Project: Instalasi Fwko Di SP 1 KTT Lokasi: SP 1 KTT Client: Pt. Pertamina Ep Asset 1 Field Jambi Contractor: Putra Bajubang & Bahana Karya Mandiri
Project: Instalasi Fwko Di SP 1 KTT Lokasi: SP 1 KTT Client: Pt. Pertamina Ep Asset 1 Field Jambi Contractor: Putra Bajubang & Bahana Karya Mandiri
Project: Instalasi Fwko Di SP 1 KTT Lokasi: SP 1 KTT Client: Pt. Pertamina Ep Asset 1 Field Jambi Contractor: Putra Bajubang & Bahana Karya Mandiri
LOKASI : SP 1 KTT
CLIENT : PT. PERTAMINA EP ASSET 1 FIELD JAMBI
CONTRACTOR : PUTRA BAJUBANG & BAHANA KARYA MANDIRI
No. Work Description JAN 1st Week JAN 2nd Week JAN 3rd Week JAN 4th Week
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 13 14 15 16 17 18 19 20 21 22
Installation and welding of 3" Oil Line FWKO Outlet to
1
Existing Gas System at SP 1.
Installation and welding of 2 x 3" Gas Line FWKO Outlet
2
to Existing Gas System at SP 1.
Installation and welding of 8" Water Injection Line
3
FWKO Outlet to Existing Water Line FWKO 1.
Installation and welding of 8" Drain Water Line FWKO
4
Outlet to Existing Pit at SP 1 KTT.
Installation and welding of 8" Oil Line inlet from
5
Existing Header 1 to FWKO.
8 X-Ray Test
11 Commissioning