Professional Documents
Culture Documents
Pipe Flushing and Inspection
Pipe Flushing and Inspection
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5002 REV.0 DATE:20-06-19 Page 1 of 8
LIMITED
LY
N
O
E
S
O
SPECIFICATION FOR INSPECTION, FLUSHING AND
P
TESTING OF PIPING
R
U
P
R
E
D
N
E
T
R
FO
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5002 REV.0 DATE:20-06-19 Page 2 of 8
LIMITED
TABLE OF CONTENTS
4.0 TESTING............................................................................................................................... 4
LY
4.1 Extent of Testing ................................................................................................................. 4
N
O
4.2 General Requirements / Test Preparation for Testing ...................................................... 5
E
4.3 Testing Media, Test Pressure and Test Pressure Gauges................................................ 6
S
O
4.4 Testing Procedure ............................................................................................................... 7
P
R
U
P
R
E
D
N
E
T
R
FO
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5002 REV.0 DATE:20-06-19 Page 3 of 8
LIMITED
1.0 SCOPE
This specification covers the general requirements for inspection, flushing and testing of
piping systems.
Flushing and testing of all piping systems shall be witnessed by the Engineer-in Charge.
2.0 INSPECTION
During various stages and after completion of fabrication and erection, the piping system
shall be inspected by the Engineer-in-charge to ensure that:-
LY
Ø Proper piping material has been used.
N
Ø Piping has been erected as per drawings and instructions of Engineer-in-Charge.
O
Ø All supports have been installed, correctly as per the pipe support index and
E
instructions of Engineer-in-Charge.
Ø
S
Test preparations mentioned in this specification have been carried out.
O
P
3.0 FLUSHING
R
Flushing shall be done by fresh potable water or dry compressed air, wherever water
flushing is not desirable, to clean the pipe of all dirt, debris or loose foreign material.
R
E
In line instruments like control valves, orifice plates, rotameters, safety valves and other
D
instruments like thermo wells which may interfere with flushing instrument shall not be
N
Required pressure for water flushing shall meet the fire hydrant pressure or utility water
T
pressure.
R
For air flushing the line / system will be pressurized by compressed air at the required
FO
pressure but to a maximum of 50 psig. The pressure shall then be released by quick
opening of a valve, already in line or installed temporarily for this purpose. This procedure
shall be repeated as many times till inside of the pipe are fully cleaned.
During flushing temporary strainers shall be retained. These shall be removed, cleaned
and reinstalled after flushing but before testing.
From all permanent strainers the screens / meshes shall be removed before flushing.
Screen / meshes shall be reinstalled after flushing out and before testing.
In case equipment such as column, vessel, exchanger etc. forms part of a piping circuit
during flushing, this shall be done with the approval of Engineer-in-Charge. However
equipments thus included in the circuit, shall be completely drained and dried with
compressed air, after flushing is completed.
During flushing discharged water / air shall be drained to the places directed by the
Engineer-in-Charge. If necessary, proper temporary drainage shall be provided by the
contractor.
The contractor shall carry out all the activities required before, during and after the flushing
operation, arising because of flushing requirements, such as but not limited to the
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5002 REV.0 DATE:20-06-19 Page 4 of 8
LIMITED
following:
Dropping of valves, specials, distance pieces, inline instruments and any other piping parts
as may be necessary before flushing. The flanges to be disengaged for this purpose shall
be envisaged by the contractor and approved by the Engineer-in-Charge. These flanges
shall be provided with temporary gaskets at the time of flushing.
Care shall be taken during flushing so as not to damage / spoil work of other agencies.
Precautions shall also be taken to prevent entry of water, foreign matter into equipments,
electric motors, instruments electrical installations etc.in the vicinity of lines being flushed.
LY
Records in triplicate shall be prepared and submitted by the contractor for each piping
N
system for the flushing done.
O
4.0 TESTING
E
4.1 Extent of Testing:-
S
O
With the exclusion of instrumentation, piping systems fabricated or assembled in the field
P
shall be tested irrespective of whether or not they have been pressure tested prior to site
R
welding of fabrication.
U
To facilitate the testing of piping systems, vessels and other equipments may be included
P
in the system with the prior approval of Engineer-in-Charge if the test pressure specified is
R
equal to or less than that for the vessels and other equipments.
E
Pumps, compressors and other rotary equipments shall not be subjected to field test
D
pressure.
N
E
Lines which are directly open to atmosphere such as vents, drains, safety valves
T
discharge need not be pressure tested, but all joints shall be visually inspected. Such line
shall be tested by continuous flow of fluid to eliminate the possibility of blockade.
R
However, such lines if provided with block valve shall be pressure tested up to the first
FO
block valve.
Seats of all valves shall not be subjected to a pressure in excess of the maximum cold
working pressure of the valve. Test pressure applied to valves shall not be greater than
the manufacturer’s recommendation nor less than that required by the applicable code.
Where allowable seat pressure is less than test pressure, test shall be made through an
open valve.
Instruments in the system to be tested shall be excluded from the test by isolation or
removals, unless approved otherwise by the Engineer-in-Charge.
Restrictions, which interfere with filling, venting and draining such as orifice plates etc.
shall not be installed unless testing is complete.
Control valves shall not be included in the test system. Where bypasses are provided test
shall be performed through the bypass end / or necessary spool shall be used in place of
control valve.
Pressure gauges, which are part of the finished system, but cannot withstand test pressure
shall not be installed until the system has been tested. Where piping systems to be tested
are directly connected at the battery limits to piping for which the responsibility rests with
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5002 REV.0 DATE:20-06-19 Page 5 of 8
LIMITED
other agencies, the piping to be tested shall be isolated from such piping by physical
disconnection such as valve or blinds.
4.2 General Requirements / Test Preparation for Testing:-
Testing shall be carried out with permanent gaskets installed unless specified otherwise or
instructed by the Engineer-in-Charge.
No pressure test shall be carried out against close valve unless approved by the Engineer-
in-Charge.
LY
The Engineer-in-Charge shall be notified in advance by the contractor of the testing
sequence and programme, to enable him to be present for witnessing the test.
N
O
Before testing, all piping shall be cleaned by flushing to make it free from dirt, loose scale,
debris and other loose foreign materials.
E
S
All piping systems to be hydrostatically tested shall be vented at the high points and the
O
systems purged of air before the test pressure is applied.
P
Wherever in the line any void is existing due to any reasons, for absence of control valves,
R
safety valves, check valves etc. it shall be filled with temporary spools.
U
All joints welded, screwed or flanged shall be left exposed for examination during the test.
P
Before pressurizing the lines, each weld joints shall be cleaned by wire brush to free it from
R
between the companion flanges. Minimum thickness of the blank shall be designed in
N
Open ends of piping system where blanks cannot be used, such as pumps, compressors,
turbines or whenever equipment or pipe spool have been recovered or disconnected prior
R
to hydrostatic testing, shall be blinded-off by using standard blind flanges of same rating as
FO
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5002 REV.0 DATE:20-06-19 Page 6 of 8
LIMITED
Gas lines when hydrostatically tested shall be provided with additional temporary supports
during testing as directed by the Engineer-in-Charge.
Piping which is spring or counter – weight supported shall be temporarily supported, where
the weight of the fluid would overload the support. Retaining pins for spring supports shall
be removed only after testing is completed and test fluid is completely drained.
When testing any piping system, air or steam of approximately 2 Kg / Sq. cm (g) may be
used as preliminary test to detect missing gaskets etc. as this avoids the necessity of
draining the line to make repairs. However, steam shall not be used for this purpose, if the
LY
steam temperature is more than the design temperature of the line.
N
For jacketed pipes, testing of core pipes shall be done on individual pieces before welding
O
the closure joint of the outer jacket. The outer jacket shall be tested separately as
separate continuous system.
E
S
4.3 Testing Media, Test Pressure and Test Pressure Gauges:-
O
4.3.1 Testing Media:-
P
In general all pressure tests shall be hydrostatic using Iron free water, which is clean and
R
free of silt. Maximum Chlorine content in water for hydrostatic testing for SS piping shall be
U
10 – 20 ppm.
P
Air shall be used for testing only if water would cause corrosion of the system or
R
Where air / water test are undesirable substitute fluid such as gas, oil, kerosene, methanol
N
etc. shall be used as the testing medium, with due consideration to the hazards involved.
E
These test fluids shall be specified in the line list given to the contractor.
T
The hydrostatic / pneumatic test pressure shall be as indicated in the line list or as per the
FO
instruction of Engineer-in-Charge.
The selection of the piping system for one individual test shall be based on the following:
Test pressure required as per line list.
Maximum allowable pressure for the material of construction of piping.
Depending upon the above requirements and based on construction progress, maximum
length of piping shall be included in each test.
4.3.3 Test Pressure Gauge:-
All gauges used for field-testing shall have suitable range so that the test pressure of the
various systems falls in 40% to 80% of gauge scale range. Gauge shall be of a good
quality and in first class working condition.
Prior to the start of any test or periodically during the field test program, all test gauges
shall be calibrated using a standard dead weight gauge tester or other suitable approved
testing apparatus. Any gauge showing an incorrect zero reading or error of more than
± 2% of full-scale range shall be discarded. The Engineer-in-Charge shall check the
accuracy of master pressure gauge used for calibration.
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5002 REV.0 DATE:20-06-19 Page 7 of 8
LIMITED
LY
Engineer-in-Charge.
Pressure shall be applied by means of suitable test pump or other pressure source which
N
shall be isolated from the system as soon as test pressure is reached and stabilized.
O
A pressure gauge shall be provided at the pump discharge for guidance in bringing the
E
system to the required pressure.
S
O
The pump shall be attended constantly during the test by an authorized person. The pump
shall be isolated from the system whenever the pump is to be left unattended.
P
R
Test pressure shall be maintained for a sufficient length of time to permit through
U
inspection of all joints for leakage or signs of failure. Any joint found leaking during a
P
pressure test should be retested to the specified pressure after repair. Test period shall be
maintained for a minimum of three hours.
R
E
The pumps and the piping system to be tested are to be provided with separate pressure
D
indicating test gauges. These gauges are to be checked by the standard test gauge
N
Care shall be taken to avoid increase in the pressure due to temperature variation during
T
the test.
R
When testing with air, pressure shall be supplied by means of a compressor. The
compressor shall be portable type with receiver, after cooler and oil separator.
Piping to be tested by air shall have joints covered with a soap and water solution so that
the joints can be examined for leaks.
All other details shall be same as per hydro testing procedure (specified above).
4.5 Completion of Testing:-
After the hydrostatic test has been completed, pressure shall be released in a manner and
at a rate so as not to endanger personnel or damage equipments.
All vents and drains shall be opened before the system is to be drained and shall remain
open till all draining is complete, so as to prevent formation of vacuum in the system. After
draining, lines / systems shall be dried by air.
After testing is completed the test blinds shall be removed and equipment / piping isolated
during testing shall be connected using the specified gaskets, bolts and nuts. This
connection shall be checked for lightness in subsequent pneumatic tests to be carried out
by the contractor for complete loop / circuit including equipments (except rotary
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5002 REV.0 DATE:20-06-19 Page 8 of 8
LIMITED
equipments).
Pressure test shall be considered complete only after approval by the Engineer-in Charge.
Defects, if any, noticed during testing shall be rectified immediately and retesting of the
system / line shall be done by the contractor at his cost.
4.6 Test Records:-
Records in quadruplicate shall be prepared and submitted by the contractor for each piping
system, for the pressure test done.
LY
N
O
E
S
O
P
R
U
P
R
E
D
N
E
T
R
FO
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5004 REV.0 DATE:20-06-19 Page 1 of 51
LIMITED
LY
N
O
E
S
O
P
R
OIL INDIA
JPEC DOC.NO.:FGGS-BJN-PIP-SPC-5004 REV.0 DATE:20-06-19 Page 2 of 51
LIMITED
TABLE OF CONTENTS
2.0 SCOPE............................................................................................................................3
LY
4.0 EQUIPMENT ...................................................................................................................6
N
5.0 SURFACE PREPARATION, SHOP PRIMER / COATING APPLICATION, REPAIR AND
O
DOCUMENTATION.........................................................................................................6
E
S
6.0 PAINT MATERIALS ......................................................................................................14
O
P
7.0 COATING SYSTEMS ....................................................................................................19
R
13.0 GUARANTEE................................................................................................................51
FO