MASTER SCHEDULE NEW FACTORY OF AUTRANS ASIA INDONESIA

OWNER : PT. Autran Asia Indonesia


Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
PROJECT : New Factory and Office Building Remaks

No. Description I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV

A Preliminary Work
- Site Survey existing Block Factory
- Establish level of Factory
- Site Facility (site offce, temp. bridge and others)
B Factory Building
- Earth Work
- Foundation Work
- RC Structure Work
- Steel Structure Work
- Roofing Work
- Architetural work (wall, window, concrete slab and other)
C Office Building
- Earth Work
- Foundation Work
- RC Structure Work
- Wall Work (ALC Block)
- Architetural work (window,door, concrete canopy and other)
D Underground Tank
E Dock Levelel
F Outdoor Work
- Earth Work
- Concrete Road
- Draiange (by Precast)
- Car and Motor Parking
- Security Building
- Fence Work
- Other Facility
G Mechanical Work
H Electrical Work