Design & Engineering Systems (Pvt.) Ltd.

Date:04-09-19
Remodeling of Warsak Canal Systems
Daily Progress Report
Total Plate Activity's
Received Total Weight Fabrication Welding Testing Finishing Mobilization
Sr.No. Description Remarks
From in kg Hydro Surface Epoxy Lining Epoxy Coating Dispatch to
Peshawar Diagonal Beveling Pre Rolling Rolling Fit Up Rerolling Tacking Root Pass Filling Capping CS Joints Back Pass DPT R.T
Testing Preparation (500Microns) (1000Microns) Peshawar
1 Plate / shell 40 50,880 40 40 40 40 40 40 40 40 40 5 40 40 40 5 - - - - -

Summary
Activity's
Fabrication Welding Testing Finishing Mobilization
Hydro Surface Epoxy Lining Epoxy Coating Dispatch to
Diagonal Beveling Pre Rolling Rolling Fit Up Rerolling Tacking Root Pass Filling Capping CS Joints Back Pass DPT R.T
Testing Preparation (500Microns) (1000Microns) Peshawar
Total 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40
Complete 40 40 40 40 40 40 40 40 40 5 40 40 40 5 - - - - -
Balance - - - - - - - - - 35 - - - 35 40 40 40 40 40

Welding Detail
Description Total Qty of
Fit Up Root Pass Filling Caping Balance
Joints
Longitudinal Seam (LS) 40 40 40 40 5 35
Circumferential Seam (CS) 32 32 32 32 4 28