Professional Documents
Culture Documents
043 Tunnelling Beneath A Glacier
043 Tunnelling Beneath A Glacier
043 Tunnelling Beneath A Glacier
SPITSBERGEN, NORWAY
Impressive Output content of 5%, and a low sulphur content Svea North is accessed by sea during
at 0.6%. the summer.
Svea North is located some 40 km from Svea North is accessed by simply
Spitsbergen’s main town of Longyearbyen, driving into the drift in a conventional
and there is a fully-functioning mine four-wheel drive vehicle. Charging the face from the rig basket.
encampment at the site. There is no road,
and the only access is by boat in summer,
snowmobile in winter, or by the daily
flights into the airstrip.
Despite its remote location, Svea North
produced an output of nearly 2.7 million t
from its single longwall face in 2003.
Indeed, in October, 2003, the mine pro-
duced a creditable 460,000 t, taking it to
the number one position in Europe.
Average output per miner of 75 t/shift
makes it one of the most efficient under-
ground coal mines in the world.
The seam averages 3.8 m thick, with
few geological faults, and good overall
conditions. It lies under 400 m of rock and
200 m of ice at its deepest, while at its
shallowest point, there is just 50 m of rock
between the coal seam and the glacier. The
estimated coal reserve is 40 million t, of
which SNSK expects to mine something
like 32 million t. It is a very marketable
product at 32 MJ/kg, with a low ash
FACE DRILLING 43
FD3/15 p43-45 29/3/04 7:27 am Page 44
SPITSBERGEN, NORWAY
Tunnel Drivage
LNS was awarded the contract for the
5.6 km-long x 38 sq m tunnel, and started
its development in November, 2002, using
a new Atlas Copco Rocket Boomer L2 C
drillrig. Planned advance of 100 m/week
was easily exceeded, with a world
drill/blast record of 150 m being achieved
in the best week.
This rate of advance is normally
achieved using TBMs, and is extremely
significant for a drill and blast operation
because of the dramatic difference in capi-
tal employed.
Rock conditions are relatively soft,
competent and not generally abrasive,
although there is some quartzite intrusion.
LNS used 48 mm bits with three holes in
front and ballistic buttons, which lasted
from 300-500 m before regrinding. For
each round, the blastholes were drilled to
depths of 5 m and took around 1.5-3 min-
utes apiece, with 75-76 holes required for
Atlas Copco Rocket Boomer L2 C at the Since production commenced, a com- a full pattern. Productivity was kept at a
face. bination of on-off highway trucks and high average rate, with LNS achieving 3-4
ADTs has hauled the coal the 6 km or so rounds/day, and sometimes five. In the
from the stockyard at the pit entrance to worst conditions, this dropped to two
the port area, making up to 50,000 rounds/day.
journeys/year. For charging the upper holes and the
As the fjord freezes during winter, the cut, the Rocket Boomer was equipped with
coal is kept in a 1.6 million t-capacity a Dyno hose charger mounted in the
stockpile beside the port until the ships can basket. With this device it was possible to
again make their way to the dock. regulate the volume of explosives injected
Keeping an ice road open in such a into each hole. A second hose was used
climate is not easy, with around NKr 5 mil- manually for charging the holes in the
lion/year spent on grading alone, to main- lower part of the face, without the option
tain the required capacity of 16,000 t/day. to regulate the volume of explosives
The wear and tear on trucks and loading injected. A standard emulsion explosive
equipment added greatly to this bill, was used, mixed in the hole and detonated
making it imperative that an alternative using Nonel. Emulsion explosives are
solution be found. more expensive than ANFO, but their
SNSK decided to replace the ice road much-reduced blasting fumes allow opera-
with a tunnel under the glacier. The 2.6% tors to return to the face quicker after each
dipping tunnel alignment lies beneath the blast. Another advantage is that emulsion
production seam, and it is designed to house components can be transported under the
both a conveyor system, and a channel to flammable material rules, and are not
drain ground water percolating through the classified as explosive until they are in the
mine from a lake beneath the glacier. hole.
The mine has suffered problems with The mucking operation took around
excessive water, despite its powerful 1.5-2 h for around 380 t of blasted rock. A
installed pump station and lengthy conventional loader was used, with a fleet
pipelines. Water ingress is greater in of six trucks, with a grader keeping the
summer because of the thaw, evidenced by roadway clear and smooth. A face crew of
the longwall being put out of action by six was sufficient for each of the two
44 FACE DRILLING
FD3/15 p43-45 29/3/04 7:27 am Page 45
SPITSBERGEN, NORWAY
Equipment Modifications
The Rocket Boomer L2 C drillrig was
fitted with Atlas Copco’s ABC Regular
control package, which indicates the hole
positions, but does not include full-function
automatic boom movement.
The contractor has had experience using
a computerized Rocket Boomer XL3 C on
the Norwegian mainland, but it was still a
major decision to send an RCS drillrig to a reliability was good, and only the usual Rockbolts and shotcrete provide the
remote location like Spitsbergen. During service parts such as filters and hoses were main support.
commissioning, Atlas Copco provided required.
three or four days of basic training at site The SNSK mine also has an Atlas
to the new operators. The instructor then Copco Swell bolter, originally supplied in
remained in support for another three 1986. This rig was rebuilt in 2001 and
weeks, and returned some months later for equipped with the new HBU bolting unit
a week of follow-up training. The contrac- with a COP 1028 hydraulic rock drill. This
tor has taken care of maintenance and bolting unit is used in parts of the mine
operation of the rig during the entire pro- with hard sandstone layers, where rotary
ject using his own people, without the need drilling cannot be used.
of outside assistance. Svea North’s future looks good. The
In the transition zone between the per- mine has a projected life until 2013, and
mafrost and the rock, it was found that the there are another two deposits of 3.5
conventional anti-jamming system fitted to and 2.7 million t nearby that SNSK may
the drillrig did not give sufficient warning wish to develop. The company is also car-
of jamming, resulting in some rod damage. rying out exploration work elsewhere on
Atlas Copco suggested an alternative pro- Spitzbergen. ■
gram, which suited the conditions better by
simultaneously monitoring rotation, feed Acknowledgements
rate and water flow. This resolved the
problem, and there were no more instances Atlas Copco is grateful to SNSK and LNS
of rod damage caused by jamming. for permission to publish this article,
By agreement with LNS, Atlas Copco which is derived from a site report written
evolved a package of spares suited to the by Mike Woof, editor of World Mining
remoteness of the operation. However, Equipment magazine.
FACE DRILLING 45