Name of Project : Improvement of Fish Pond

Location : Provincial Nursery, Bansalan, Davao del Sur


Subject : Bill of Quantities and Materials

Subject -

Manpower Requirement
Manpower No. of Gang Qty. Required Manpower Output (sq.m./man-day)
10.00 Laborers 1 4,042.00 300

A. Manpower
Quantity Description
10.00 Laborers

B. Materials
Quantity Unit Description

C. Equipment
Quantity Unit Description
Quantity: 4,042.00 sq.m

Activity Duration
ower Output (sq.m./man-day)
(days)
300 14

No. of Days Unit Cost Amount


14 436.80 61,152.00
Sub-Total Php 61,152.00

Description Unit Cost Amount

Sub-Total Php

on No. of Days Unit Cost Amount


-
Sub-Total Php -

D. DIRECT COST (A+B+C) Php 61,152.00

E. OCM 15% of Direct Cost 9,172.80


F. CP 10% of Direct Cost 6,115.20
G VAT 5% (DC + OCM + CP) 3,822.00
H INDIRECT COST (E + F + G) Php 19,110.00

I. TOTAL ITEM COST (D + H) Php 80,262.00


J. UNIT COST / sq.m Php 19.86

You might also like