WO#40 SEPARATE DEDICATED NITROGEN HEADER AT MAA REFINERY

Activity ID Activity Name Original Start Finish 2019 2020


Duration
Aug Sep Oct N Dec Jan F

WO#40 SEPARATE
SE DEDICATED NITROGEN HEADER AT MAA REFINERY 144 01-Sep-19 A 15-Feb-20

MILESTONES
MILESTON 0 15-Feb-20 15-Feb-20

MS155 Work Order Completion 0 15-Feb-20

GENERAL ACTIVTIES 0

INITIATION 0
MOBILIZATIO
MOBILIZATION 0
SUBMISSIONS OF DOCUMENT
SUBMISSION 0
METHOD STATEMENTS
STA & PROCEDURES 0
PAINTING & B
BLASTING PROCEDURE 0
WPS 0
ITP 0
HYDROTEST PROCEDURE 0
PROCUREMENT
PROCURE 20 27-Nov-19 21-Dec-19

MECHANICAL ITEMS
MECHANICA 0
PIPE & FITTINGS
FITTIN 0
CS LINE 4",SCH
4",S 40 (2439 M) 0
CS LINE 3" S
SCH 40 (732 M) 0
CS LINE 2" S
SCH 40 (86 M) 0
CS LINE 1" SCH
S 80 ( 250 M) 0
INSTRUMENTATION MATERIAL
INSTRUMEN 20 27-Nov-19 21-Dec-19
CONTROL CABLES
CA 0
CONTROL VALVE
VA ( 1 NO) 20 27-Nov-19 21-Dec-19
PR3080 Delivery & Inspection at Site 20 27-Nov-19 21-Dec-19
PRESSURE TRANSMITTER
T 0
CIVIL ITEMS 0
GENERAL CONSTRUCTION
CO MATERIAL 0
ELECTRICAL ITEMS 0

CONSTRUCTION
CONSTRU 112 01-Sep-19 A 08-Jan-20

MECHANICAL
MECHANICA 103 01-Sep-19 A 29-Dec-19
U-71 GROUND LEVEL 0
TIE IN 0
U-71 57 01-Sep-19 A 05-Nov-19
Near Unit 80 57 01-Sep-19 A 05-Nov-19
CON2270 Scaffolding 21 01-Sep-19 A 08-Oct-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 2
30-Sep- Updated Schedule
Actual Work Critical Remainin...
WO#40 SEPARATE DEDICATED NITROGEN HEADER AT MAA REFINERY
Activity ID Activity Name Original Start Finish 2019 2020
Duration
Aug Sep Oct N Dec Jan F
CON2350 Rigging 7 21-Sep-19 A 12-Oct-19
CON2280 Fit-up and Welding 21 13-Oct-19 05-Nov-19
Near Unit 56 0
U-26 0
U-25 0
U-05 45 09-Oct-19 30-Nov-19
CON1880 Erection of scaffolding 21 09-Oct-19 02-Nov-19
CON2360 Rigging 7 29-Oct-19 05-Nov-19
CON1910 Fit-up & welding of field joints 21 06-Nov-19 30-Nov-19
U-98 0
U-58 49 03-Nov-19 29-Dec-19
CON1210 Erection of scaffolding 21 03-Nov-19 26-Nov-19
CON2370 Rigging 10 19-Nov-19 30-Nov-19
CON1240 Fit-up & welding of field joints 25 01-Dec-19 29-Dec-19
E&I 37 27-Nov-19 08-Jan-20
CON2310 Scaffolding 10 27-Nov-19 08-Dec-19
CON2320 Tube bending & cable pulling 10 09-Dec-19 19-Dec-19
CON2060 Installation of control valve 3 21-Dec-19 23-Dec-19
CON2070 Termination Testing & commissioning of Instruments 15 23-Dec-19 08-Jan-20
SHUTDOWN MECHANICAL ( Tie In )
SHUTDOW 10 30-Dec-19 09-Jan-20

SD2390 Unit (25,26,5,58,98 & 71) shutdown to be determined 10 30-Dec-19 09-Jan-20

COMPLETION & HANDOVER


COMPLET 34 06-Jan-20 15-Feb-20
COMP100 Closure of Punch Points 30 06-Jan-20 05-Feb-20
COMP2330 Radiography Testing 10 11-Jan-20 21-Jan-20
COMP2340 Hydrotest 10 22-Jan-20 02-Feb-20
COMM2380 Commissioning 10 03-Feb-20 13-Feb-20
COMP110 As built and finals issue of documents 10 05-Feb-20 15-Feb-20

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 2 of 2
30-Sep- Updated Schedule
Actual Work Critical Remainin...