Name: Stopira Ricambi

NIM: 2001886762

1. A new schedule look like

Explanation of A and B

- Activity A will start at day 0 and finish at day 4


- Activity B will start at day 0 and finish at day 5

Explanation for C; D; E

- If we look at activity C+D+E, It needs 5 resources


- Activity D start first than activity C and E, because it needs only 1 resource. It start at day 5
and finish at day 10.
- Activity C has smaller slack than E
- Activity C can’t start at day 4 because it requires 2 resources. Activity C will delay for 1 day.
Activity C start at day 5 and finish at day 9.
- Activity E delay for 4 days, start at day 9 and finish at day 12

Explanation F

- Activity F delay for 2 days


- Activity F start at day 12 and finish at day 14

Project duration: 14 days


Name: Stopira Ricambi
NIM: 2001886762

2. Duration: 17
Direct cost: $2,000
Indirect cost: $1,500
Total cost: $3,500
Act. Change:

Duration: 16
Direct cost: $2,040
Indirect cost: $1,450
Total cost: $3,490
Act. Change: D

Duration: 15
Direct cost: $ 2,100
Indirect cost: $1,400
Total cost: $ 3,500
Act. Change: H

Duration: 14
Direct cost: $ 2,160
Indirect cost: $1,350
Total cost: $ 3,510
Act. Change: H
Name: Stopira Ricambi
NIM: 2001886762

Duration: 13
Direct cost: $ 2,260
Indirect cost: $1,300
Total cost: $ 3,560
Act. Change: B

Duration: 12
Direct cost: $ 2,460
Indirect cost: $1,250
Total cost: $ 3,610
Act. Change: I

The optimum time cost schedule would be 16 weeks

Total cost $3,490