WO#40 SEPARATE
SEPARA DEDICATED NITROGEN HEADER AT MAA REFINERY 91 29-Jul-19 11-Nov-19
GENERAL ACTIVTIES
AC 0
INITIATION 0
MOBILIZATION 0
SUBMISSIONS OF DOCUMENT 0
METHOD STATEMENTS
STAT & PROCEDURES 0
PAINTING & B
BLASTING PROCEDURE 0
WPS 0
ITP 0
HYDROTEST P PROCEDURE 0
PROCUREMENT
PROCUREME 20 09-Sep-19 01-Oct-19
MECHANICAL ITEMS
I 0
PIPE & FITTINGS
FITTIN 0
CS LINE 4"
4",SCH 40 (2439 M) 0
CS LINE 3" SCH 40 (732 M) 0
CS LINE 2" SCH 40 (86 M) 0
CS LINE 1" SCH 80 ( 250 M) 0
INSTRUMENTATION MATERIAL
INSTRUMENTA 20 09-Sep-19 01-Oct-19
CONTROL CABLES
CAB 0
CONTROL VALVE
VAL ( 1 NO) 20 09-Sep-19 01-Oct-19
P3080 Delivery & Inspection at Site 20 09-Sep-19 01-Oct-19
PRESSURE TRANSMITTER
TR 0
CIVIL ITEMS 0
GENERAL CONSTRUCTION
CO MATERIAL 0
ELECTRICAL ITEMS
IT 0
CONSTRUCTION
CONSTRUCTI 73 29-Jul-19 21-Oct-19