎𝟗𝟎𝟑(𝟏.𝟏−𝟏)+𝟎 1+0.0903(1.2−1)+0
= 0.991 = 0.982
14
𝟕𝟓𝟑 753
VP = 𝟎.𝟖𝟐𝟐∗𝟏∗𝟎.𝟗𝟗𝟏= 924 VP = 0.822∗1∗0.982= 933
The capacity to be designed for the proposed road section is for 20 years. The relevant
calculations are as follows.
For the convenience of calculation the vehicles that travelled towards Mattakkuliya bus stop
and out of Mattakkuliya bus stop can be considered as a total in 15 minute intervals as
below.
15
Table 2.Simplified Traffic data Collected
The growth rate of each vehicle type is as below (Road note 31)
The traffic that will occur in 15 minute intervals in 20 years can be calculated as below.
16
Trucks (45-60minutes) 5×(1.070)20=19.34842
Three wheelers(0-15minutes) 109×(1.035)20=216.8869861
Three wheelers(15-30minutes) 103×(1.035)20=204.9482529
Three wheelers(30-45minutes) 106×(1.035)20=210.9176195
Three wheelers(45-60minutes) 67×(1.035)20=133.3158539
Bicycle(0-15minutes) 35×(1.035)20=69.64261022
Bicycle(15-30minutes) 23×(1.035)20=45.76514386
Bicycle(30-45minutes) 23×(1.035)20=51.73451045
Bicycle(45-60minutes) 23×(1.035)20=45.76514386
Motor bikes(0-15minutes) 40×(1.035)20=79.59155454
Motor bikes(15-30minutes) 24×(1.035)20=47.75493272
Motor bikes(30-45minutes) 31×(1.035)20=61.68345477
Motor bikes(45-60minutes) 32×(1.035)20=63.67324363
The traffic that will occur in 15 minute intervals in 20 years calculated above can be
tabulated as below.
Table 5.Table 6.Tabulated traffic that will occur in 15 minute intervals in 20 years
Therefore the total maximum vehicle flow in 1 hour after 20 years (V) =1616.222
And the total maximum vehicle flow in 15minutes after 20 years (V 15, max) =498.8516
V = 1616.222
V 15,max =498.8516
𝑽
𝑽𝒑 = 𝑷𝑯𝑭∗𝑭𝑮 ∗𝒇𝑯𝑽
(20-3) [4]
17
𝑽
𝑷𝑯𝑭 =
𝑽𝟏𝟓 ∗ 𝟒
𝟏𝟔𝟏𝟔.𝟐𝟐𝟐
= =0.810
𝟒𝟗𝟖.𝟖𝟓𝟏𝟔∗𝟒
(𝟕𝟎.𝟏𝟏𝟓𝟗𝟒𝟎𝟓𝟖+𝟏𝟑𝟗.𝟑𝟎𝟖𝟔𝟒𝟎𝟔)
PT = 𝟏𝟔𝟏𝟔.𝟐𝟐𝟐
∗ 𝟏𝟎𝟎%= 12.96% (considering buses and trucks)
𝒇 𝟏 𝑓 1
𝑯𝑽 = 𝐻𝑉 =
𝟏+𝟎.𝟏𝟐𝟗𝟔(𝟏.𝟎−𝟏)+𝟎 1+0.1296(1.1−1)+0
=1 = 0.987
𝟏𝟔𝟏𝟔.𝟐𝟐𝟐 1616.222
VP = 𝟎.𝟖𝟏𝟎∗𝟏∗𝟏=1995.336 VP = 0.810∗1∗0.987= 2021.617
18
FFS = BFFS – FLS -fA(20-2)
FFS = 110 – 6.8 – 9.33 = 93.87 kmh-1
FFS = 93.87 kmh-1
= 100 (1 - e-0.000879 * 1995.336) = 82.69kmh-1 ATS = 93.87 – 0.0125* 2021.617– 0=68.60 kmh-1
The following calculation is carried out to model the highway as a multi lane road with two lanes for
each side (Total four lanes) with a design life of 20 years.
V 15,max = 498.8516 veh/hour
V 15,max = maximum volume within 15 minutes
V = 1616.222 veh/hour
V = Demand volume for the full peak hour
𝑽
𝑽𝒑 =
𝑷𝑯𝑭 ∗ 𝑵 ∗ 𝑭𝒑 ∗ 𝒇𝑯𝑽
(20-3)[4]
𝐕𝐩 = 𝐩𝐚𝐬𝐬𝐞𝐧𝐠𝐞𝐫 𝐜𝐚𝐫 𝐞𝐪𝐮𝐢𝐯𝐚𝐥𝐞𝐧𝐭 𝐟𝐥𝐨𝐰 𝐟𝐨𝐫 𝟏𝟓 𝐦𝐢𝐧 𝐩𝐞𝐫𝐢𝐨𝐝 𝐩𝐜/𝐡)
𝑽
𝑷𝑯𝑭 =
𝑽𝟏𝟓 ∗ 𝟒
𝟏𝟔𝟏𝟔.𝟐𝟐𝟐
𝑷𝑯𝑭 = 𝟒𝟗𝟖.𝟖𝟓𝟏𝟔∗𝟒= 0.810
19
ET = 1.5
ER = 1.2
(Exhibit 21-8)
(𝟕𝟎.𝟏𝟏𝟓𝟗𝟒𝟎𝟓𝟖+𝟏𝟑𝟗.𝟑𝟎𝟖𝟔𝟒𝟎𝟔)
PT = 𝟏𝟔𝟏𝟔.𝟐𝟐𝟐
∗ 𝟏𝟎𝟎%= 12.96% (considering buses and trucks)
20
Level of service = C (Exhibit 21-3)
Therefore it is clear that by widening the road with four lanes consisting of lane width =3m, Drain
width = 0.45m, Shoulder width =1.8m, Lateral clearance= 0.6m the road can be maintained at level
of service C after 20 years. But the road reaches level of service C marginally according to the
calculation.
From the above calculation it can be predicted that if a road of three lanes for each side (Total six
lanes) is designed the level of service can be maintained at or above level of service C comfortably
even after 20 years. But Colombo 15 is a densely populated area and land acquisition to construct a
six lane highway will be highly costly. Therefore it is optimum to construct a four lane highway and
channel the excess traffic to alternative roads if necessary.
Geometric design
In the considered 1km span though there are several junctions no horizontal curves are
encountered. Therefore the horizontal alignment design is not required.
By carrying out site visits it was concluded that the considered road section has a vertical
profile of a crest vertical curve and the vertical elevation above mean sea level and
curvatures were obtained by using Google Earth.
21
Figure 7.Longitudinal cross section1 along the considered path (Courtesy-Google Earth)
Figure 8. Longitudinal cross section 2 along the considered path (Courtesy-Google Earth)
22
From the figure, length of the curve (L) = (974m-683m) =291m
The Reaction time (TR) is considered as 2.5 Sec (Reference AASHTO Manual)
V2
Stopping Sight Disance (SSD) = V ∗ TR +
2(a + G ∗ g)
64 ∗ 1000
64 ∗ 1000 ∗ 2.5 [ 3600 ]2
SSD = +
3600 2(3.4 + .036 ∗ 9.81)
SSD = 86.55m
SSD calculated above is less than the length of the considered curve (291m). Therefore the
safety is enough for a vehicle to stop in the crest without getting in to an accident.
Source: http://safety.fhwa.dot.gov/speedmgt/ref_mats/fhwasa10001/images/Fig2.gif
23
Vehicle tail light of the front vehicle (H2) =0.3m
L= 86.55m
SSD2
L = |G1 − G2| × 2
200 (√H1+√H2)
SSD2
86.55m = 7.3 × 2
200 (√0.6+√0.3)
SSD=64.39m
The below mentioned table represents the minimum SSD values suggested by the Federal
Highway Administration, U.S. Department of Transportation
(http://safety.fhwa.dot.gov/speedmgt/ref_mats/fhwasa10001/)
According to the above table both values obtained for SSD before and after height
adjustment calculation is well below the required value. Therefore the considered road
section is safe according to vertical alignment.
3. Chainage design
The CBR values gained by conducting CBR tests from three different locations of the
considered section of highway were similar. Therefore the chainage and elevation design is
done assuming a typical cross section as below consisting of a gradient of 2.5% towards
both left hand side (LHS) and right hand side (RHS).
24
Figure 10.Typical cross section of the highway
Considering the starting point 0+000 of highway at the main entrance of the Northshore
College of business and technology the following chainages and elevations can be
calculated.
Table 7. Finishing surface chainage and height above mean sea level
Height Height
above above
mean sea mean sea LHS 1- LHS 2- RHS 1- RHS 1-
level of level of the Finishing Finishing Finishing Finishing
centre line finishing height height height height
in existing centre line above above above above
ground after mean sea mean sea mean sea mean sea
Chainage construction level level level level
0+000 9 9.4 9.325 9.25 9.325 9.25
0+010 9 9.4 9.325 9.25 9.325 9.25
0+020 9 9.4 9.325 9.25 9.325 9.25
0+030 9 9.4 9.325 9.25 9.325 9.25
0+040 9 9.4 9.325 9.25 9.325 9.25
0+050 9 9.4 9.325 9.25 9.325 9.25
0+060 9 9.4 9.325 9.25 9.325 9.25
0+070 9 9.4 9.325 9.25 9.325 9.25
0+080 9 9.4 9.325 9.25 9.325 9.25
0+090 9 9.4 9.325 9.25 9.325 9.25
0+100 9 9.4 9.325 9.25 9.325 9.25
25
0+110 9 9.4 9.325 9.25 9.325 9.25
0+120 9 9.4 9.325 9.25 9.325 9.25
0+130 9 9.4 9.325 9.25 9.325 9.25
0+140 9 9.4 9.325 9.25 9.325 9.25
0+150 9 9.4 9.325 9.25 9.325 9.25
0+160 9 9.4 9.325 9.25 9.325 9.25
0+170 9 9.4 9.325 9.25 9.325 9.25
0+180 9 9.4 9.325 9.25 9.325 9.25
0+190 9 9.4 9.325 9.25 9.325 9.25
0+200 9 9.4 9.325 9.25 9.325 9.25
0+210 9 9.4 9.325 9.25 9.325 9.25
0+220 9 9.4 9.325 9.25 9.325 9.25
0+230 9 9.4 9.325 9.25 9.325 9.25
0+240 9 9.4 9.325 9.25 9.325 9.25
0+250 9 9.4 9.325 9.25 9.325 9.25
0+260 9 9.4 9.325 9.25 9.325 9.25
0+270 9 9.4 9.325 9.25 9.325 9.25
0+280 9 9.4 9.325 9.25 9.325 9.25
0+290 9 9.4 9.325 9.25 9.325 9.25
0+300 9 9.4 9.325 9.25 9.325 9.25
0+310 9 9.4 9.325 9.25 9.325 9.25
0+320 9 9.4 9.325 9.25 9.325 9.25
0+330 9 9.4 9.325 9.25 9.325 9.25
0+340 8 8.4 8.325 8.25 8.325 8.25
0+350 8 8.4 8.325 8.25 8.325 8.25
0+360 8 8.4 8.325 8.25 8.325 8.25
0+370 8 8.4 8.325 8.25 8.325 8.25
0+380 8 8.4 8.325 8.25 8.325 8.25
0+390 8 8.4 8.325 8.25 8.325 8.25
0+400 8 8.4 8.325 8.25 8.325 8.25
0+410 8 8.4 8.325 8.25 8.325 8.25
0+420 8 8.4 8.325 8.25 8.325 8.25
0+430 8 8.4 8.325 8.25 8.325 8.25
0+440 7 7.4 7.325 7.25 7.325 7.25
0+450 7 7.4 7.325 7.25 7.325 7.25
0+460 7 7.4 7.325 7.25 7.325 7.25
0+470 7 7.4 7.325 7.25 7.325 7.25
0+480 7 7.4 7.325 7.25 7.325 7.25
0+490 7 7.4 7.325 7.25 7.325 7.25
0+500 7 7.4 7.325 7.25 7.325 7.25
0+510 7 7.4 7.325 7.25 7.325 7.25
0+520 7 7.4 7.325 7.25 7.325 7.25
0+530 7 7.4 7.325 7.25 7.325 7.25
0+540 7 7.4 7.325 7.25 7.325 7.25
0+550 7 7.4 7.325 7.25 7.325 7.25
0+560 7 7.4 7.325 7.25 7.325 7.25
0+570 7 7.4 7.325 7.25 7.325 7.25
0+580 7 7.4 7.325 7.25 7.325 7.25
0+590 7 7.4 7.325 7.25 7.325 7.25
0+600 7 7.4 7.325 7.25 7.325 7.25
0+610 7 7.4 7.325 7.25 7.325 7.25
0+620 7 7.4 7.325 7.25 7.325 7.25
0+630 7 7.4 7.325 7.25 7.325 7.25
26
0+640 7 7.4 7.325 7.25 7.325 7.25
0+650 7 7.4 7.325 7.25 7.325 7.25
0+660 7 7.4 7.325 7.25 7.325 7.25
0+670 7 7.4 7.325 7.25 7.325 7.25
0+680 7 7.4 7.325 7.25 7.325 7.25
0+690 7 7.4 7.325 7.25 7.325 7.25
0+700 8 8.4 8.325 8.25 8.325 8.25
0+710 8 8.4 8.325 8.25 8.325 8.25
0+720 8 8.4 8.325 8.25 8.325 8.25
0+730 9 9.4 9.325 9.25 9.325 9.25
0+740 9 9.4 9.325 9.25 9.325 9.25
0+750 9 9.4 9.325 9.25 9.325 9.25
0+760 10 10.4 10.325 10.25 10.325 10.25
0+770 11 11.4 11.325 11.25 11.325 11.25
0+780 11 11.4 11.325 11.25 11.325 11.25
0+790 12 12.4 12.325 12.25 12.325 12.25
0+800 12 12.4 12.325 12.25 12.325 12.25
0+810 13 13.4 13.325 13.25 13.325 13.25
0+820 13 13.4 13.325 13.25 13.325 13.25
0+830 13 13.4 13.325 13.25 13.325 13.25
0+840 13 13.4 13.325 13.25 13.325 13.25
0+850 13 13.4 13.325 13.25 13.325 13.25
0+860 13 13.4 13.325 13.25 13.325 13.25
0+870 13 13.4 13.325 13.25 13.325 13.25
0+880 13 13.4 13.325 13.25 13.325 13.25
0+890 13 13.4 13.325 13.25 13.325 13.25
0+900 14 14.4 14.325 14.25 14.325 14.25
0+910 14 14.4 14.325 14.25 14.325 14.25
0+920 14 14.4 14.325 14.25 14.325 14.25
0+930 14 14.4 14.325 14.25 14.325 14.25
0+940 13 13.4 13.325 13.25 13.325 13.25
0+950 13 13.4 13.325 13.25 13.325 13.25
0+960 13 13.4 13.325 13.25 13.325 13.25
0+970 12 12.4 12.325 12.25 12.325 12.25
0+980 12 12.4 12.325 12.25 12.325 12.25
0+990 12 12.4 12.325 12.25 12.325 12.25
1+000 11 11.4 11.325 11.25 11.325 11.25
The chainage and the Granular road base finishing height above mean sea level can be
tabulated as below
Table 8.Granular road base surface chainage and height above mean sea level
27
0+010 9 9.4 9.175 9.1 9.175 9.1
0+020 9 9.4 9.175 9.1 9.175 9.1
0+030 9 9.4 9.175 9.1 9.175 9.1
0+040 9 9.4 9.175 9.1 9.175 9.1
0+050 9 9.4 9.175 9.1 9.175 9.1
0+060 9 9.4 9.175 9.1 9.175 9.1
0+070 9 9.4 9.175 9.1 9.175 9.1
0+080 9 9.4 9.175 9.1 9.175 9.1
0+090 9 9.4 9.175 9.1 9.175 9.1
0+100 9 9.4 9.175 9.1 9.175 9.1
0+110 9 9.4 9.175 9.1 9.175 9.1
0+120 9 9.4 9.175 9.1 9.175 9.1
0+130 9 9.4 9.175 9.1 9.175 9.1
0+140 9 9.4 9.175 9.1 9.175 9.1
0+150 9 9.4 9.175 9.1 9.175 9.1
0+160 9 9.4 9.175 9.1 9.175 9.1
0+170 9 9.4 9.175 9.1 9.175 9.1
0+180 9 9.4 9.175 9.1 9.175 9.1
0+190 9 9.4 9.175 9.1 9.175 9.1
0+200 9 9.4 9.175 9.1 9.175 9.1
0+210 9 9.4 9.175 9.1 9.175 9.1
0+220 9 9.4 9.175 9.1 9.175 9.1
0+230 9 9.4 9.175 9.1 9.175 9.1
0+240 9 9.4 9.175 9.1 9.175 9.1
0+250 9 9.4 9.175 9.1 9.175 9.1
0+260 9 9.4 9.175 9.1 9.175 9.1
0+270 9 9.4 9.175 9.1 9.175 9.1
0+280 9 9.4 9.175 9.1 9.175 9.1
0+290 9 9.4 9.175 9.1 9.175 9.1
0+300 9 9.4 9.175 9.1 9.175 9.1
0+310 9 9.4 9.175 9.1 9.175 9.1
0+320 9 9.4 9.175 9.1 9.175 9.1
0+330 9 9.4 9.175 9.1 9.175 9.1
0+340 8 8.4 8.175 8.1 8.175 8.1
0+350 8 8.4 8.175 8.1 8.175 8.1
0+360 8 8.4 8.175 8.1 8.175 8.1
0+370 8 8.4 8.175 8.1 8.175 8.1
0+380 8 8.4 8.175 8.1 8.175 8.1
0+390 8 8.4 8.175 8.1 8.175 8.1
0+400 8 8.4 8.175 8.1 8.175 8.1
0+410 8 8.4 8.175 8.1 8.175 8.1
0+420 8 8.4 8.175 8.1 8.175 8.1
0+430 8 8.4 8.175 8.1 8.175 8.1
0+440 7 7.4 7.175 7.1 7.175 7.1
0+450 7 7.4 7.175 7.1 7.175 7.1
0+460 7 7.4 7.175 7.1 7.175 7.1
0+470 7 7.4 7.175 7.1 7.175 7.1
0+480 7 7.4 7.175 7.1 7.175 7.1
0+490 7 7.4 7.175 7.1 7.175 7.1
0+500 7 7.4 7.175 7.1 7.175 7.1
0+510 7 7.4 7.175 7.1 7.175 7.1
0+520 7 7.4 7.175 7.1 7.175 7.1
0+530 7 7.4 7.175 7.1 7.175 7.1
28
0+540 7 7.4 7.175 7.1 7.175 7.1
0+550 7 7.4 7.175 7.1 7.175 7.1
0+560 7 7.4 7.175 7.1 7.175 7.1
0+570 7 7.4 7.175 7.1 7.175 7.1
0+580 7 7.4 7.175 7.1 7.175 7.1
0+590 7 7.4 7.175 7.1 7.175 7.1
0+600 7 7.4 7.175 7.1 7.175 7.1
0+610 7 7.4 7.175 7.1 7.175 7.1
0+620 7 7.4 7.175 7.1 7.175 7.1
0+630 7 7.4 7.175 7.1 7.175 7.1
0+640 7 7.4 7.175 7.1 7.175 7.1
0+650 7 7.4 7.175 7.1 7.175 7.1
0+660 7 7.4 7.175 7.1 7.175 7.1
0+670 7 7.4 7.175 7.1 7.175 7.1
0+680 7 7.4 7.175 7.1 7.175 7.1
0+690 7 7.4 7.175 7.1 7.175 7.1
0+700 8 8.4 8.175 8.1 8.175 8.1
0+710 8 8.4 8.175 8.1 8.175 8.1
0+720 8 8.4 8.175 8.1 8.175 8.1
0+730 9 9.4 9.175 9.1 9.175 9.1
0+740 9 9.4 9.175 9.1 9.175 9.1
0+750 9 9.4 9.175 9.1 9.175 9.1
0+760 10 10.4 10.175 10.1 10.175 10.1
0+770 11 11.4 11.175 11.1 11.175 11.1
0+780 11 11.4 11.175 11.1 11.175 11.1
0+790 12 12.4 12.175 12.1 12.175 12.1
0+800 12 12.4 12.175 12.1 12.175 12.1
0+810 13 13.4 13.175 13.1 13.175 13.1
0+820 13 13.4 13.175 13.1 13.175 13.1
0+830 13 13.4 13.175 13.1 13.175 13.1
0+840 13 13.4 13.175 13.1 13.175 13.1
0+850 13 13.4 13.175 13.1 13.175 13.1
0+860 13 13.4 13.175 13.1 13.175 13.1
0+870 13 13.4 13.175 13.1 13.175 13.1
0+880 13 13.4 13.175 13.1 13.175 13.1
0+890 13 13.4 13.175 13.1 13.175 13.1
0+900 14 14.4 14.175 14.1 14.175 14.1
0+910 14 14.4 14.175 14.1 14.175 14.1
0+920 14 14.4 14.175 14.1 14.175 14.1
0+930 14 14.4 14.175 14.1 14.175 14.1
0+940 13 13.4 13.175 13.1 13.175 13.1
0+950 13 13.4 13.175 13.1 13.175 13.1
0+960 13 13.4 13.175 13.1 13.175 13.1
0+970 12 12.4 12.175 12.1 12.175 12.1
0+980 12 12.4 12.175 12.1 12.175 12.1
0+990 12 12.4 12.175 12.1 12.175 12.1
1+000 11 11.4 11.175 11.1 11.175 11.1
29
Similar to the above table, the chainage and the height above mean sea level that the
excavations should be carried out can be tabulated by deducting another 0.250m from each
height above mean sea level of the above table.
Pavement design
The following pavement calculation is done for a 20 year design lifetime of the highway. The
time that the vehicles flow on the road is assumed as 16 hours per day. Road note 31 and
Guide lines for capacity of roads in rural areas-Indian road congress guide lines are mainly
used to carry out the following calculations.
The below Equivalent standard axles (ESA) values are generated by using the following
formula.
4.5
Axle Load (kg)⁄
ESA factor=⌊ 8160 ⌋ Overseas Road note 31-Table 2.1
The following is a conservative pavement design. Therefore the four lane road to be
designed is designed as a combination of 2 two lane roads.
Therefore the following maximum hourly flow is considered to be half of the maximum hourly
flows gained by the survey.
30
Pi (Cars/SV) =33 ×16×1.88=992.64
Pi (Bicycle) = 63.5×16×9.147*10-7=9.293*10-4
A=365 ∑m n th
i=1 Pi((1 + ri) − 1)/ri ; Table 2.2 -OVERSEAS ROAD NOTE 31(4 EDITION)
992.64[(1+0.05)20 −1]
A (Cars/SV) =365{ 0.05
}=11.98×106
76.8[(1+0.04)20 −1]
A (Bus/LB) =365{ 0.04
}=0.835×106
3.744[(1+0.07)20 −1]
A (Trucks/MA) =365{ 0.07
}=0.056×106
0.0128[(1+0.035)20 −1]
A (Three wheeler) =365{ 0.035
}=0.0000132×106
31
1.318×10−4 [(1+0.035)20 −1]
A (Motor bike) =365{ 0.035
}=0.000001×106
Vehicle type A
PC 11.98×106
Bus 0.835×106
Truck 0.056×106
Three-wheeler 0.0000132×106
Motorbike 0.000001×106
Bicycle 0.0000096×106
Total 12.8710238×106
According to the results gained by laboratory testing the CBR value of the soil in the area is
20.
Therefore select sub grade strength class S5 -Table 3.1 -OVERSEAS ROAD NOTE
31(4thEDITION)
SD-Surface dressing
32
Granular road base, GB1-GB3
The main types of materials used for the construction of the considered 1km span of
highway are.
Cement or lime stabilization is done to the soil in order to develop the engineering properties
required for the pavement sub layers. Stabilization process is also capable of minimizing the
risk of long-term deleterious reactions that occur in the material that might reduce the
pavement structural capacity.
For a granular material to be qualified as a base material the following criteria has to be met
according to the Road development authority (RDA) Specifications.
The main type of granular material used in Sri Lanka for road base construction is Aggregate
base course (ABC). Apart from the above three main qualities the material should be well
graded according to the particle size distribution curve and the Flakiness index of the
material should be less than 25% for the material t be qualified as a base material.
The reasons for selecting the base material according to the above limitations are due to the
following explanations.
33
a) Flakiness is considered an unfavourable condition for a base material as it inherits a
feature of breaking down under heavy loads on the structure. This inherent feature of
material with higher flakiness reduces its ability to bear higher loads.
b) The material should be well graded in order to provide the following features that are
essential for a road structure.
A well graded material has the required level of natural interlock between each
angular particle of aggregate that will finally result in low amount of voids once the
material reaches its compacted state.
A well graded material spreads the load applied throughout the structure.
Grading of the material is an indicator of other engineering properties such as
compressibility of material, shear strength capacity and hydraulic conductivity of
material.
c) CBR value directly indicates the strength of the material which is the most critical
factor for a base material.
d) Maximum dry density (MDD) represents a state of maximum interlocking of particles
and behaves similarly to the CBR value which makes it special.
e) Plasticity index is essential to maintain the plasticity of the material.
3) Asphalt
The main function of bitumen in an asphalt mix in a flexible pavement is to make and
maintain a strong bond between the components of the pavement in the highway and most
importantly to provide a smooth surface for the pedestrians and vehicles.
The bitumen content Pb is designed below in order to construct the one kilo meter span of
highway.
This design is mainly done in order to find the bitumen content of the asphalt that is to be
used for the construction of the road section. The design criteria required for the design
calculations are as follows.
34
Table 14.All design Criteria of materials
Assumptions
The required values for Voids in Total Mix (Va) and Void in Mineral Aggregate (VMA) are
calculated using the below equations
35
Void in Total Mix (Va)
Gmb
Va = (1 - Gmm) × 100
Gmb ( 1− Pb )
VMA = 1-( Gsb
) × 100
VMA−Va
VFA = ( VMA
) × 100
The values calculated by using the above formulae can be tabulated as below
Voids in
Voids in Mineral
Asphalt Ps (100- Stability Total Mix Aggregate
%(Pb) Pb) Gmb (N) Flow Gmm (Va) (%) (VMA) (%)
5.5 94.5 2.348 3550 8 2.501219344 6.125786 17.29929184
6 94 2.364 5800 11 2.48200546 4.75444 17.17629519
6.5 93.5 2.36 7600 13 2.463084521 4.18518 17.75624301
7 93 2.353 8250 17 2.444449877 3.741123 18.43868804
7.5 92.5 2.341 7000 22 2.426095079 3.5074915 19.2909057
36
7
6
Void in Total Mix (Va) (%)
0
0 1 2 3 4 5 6 7 8
Pb %
9000
8000
7000
6000
Stability(N)
5000
4000
3000
2000
1000
0
0 1 2 3 4 5 6 7 8
Pb%
37
The variation of Gmb Vs Pb can be plotted as below
2.37
2.365
2.36
2.355
Gmb
2.35
2.345
2.34
2.335
0 2 4 6 8
Pb%
According to the above graph Pb3 (The Pb value corresponding to maximum Gmb value) = 6%
Pb1+Pb2+Pb3 6.6+7.0+6
Therefore Design Pb = 3
= 3
= 6.53%
Road note 31 suggests that a Pb value should be taken so that the corresponding flow value
is retained at a value higher than 2mm.
25
20
Flow(mm)
15
10
0
0 1 2 3 4 5 6 7 8
Pb%
38
From the above table it is evident that the Flow corresponding to Pb% of 6.53 is well above
2mm. Therefore the Pb% value of 6.53 is ok according to the flow limit.
2. The variation of Voids in Mineral Aggregate (VMA) (%) Vs Pb% can be plotted as
below.
Maximum particle size is 14mm, Therefore Table 8.5; overseas road note 31 suggests that a
Pb value should be taken so that the corresponding VMA value is retained at a value higher
than 15%.
19.5
Void in Mineral Aggregate (VMA) (%)
19
18.5
18
17.5
17
0 1 2 3 4 5 6 7 8
Pb%
According to the above graph the value of void in mineral aggregate (VMA) (%) is well above
15 %. Therefore the Pb% value of 6.53 is ok according to the VMA limit.
Therefore the asphalt content of 6.53% should be used for the construction as it satisfies all
the conditions in Table 8.4 of Overseas Road Note 31 (Stability above 6, Flow above 2, Air
voids between 3%-5%)
The Compaction level (number of blows) that the material will be subjected to is 2×75.
Costing
Assumptions
The construction project in the considered 1km span is carried out in a period of one
month.
Surface dressing (Wearing course) is 75mm
39
250mm thick cement or lime stabilized gravel road base
40
References
routemaster.lk. 2016. Sri Lanka bus route 178 from Narahenpita to Mattakkuliya.
[ONLINE] Available at: http://routemaster.lk/bus/178/. [Accessed 01 June 2016].
Google Maps. 2016. Google Maps. [ONLINE] Available at:
https://www.google.lk/maps. [Accessed 01 June 2016].
[ONLINE]Availableat:http://www.tc.umn.edu/~cliao/ROAD/javahelp/Images/crest_cur
ve.jpg [Accessed 01 June 2016].
[ONLINE]Availableat:http://safety.fhwa.dot.gov/speedmgt/ref_mats/fhwasa10001/ima
ges/Fig2.gif [Accessed 7 Jun. 2016].
Overseas Road note 31 fourth edition.
Transport in Sri Lanka (2015) Wikipedia, the free encyclopaedia. Available from :
http://en.wikipedia.org/wiki/Transport_in_Sri_Lanka [ Accessed on 4th May, 2016]
National highways in Sri Lanka (2015) Road Development Authority. Available from :
http://www.rda.gov.lk/source/rda_roads.htm [Accessed on 4th May, 2016]
Professional Review Examination, February/March 2010, Institution of Engineers, Sri
Lanka Eng. S.A.S.T Salawavidana
Highway Capacity Manual, Transportation Research Board, Washington, D.C., 2000.
A Policy on Geometric Design of Highways and Streets, Fourth Edition, American
Association of State Highway and Transportation Officials (AASHTO), Washington,
D.C., 2001.
Guide lines for capacity of roads in rural areas-Indian road congress guide lines.
Highway-with-beautiful-nature, http://alliswall.com/file/107/1920x1200/16:9/big-
highway-with-beautiful-nature.jpg [Accessed on 4th May, 2016]
[ONLINE]Available at:http://www.virginiadot.org/business/resources/bu-mat-
chapt1ap.pdf [Accessed 7 Jun. 2016].
[ONLINE]Available at: http://www.aboutcivil.org/importance-types-of-bituminous-
materials.html[Accessed 7 Jun. 2016].
[ONLINE]Available
at:http://safety.fhwa.dot.gov/speedmgt/ref_mats/fhwasa10001/[Accessed 7 Jun.
2016].
41