ANALYSIS OF RATE FOR FABRICATION / FIXING OF GUARD RAIL, EMBEDED IN

RCC 1:1.50:3 ETC COMPLETE (GROUP-I)


Unit = P.Rft
Take Length 37.50 Rft for Analysis Purpose

1 Fabrication of heavy steel work, with angle, tees, flat iron, round iron and sheet
iron for making trusses, girders, tanks, etc., including cutting, drilling, revitting,
handling, assembling and fixing, but excluding erection in position.

Steel Vertical Post size 120 x 55 x 7mm


7 x 1.82 x 11.20 = 142.69 Kg.
Nos. Length Kg./Meter

Block Between W-Rail and Vertical Post.


7 x 0.325 x 3.90 = 8.87 Kg.
Nos. Length Kg./Meter

W-Beam Guard Rail Size 4110 x 310 x (2.75mm)


3 x 4.11 x 10.34 = 127.49 Kg.
Nos. Length Kg./Meter

Nut & Bolts for fixing W-Beam Rail with vertical post.
4 x 12 = 48.00 Nos.
3 x 4 = 12.00 Nos.
Total = 60.00 Nos.
60.00 x 0.200 = 12.00 Kg.

S.Total = 291.05 Kg.


End Pieces
Approach End 3.00 M @ 10.34 Kg. / Meter = 31.02 Kg.
Departure End 1.00 M @ 10.34 Kg. / Meter = 10.34 Kg.

S.Total = 41.36 Kg.

Total = 332.41 Kg.

@ Rs.11,306.80 P%Kg. = Rs.37,585

Cost Per Rft Rs.37,585 = Rs.1,002.27


37.50

3 Cost of Hot Dip Galvanization.

Qty as per Item No.1 = 332.41 Kg.

@ Rs.50 P.Kg. = Rs.16,621

G-II Page1
4 Excavation in foundation for structure.

7 x 2 x 2 x 3.50 = 98.00 Cft.

@ Rs.5,995.45 P%Cft. = Rs.588

5 P/L P.C.C 1:2:4 i/c placing, mixing, finishing and curing compete.

7 x 2 x 2 x 3.50 = 98.00 Cft.

@ Rs.24,776.20 P%Cft. = Rs.24,281

6 P/F Double face reflector (red) of approved quality i/c cost of bolts & nuts and
welding etc compelete in all respect.

1 x 3 = 3.00 Nos.

@ Rs.500.00 Each = Rs.1,500

Total = Rs.80,573

G.Total = Rs.80,573

Cost Per Rft Rs.80,573 = Rs.2,149


37.50

Sub Engineer, Sub Divisional Officer, Executive Engineer,


Highway Sub Division, Highway Division,
Khanewal Khanewal