Concrete Volume Take-Off Per Level

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 10

CONCRETE VOLUME TAKE-OFF PER LEVEL

ITEM DIMENSION (M)


DESCRIPTION QTY UNIT TOTAL (M3) OVER-ALL REMARKS
NO TOTAL (M3)
W H/T L

1 Column 1 102 m³ 0.250 3.75 0.300 0.28125 28.69

2 Column 2 8 m³ 0.250 4.871 0.300 0.365325 2.92

3 Column 3 4 m³ 0.250 5.85 0.300 0.43875 1.76

4 Column 4 2 m³ 0.150 3.65 0.250 0.136875 0.27

5 Wall Footing 1 m³ 0.40 0.250 384.1 38.4 38.41

6 Footing 1 114 m³ 1.0 0.3 1.0 0.3 34.20

7 Footing 2 2 m³ 0.8 0.3 0.8 0.2 0.38

8 Slab 1 1 m³ 15.7 0.1 150.8 236.8 236.80

9 Slab 2 1 m³ 2.0 0.1 6.1 1.2 1.22

10 Slab 3 1 m³ 0.8 0.1 314.8 25.2 25.18

11 Slab 4 1 m³ 1.5 0.1 10.0 1.5 1.49

12 Tied Beam 1 m³ 0.20 0.300 384.1 23.0 23.05

13 Roof Beam 1 m³ 0.20 0.400 384.1 30.7 30.73

14 CHB 6" with 0.3x0.6 window 37 pcs 2.7 3.00 99.0 3663.00

15 CHB 6" with 0.3x0.6 & 0.5x0.8 w 42 pcs 2.7 3.00 94.0 3948.00

16 CHB 6" without less 2 pcs 2.7 3.00 101.3 202.50

17 CHB 6" wall 1 1 pcs 1862.5 1862.50

18 CHB 6" machine 1 pcs 837.5 837.50

19 CHB 6" @ the back 1 pcs 700.0 700.00 12527.25

20 CHB 6" with exchust 6 pcs 75.0 450.00 13780

21 CHB 6" with door 3 pcs 62.5 187.50

22 CHB 6" 1 pcs 313.8 313.75

23 CHB 6" at control room 1 pcs 362.5 362.50


ITEM DIMENSION (M) OVER-ALL
NO DESCRIPTION QTY UNIT TOTAL (M3) TOTAL (M3) REMARKS
W H/T L
106.63

117.2961 cement 176.45 X 9= 1588 bags

sand 176.45 X 0.5 = 88.2 m³

gravel 176.45 X 1= 176.4 m³

264.69 cement 264.69 X 9= 2382.19 bags 543324

sand 264.69 X 0.5 = 132.34 m³ 79406.33

53.8 gravel 264.69 X 1= 265 m³ 132343.9

59.1514

cement 138 X 1.018 = 140.28 bags

sand 138 X 0.0844 = 12 m³

Grand Total:

cement 4110 bags 937,193.48

sand 232.2 m³ 139,318.76

gravel 441.1 m³ 220,567.64

1,297,079.89
Dimensions Total Area Ceramic Tiles Cement Mortar (0.086)

L W m² pcs bags

bedroom 1 2.8 2.95 8.26 57 0.8

bedroom 2 2.9 2.95 8.56 59 0.8

bedroom 3 2.95 2.95 8.70 60 0.8

bedroom 4 2.95 2.95 8.70 60 0.8

Hall Way 5.65 0.8 4.52 31 0.4

Living Room 5.87 4.25 24.95 76 2.4

0.95 0.9 0.86 3 0.1

Kitchen 1.54 2.03 3.13 10 0.3

1 1.43 1.43 4 0.1

Terrace 2.6 5.65 14.69 45 1.4

Ceramic Tiles 40x40cm 39 266 4

Ceramic Tiles 60x60cm 45 138 4


White Cement Filler (0.50) Tile Adhesive (0.11)

bags bags

4.5 1.0

4.7 1.0

4.8 1.1

4.8 1.1

2.5 0.5

13.7 3.0

0.5 0.1

1.7 0.4

0.8 0.2

8.1 1.8

21 5

25 5
EMBEDDED PLATES TAKE-OFF PER STRUCTURE

ITEM COMPOSITE TOTAL WT DIMENSION (M)


DESCRIPTION QTY UNIT REMARKS
NO WT/PLATE (KG)
W L THK

NOTE : 942
AS PER SCOPE OF WORK = 150MM X 150MM X 1/4"thk
AS PER ACTUAL = 200MM X 200MM X 1/2"thk

A DORMITORY 1-2 PHASE - 1

a.1 HORIZONTAL TIE BEAM 14 EA 4.71 65.94 0.20 0.20 0.125

SUB-TOTAL 65.94

B DORMITORY 1-1 PHASE - 1

b.1 HORIZONTAL TIE BEAM 14 EA 4.71 65.94 0.20 0.20 0.125

SUB-TOTAL 65.94

C DORMITORY 4-2 PHASE - 1

c.1 HORIZONTAL TIE BEAM 14 EA 4.71 65.94 0.20 0.20 0.125

SUB-TOTAL 65.94

D DORMITORY # 2 PHASE - 1

d.1 HORIZONTAL TIE BEAM 14 EA 4.71 65.94 0.20 0.20 0.125

d.2 TOILET BEAM 18 EA 4.71 84.78 0.20 0.20 0.125

SUB-TOTAL 150.72

E DORMITORY # 3 PHASE - 1

e.1 HORIZONTAL TIE BEAM 14 EA 4.71 65.94 0.20 0.20 0.125

e.2 TOILET BEAM 18 EA 4.71 84.78 0.20 0.20 0.125

SUB-TOTAL 150.720

F DORMITORY # 4-1 PHASE - 2

f.1 HORIZONTAL TIE BEAM 14 EA 4.71 65.94 0.20 0.20 0.125

SUB-TOTAL 65.94

G DORMITORY # 4-2 PHASE - 2

g.1 HORIZONTAL TIE BEAM 14 EA 4.71 65.94 0.20 0.20 0.125

SUB-TOTAL 65.94

H DORMITORY # 4-2 PHASE - 2

h.2 HORIZONTAL TIE BEAM 14 EA 4.71 65.94 0.20 0.20 0.125

SUB-TOTAL 65.94

J DORMITORY # 5 PHASE - 2

j.1 HORIZONTAL TIE BEAM - 5-1 10 EA 4.71 47.1 0.20 0.20 0.125

SUB-TOTAL 47.100

K DORMITORY # 6 PHASE - 2

k.2 HORIZONTAL TIE BEAM 10 EA 4.71 47.1 0.20 0.20 0.125

SUB-TOTAL 47.100

OVER-ALL TOTAL 791.280


+4.400M ADDITIONAL LG
L MEN'S TOILET & BATCHROOM

l.1 No of Plates Embedded 10 EA 4.71 47.1 0.20 0.20 0.125

TOTAL 47.10
FLOOR SMOOTH FINISHTAKE-OFF PER STRUCTURE

ITEM DIMENSION (M) OVER-ALL


NO DESCRIPTION QTY UNIT TOTAL (M2) TOTAL (M2) REMARKS
W H L

A DORMITORY 1-2 PHASE - 1

a.1 FLOOR SMOOTH FINISH 1 EA 4.80 21.60 103.68 103.68

SUB-TOTAL 103.68

B DORMITORY 1-1 PHASE - 1

b.1 FLOOR SMOOTH FINISH 1 EA 4.80 21.60 103.68 103.68

SUB-TOTAL 103.68

C DORMITORY 4-2 PHASE - 1

c.1 FLOOR SMOOTH FINISH 1 EA 4.80 21.60 103.68 103.68

SUB-TOTAL 103.68

D DORMITORY # 2 PHASE - 1

d.1 FLOOR SMOOTH FINISH 1 EA 4.80 21.75 104.40 104.40

SUB-TOTAL 104.40

E DORMITORY # 3 PHASE - 1

e.1 FLOOR SMOOTH FINISH 1 EA 4.80 21.60 103.68 103.68

SUB-TOTAL 103.68

F DORMITORY # 4-1 PHASE - 2

f.1 FLOOR SMOOTH FINISH 1 EA 4.80 21.60 103.68 103.68

SUB-TOTAL 103.68

G DORMITORY # 4-2 PHASE - 2

g.1 FLOOR SMOOTH FINISH 1 EA 4.80 21.60 103.68 103.68

SUB-TOTAL 103.68

H DORMITORY # 4-2 PHASE - 2

h.1 FLOOR SMOOTH FINISH 1 EA 4.80 21.60 103.68 103.68

SUB-TOTAL 103.68

J DORMITORY # 5 PHASE - 2

j.1 FLOOR SMOOTH FINISH 1 EA 4.80 14.55 69.84 69.84

SUB-TOTAL 69.84

K DORMITORY # 6 PHASE - 2

k.1 FLOOR SMOOTH FINISH 1 EA 4.80 14.55 69.84 69.84

SUB-TOTAL 69.84

L MEN'S TOILET & BATCHROOM +4.400M ADDITIONAL LG

l.1 FLOOR SMOOTH FINISH 1 EA 5.00 21.65 108.25 108.25

SUB-TOTAL 108.25

OVER-ALL TOTAL 1,078.09


DORMITORY WATER PROOFINGTAKE-OFF PER STRUCTURE

ITEM DIMENSION (M) TOTAL


NO DESCRIPTION QTY UNIT (LM) REMARKS
W H L

A DORMITORY 1-2 PHASE - 1

a.1 Horizontal Panel 2 EA 21.60 43.20

a.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.80

B DORMITORY 1-1 PHASE - 1

b.1 Horizontal Panel 2 EA 21.60 43.20

b.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.80

C DORMITORY 4-2 PHASE - 1

c.1 Horizontal Panel 2 EA 21.60 43.20

c.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.80

D DORMITORY # 2 PHASE - 1

d.1 Horizontal Panel 2 EA 21.60 43.20

d.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.80

E DORMITORY # 3 PHASE - 1

e.1 Horizontal Panel 2 EA 21.60 43.20

e.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.80

F DORMITORY # 4-1 PHASE - 2

f.1 Horizontal Panel 2 EA 21.60 43.20

f.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.80

G DORMITORY # 4-2 PHASE - 2

g.1 Horizontal Panel 2 EA 21.60 43.20

g.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.80

H DORMITORY # 4-2 PHASE - 2

h.1 Horizontal Panel 2 EA 21.60 43.20

h.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.80

J DORMITORY # 5 PHASE - 2

j.1 Horizontal Panel 2 EA 14.55 29.10

j.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 38.70
ITEM DIMENSION (M) TOTAL
NO DESCRIPTION QTY UNIT (LM) REMARKS
W H L

K DORMITORY # 6 PHASE - 2

k.1 Horizontal Panel 2 EA 14.55 16.55

k.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 26.15

L PHASE 3 - DORMITORY 1-2 PHASE - 3

l.1 Horizontal Panel 2 EA 21.65 43.30

l.2 Vertical Panel 2 EA 4.80 9.60

SUB-TOTAL 52.90

OVER-ALL TOTAL 540.15


FENCE QTY TAKE-OFF
QTY AMT
SCOPE 1.80 0.45 80 97.77778 1.222222
ACTL 2.20 0.55 122.7
4.00 202.70

You might also like